I-5 South Connector Study
Four Creeks Neighborhood Association
January 21, 2026
1
1
Project Background & Issues
2
2
Project Timeline
Mid 2000’s
Connection between I-5 at SR 502 (NW 219th St added to County and City Plans
2019 – 2021
WSDOT Planning Grant Funded Study. Resulted in 7 alternatives. Included limited stakeholder engagement.
Other planning studies
2023
Petition for “purple” alternative received in July.
2025
City and County updating Comprehensive Plans
2026
NTP issued (1/16/26) for consultant to begin work on federal PL grant through RTC for this phase ($270K).
Anticipated duration: 18 months
3
3
Where to Find Past (and Current) Information
NOTE: reports from the previous planning study are now available on the Ridgefield Roundtable page:
4
4
Legislative Request
Purpose:
The I-5 South Connection project will improve regional mobility and accommodate existing and planned population and employment growth in the project area.
Need:
Purpose and Need
5
5
Alternative Analysis
6
6
MAP OF ALL ALTERNATIVES STUDIED
7
7
ANALYSIS OF I-5 SOUTH CONNECTION PRELIMINARY ROUTE CONCEPTS
Connection | Summary | Cost Estimate |
Pink | Is the shortest and most direct route; avoids steep land and does not cross additional ravines; has minimal impact to two private and one historic property. | $50–$55 million |
Blue | Follows the Pink Connection but is longer. Has minimal impact to historic property; impacts one nonresidential structure; avoids the two residential properties mentioned in the Pink Connection; requires an additional steep ravine to be crossed for construction. | $52–$57 million |
Orange | Follows the Pink Connection but diverges to the south to have no impact on the two residential properties mentioned in Pink Connection description; results in a longer route; has minimal impact to historic properties; avoids steep land and does not cross additional ravines. | $55–$60 million |
Yellow | Including improvements to NW 31st Avenue north to Hillhurst Road, this option is the longest and least direct route. Uses a portion of the existing roadway on NW 219th Street but is a more winding path to I-5; has minimal impact to private and historic properties; has greater environmental impacts because it crosses a fish-bearing stream immediately below an earthen dam and water body. | $57–$62 million |
Green | Creates an offset intersection along NW 31st Avenue; is longer than most other options, otherwise follows Pink Connection. | $50–$55 million |
Red | Almost exactly matches the Pink Connection but is offset to the south for about 1,500 feet to avoid filling the headwater of a second unnamed tributary of Gee Creek; has greater impact on an historic home and historic property (the neighboring farm indicated by the red circle on Figure 7); is the second shortest and most direct route; avoids steep land and does not cross additional ravines; has the least environmental impact. | $55–$60 million |
Purple | Creates an indirect route to I-5 using the existing NW Eklund Road and NW 11th Avenue roadways to connect to NW Carty Road, which will be improved in the future in a separate City project. To meet rural arterial standards, multiple curves would be redesigned and the intersections at NW Eklund Road and NW Carty Road would be improved. Private property would need to be acquired on either side of the roadway. | $90–$100 million total ($40–$45 is for Purple concept alignment. An additional $50–$55 million for the NW Carty Road project, which is a planned/unfunded City project currently included on the Capital Facilities Plan.) |
8
8
Next Steps
9
9
Next Steps
10
10
487 S. 56th Place | PO Box 608
Ridgefield, WA 98642
Miranda Lange, Deputy Director of Public Works
Direct: (360) 857-5022
11
11