1 of 12

IPL Generation Plan

Presented on ??

2022

1

1/18/2022

2 of 12

Independence and SPP

  • SPP coordinates all generation and transmission service within the region.
  • SPP schedules generation resources to protect the stability of the grid and meet the energy needs of the entire region
  • Independence purchases all energy consumed from SPP
  • Independence is obligated to maintain generation assets capable of producing our maximum demand plus a reserve margin
  • SPP credits Independence for any energy produced by Independence’s generation assets.

2

1/18/2022

3 of 12

IPL Resource Portfolio (Accredited Capacity)

  • IPL CT’s 93.5 MW
  • Dogwood 80 MW
  • Iatan II 53 MW
  • Nebraska City II 57.6 MW
  • Smoky Hills 4 MW
  • Marshall Wind 6.7 MW
  • Oneta (Capacity) 45 MW
  • Solar Farms (2.9 MW) (reduces IPL demand)
  • Total Capacity 339.8 MW
  • Capacity Obligation 333.8 MW

3

1/18/2022

4 of 12

Capacity Timeline

  • Excess Capacity 2022 6 MW
  • IPL CTs TBD (-93.5)
  • Smoky Hills 2029 -4 MW -4 MW
  • Oneta 2030 -45 MW -49 MW
  • Marshall Wind 2036 -6.7 MW -55.7 MW
  • Solar 2042/2043 -2.9 MW -58.6 MW
  • Nebraska City II 2049 -57.6 MW -116.2 MW
  • Iatan II 2050 -53 MW -169.2 MW
  • Dogwood 2051 -80 MW -249.2 MW

4

1/18/2022

5 of 12

5

1/18/2022

6 of 12

Adding Additional Capacity

  • Capacity only contracts – ONETA
  • Power Purchase Agreements - adds capacity plus market opportunity for any energy generated
  • Ownership/Partnerships – Dogwood Energy
  • City owned generation

6

1/18/2022

7 of 12

Considerations

  • Timeline to design/build new assets
  • Location – remote assets also have an added cost for Transmission service
  • SPP Approval – engineering studies to determine the impact on the electric grid. Currently takes 4-5 years for new proposals plus mandatory cost share for any transmission improvements, 12-18 months for replacement of existing assets
  • FERC waiver – granted for use of the Blue Valley site, 36 month window to put something into operation
  • Market opportunity to offset costs
  • Developing technologies for Renewable Energy

7

1/18/2022

8 of 12

Annual Costs by Resource (3yr avg)

Cost Revenue Net Cost ($M) $/MW

  • IPL CT’s $4.73 Million $0.37 M 4.36 46K
  • Dogwood $9.32 Million $7.16M 2.16 27K
  • Iatan II $19.66 Million $7.69M 11.97 226K
  • Nebraska City II $15.23 Million $9.61M 5.62 97K
  • Smoky Hills $2.22 Million $0.87M 1.35 337K
  • Marshall Wind $2.48 Million $1.59M 0.89 133K
  • Oneta (Capacity) $1.25 Million $0.00 1.25 28K
  • Solar Farms $1.43 Million $0.58M 0.85 293K

8

1/18/2022

9 of 12

IPL Staff Recommendation

  • Multi-phased project to maintain the advantages of a diverse portfolio to meet our SPP capacity requirements
  • Initial investment for new generation located in Independence
  • Allow for strategic retirement of older assets and options for negotiating new/extended contracts
  • Develop proposals for addition of Renewable resources such as batteries to complement Wind/Solar within SPP
  • Allow time for continued technology improvements and clarification of regulatory environment

9

1/18/2022

10 of 12

Sustainability - Green Resource Initiatives

  • Continued Investment in Wind/Solar
  • Backfill Intermittent Green Technologies
    • Energy Storage Resources (Batteries) - 4hr
    • Current est. $1M/MW (NREL, Dept of Energy)
    • Peaking Resources > 4hr
      • Low-Carbon Resource Initiative (LCRI)
      • New Resource Capable of Burning 30% Hydrogen

10

1/18/2022

11 of 12

Resource Plans – Possible Future

Now - Gen Capable of Burning 30% Hydrogen (LCRI)

2024? – Sub J Retirement – Replace w/Battery 2027

2027? – Sub I Retirement

- Addition Wind Resource

- 2030 - Replace w/LCRI Gen

2029 – Renew/New Wind Contract

2030 – New Solar/Battery

2034 – Sub H Retirement

- 2037 - Replace w/LCRI Gen

11

1/18/2022

12 of 12

Questions ?

12

1/18/2022