1 of 10

    • Initial facility needs discussions
    • Admin/Board/Contractors involved

March 2021

    • Initial estimates of needs/wants
    • Overall budget deemed too high ($11.5M)

Spring/Summer 2021

    • Ongoing discussion on needs/budget

Calendar Year 2022

    • Needs vs. affordability discussions continued
    • Reduced project scope/cost

Early 2023

    • District initiates Design-Build process

Mid 2023

    • Public survey on facility needs completed

August 2023

    • Request for Proposals (RFP)
    • Ayars & Ayars hired for construction

Fall/Winter 2023

    • Bond election called for $8.75M

January 2024

    • Public bond information
    • Election Day-March 12th

Jan/Feb/Mar 2024

Process/Timeline

(3 years)

​

​

​