1 of 11

I-5 South Connector Study

Four Creeks Neighborhood Association

January 21, 2026

1

1

2 of 11

Project Background & Issues

2

2

3 of 11

Project Timeline

Mid 2000’s

Connection between I-5 at SR 502 (NW 219th St added to County and City Plans

2019 – 2021

WSDOT Planning Grant Funded Study. Resulted in 7 alternatives. Included limited stakeholder engagement.

Other planning studies

  • 179th St Corridor
  • Ridgefield Transportation Plan (multiple LOS deficiencies in study area)

2023

Petition for “purple” alternative received in July.

2025

City and County updating Comprehensive Plans

2026

NTP issued (1/16/26) for consultant to begin work on federal PL grant through RTC for this phase ($270K).

Anticipated duration: 18 months

3

3

4 of 11

Where to Find Past (and Current) Information

    • I-5 South Connection Project Corridor Planning Study
    • 179th Street Corridor and Interchange long-term operational and simulation modeling
    • Future Travel Demand Modeling (County, RTC)
    • Traffic Impact Analyses and Forecasting for City’s Carty Road Subarea Plan and 2025-2045
    • Transportation Capital Facilities Plan Update

NOTE: reports from the previous planning study are now available on the Ridgefield Roundtable page:

https://ridgefieldroundtable.org/i5-south-connection

4

4

5 of 11

Legislative Request

Purpose:

The I-5 South Connection project will improve regional mobility and accommodate existing and planned population and employment growth in the project area.

Need:

    • Even with improvements, in the future:
      • 179th Street corridor and interchange will experience operational and queuing issues
      • Pioneer Street/ SR 501 corridor will experience congestion at I-5 interchange
    • Amphitheater and Fairgrounds event traffic and local traffic use the same interchange (179th Street)
    • Level of Service deficiencies will appear in short term along NW 209th Street and NW 31st Avenue
    • There is currently no I-5 access to/from land uses west of I-5 between 179th Street and Pioneer Street/ SR 501
    • There is no east-west corridor connecting Battle Ground/ SR 502 corridor to west County and south Ridgefield

Purpose and Need

5

5

6 of 11

Alternative Analysis

6

6

7 of 11

MAP OF ALL ALTERNATIVES STUDIED

7

7

8 of 11

ANALYSIS OF I-5 SOUTH CONNECTION PRELIMINARY ROUTE CONCEPTS

Connection

Summary

Cost Estimate

Pink

Is the shortest and most direct route; avoids steep land and does not cross additional ravines; has minimal impact to two private and one historic property.

$50–$55 million

Blue

Follows the Pink Connection but is longer. Has minimal impact to historic property; impacts one nonresidential structure; avoids the two residential properties mentioned in the Pink Connection; requires an additional steep ravine to be crossed for construction.

$52–$57 million

Orange

Follows the Pink Connection but diverges to the south to have no impact on the two residential properties mentioned in Pink Connection description; results in a longer route; has minimal impact to historic properties; avoids steep land and does not cross additional ravines.

$55–$60 million

Yellow

Including improvements to NW 31st Avenue north to Hillhurst Road, this option is the longest and least direct route. Uses a portion of the existing roadway on NW 219th Street but is a more winding path to I-5; has minimal impact to private and historic properties; has greater environmental impacts because it crosses a fish-bearing stream immediately below an earthen dam and water body.

$57–$62 million

Green

Creates an offset intersection along NW 31st Avenue; is longer than most other options, otherwise follows Pink Connection.

$50–$55 million

Red

Almost exactly matches the Pink Connection but is offset to the south for about 1,500 feet to avoid filling the headwater of a second unnamed tributary of Gee Creek; has greater impact on an historic home and historic property (the neighboring farm indicated by the red circle on Figure 7); is the second shortest and most direct route; avoids steep land and does not cross additional ravines; has the least environmental impact.

$55–$60 million

Purple

Creates an indirect route to I-5 using the existing NW Eklund Road and NW 11th Avenue roadways to connect to NW Carty Road, which will be improved in the future in a separate City project. To meet rural arterial standards, multiple curves would be redesigned and the intersections at NW Eklund Road and NW Carty Road would be improved. Private property would need to be acquired on either side of the roadway.

$90–$100 million total ($40–$45 is for Purple concept alignment. An additional $50–$55 million for the NW Carty Road project, which is a planned/unfunded City project currently included on the Capital Facilities Plan.)

8

8

9 of 11

Next Steps

9

9

10 of 11

Next Steps

    • Conducting a project kick-off meeting with the City, Clark County, WSDOT, and other agency partners
    • Developing a public involvement plan to include outreach activities.
    • Collecting traffic data and coordinating travel demand forecasts with the Southwest Washington Regional Transportation Council (RTC).
    • Developing future traffic volumes and analyzing roadway alternative alignments.
    • Conducting an initial evaluation of the “build” alternatives; assessing the potential environmental effects and benefits for each.

    • Key Tasks:
    • Refresh alternatives analysis;
    • Public involvement including consultation with agency partners and key stakeholders, public open houses.
    • Planning level (Tier I) NEPA and SEPA analysis for the locally preferred alternative.
    • Evaluation framework to assess the alternatives.
    • Concept development of the preliminary locally preferred alternative.
    • Draft and Final documentation of the Stage II study.

10

10

11 of 11

487 S. 56th Place | PO Box 608

Ridgefield, WA 98642

Miranda Lange, Deputy Director of Public Works

Direct: (360) 857-5022

11

11