SAP Project System
Material
Non-Stock
Receive to own Premises
Process Flow
Scenario | Control Key (in PS) | Account Assignment (in PR/PO) | Item Category (in PR/PO) | To Complete the PO | Special Stock Indicator in MM Inventory | Goods Issue |
External Activity | PS02 | F | Blank | MIGO | N/A | N/A |
External Service | PS05 | F | D | ML81N | N/A | N/A |
| Item Category (in PS) | | | | | |
Non-Stock | N | F | Blank | MIGO | N/A | N/A |
3rd Party | N | F | S | MIGO | N/A | N/A |
w/o MRP | L | Q | Blank | MIGO | Q | GI “Q” stock |
with MRP | L | Q | Blank | MIGO | Q | GI “Q” stock |
Copy from E-1203A to create new Material M2000
This estimated price will go to the PR
Create Info Record for the Material M2000
Info Record Price will goto the PO
Enter Material M2000
Enter Item Category “N”
Scenario | Item Category (in PS) | Account Assignment (in PR/PO) | Item Category (in PR/PO) | To Complete the PO | Special Stock Indicator in MM Inventory | Goods Issue |
Non-Stock | N | F | Blank | MIGO | N/A | N/A |
BLANK the Procurement Type field and press ENTER
Select “PR for Network” then OK
Enter “1” and press ENTER
Estimated Price from Material Master Accounting Data View
Note some data from Material Master Purchasing Data view
Check the Non-Stock PR
Scenario | Item Category (in PS) | Account Assignment (in PR/PO) | Item Category (in PR/PO) | To Complete the PO | Special Stock Indicator in MM Inventory | Goods Issue |
Non-Stock | N | F | Blank | MIGO | N/A | N/A |
Click to select the PR item and then select “Assign Automatically” to perform Source Determination
Notice Info Record picked up by the system
Click here and then the “Process Assignment “ button
Scenario | Item Category (in PS) | Account Assignment (in PR/PO) | Item Category (in PR/PO) | To Complete the PO | Special Stock Indicator in MM Inventory | Goods Issue |
Non-Stock | N | F | Blank | MIGO | N/A | N/A |
Note PO #
Note PO# in CJ20N for the Material Non-Stock
GR to Non-Stock PO
Material Document Created
Debit Expenses
Credit Accrual
Cost charged to Project