SAP Material Management
S/4Hana
LEAN Service
Configuration and Process steps
new Material type “SERV” in S/4 with:
for
LEAN Service Scenario
“SERV” assigned with Product Type Group “2” (designated the intended Material is for LEAN Service scenario)
Product Type Group “1” in S/4 will be for
Stocks and Consumables scenario
“SERV” applicable for Procurement via
LEAN Service FLOW
“SERV” also applicable for
Sales of Service via SD (like “DIEN”) but required appropriate Item Category Group
SAP default Standard Price for “SERV” but “MAP” is possible
SAP default only External Procurement for “SERV”
like “NLAG”,
no QTY and
no Value update
many data fields are hidden via this Field Reference
Field Reference “SERV”
HIDEs many fields
Field Reference “SERV”
HIDEs many fields
Field Reference “SERV”
HIDEs many fields
Copy “SERV” to new Material Type “ZS”
Target is Material type “ZS”, all parameter SAME
except set Pricing Control to be “MAP”.
new Material type “ZS” for LEAN Service is set with “MAP”
We want to simulate
Material type
“SERV” (with Standard Price)
“ZS” (with MAP Price)
for
LEAN Service Scenario
LEAN Service Material type (via Product Type Group “2”) only allow
Standard Price Control
We want to simulate
Material type
“SERV” (with Standard Price)
“ZS” (with MAP Price)
for
LEAN Service Scenario
(only Standard Price Control)
MM01 or the new ‘Manage Product Master Data”
FIORI App
to create Material Masters
Copy from another Material Master
Product Group = Material Group
Product Type = Material Type
Product Number = Material Master Number
These are CLIENT level data for the Material
In the Plant TAB, extend to Plant views
Enter the Plant code and
click “Apply”
Plant specific data can be entered now
To extend to the Accounting view
Valuation Area is for the Accounting data view
Valuation Area = Plant code
Enter Valuation Class
Enter the Price and click APPLY
click CHECK for Duplicate
click Create
If Duplicate found, system will show a
INFO Message
COPY Material
“SERVICE1”
to
“SERVICE2”
Plant choice to be copied to the new Material
Enter new Material
SERVICE2
Logistics and Accounting views extended to Plant 1010
choice to change the Logistics Plant data extended
Change the Standard Price
change price
from copied 50 to 100
SAVE
2 LEAN Service Materials created
click CREATE and select “Info Record”
All 4 types of Purchasing Info Record can be selected
Warning of Mandatory fields not filled-up
Can be from Service Material MRP2 view
Enter Manually the Standard Qty
Create Conditions
Note Condition Type PPR0 allowed at the moment in this App
Apply and CREATE
Info record for both Service Material
SERVICE1 50eur/hr
SERVICE2 100eur/hr
click CREATE and select “Source List”
Validity period
Supplier/Vendor
Pur.Organization
Enter SERVICE1
and Plant 1010
Copy/Generate/Create Source List functions
Source List created for the 2 LEAN Service Master
Source List is still accessible in ME01
Info record for both Service Material
SERVICE1 50eur/hr
SERVICE2 100eur/hr
and Source list for
SERVICE1
SERVICE2
click CREATE and there are 4 choices:
Cross Catalog can be created in FIORI platform
Enter the Service Material
SERVICE1
LEAN Service uses item Category “ “ (Std) and not “D”
Expected
Start date of period of Performance
End date of period of Performance
Release date is influenced by: Purchasing Processing time + Planned Delivery time + GR Processing time
From LEAN Service Material Accounting view
G/L Account Determination via Trx Event Key GBB (one of the factor is the Valuation Class in the LEAN Service Material Accounting view)
Select the
Info Record
One of the advantages of S/4 LEAN Service Material is available entry of a Service Performer
Service Performer ae available if they are created as BP and assigned as Service Performer to the BP Vendor
PR 10000307 created
before SAVE, added the SERVICE2 as second item
Whether it is FIORI App or ME52N, system Warning to enter a Service Performer
SAVE
Service Performer field HIDDEN in ME52N
Service Performer ae available if they are created as BP and assigned as Service Performer to the BP Vendor
Expected
Start date of period of Performance
End date of period of Performance
Release date is influenced by: Purchasing Processing time + Planned Delivery time + GR Processing time
Try to ADD a
LEAN Service Material in ME52N
Looks like LEAN Service Material with Product Type Group “2” is not supported in ME52N.
(but display or changes seemed OK)
ME51N cannot be used to create PR for LEAN Service Material.
ME52N can access PR for LEAN Service Material created via specific FIORI App (some changes is possible) BUT Insert a new PR item for LEAN Service Material is not possible.
ME53N can display PR for LEAN Service Material created via specific FIORI App.
Partial conversion not possible
PO created
PO created
GR Relevancy indicator
GR not possible for LEAN Service PO
ADD a Stock material to the LEAN Service PO using ME22N
In the same APP, the system detect at least one item in the PO relevant for MIGO
Only the PO item relevant for MIGO is included
ML81N also not relevant for LEAN Service PO
ADD “Manage Service Entry Sheet” FIORI App.
Search for “Manage Service Entry Sheet”
Enter Performance Period
Enter Hours
Before Approval, only the SES is created
Before Approval, only the SES is found in the PO History
After Approval, Material Document is created
After Approval, Material Document now is found in the PO History
click Box, and on dialogue,
select Material Documents Overview
click Box, and on dialogue,
select Manage Journal Entries
Debit Expenses
Credit GR/IR
Invoice Entry
Enter the PO with both LEAN Service and Stock Material
PO items both LEAN Service and Stock Material
Enter 160 and click CHECK
Logistics Invoice created
Follow-on Documents available
check the PO history
SES
SES Approval
Invoice created