SAP Project System

Using CATS to post

Activity Allocation

to WBS

2 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

3 of 38

Assign Cost Element 615000

Create new Activity Type 4421 (copy from 1421)

4 of 38

Note Cost Element 615000 is part of Value Category 615

5 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

6 of 38

7 of 38

$100 per Hour

8 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

9 of 38

Record CATs for Personnel 1940

(1920+##)

10 of 38

Use standard Data Entry Profile

1303

Personnel Number

1920 +##

User 20 is 1940

Click “Pencil”

11 of 38

E-99##-1-2 1 hour

E-99##-2-2 2 hour

E-99##-3-2 3 hour

Cost Center 4297

Activity Type 4421

12 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

13 of 38

Post to CO/PS

14 of 38

Personnel

1920+##

15 of 38

16 of 38

You can check this document in

KB23N

17 of 38

View CATA Postings

18 of 38

19 of 38

20 of 38

Note Cost Element 615000

Debit WBS

Credit Cost Center/Activity Type

21 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

22 of 38

23 of 38

24 of 38

E-9920-1-2 1 hr x $100 = $100

E-9920-2-2 2 hr x $100 = $200

E-9920-3-2 3 hr x $100 = $300

Total $600

25 of 38

click “Call Up Report”

26 of 38

27 of 38

PS Document

1 hour

28 of 38

Click Document

then

Manu

Extra - Follow-on documents

29 of 38

CO Doc

Access via KB23N

Double-click here also bring you to the CO Doc

30 of 38

CO Doc

PS Doc

31 of 38

  • Prepare Activity Type
  • Prepare Activity Rate
  • Record Time Sheet for Personnel
  • Cross-Application Posting
  • Check Cost Element Report
  • Check Hierarchy Cost Report

32 of 38

Hierarchical Cost Report

33 of 38

34 of 38

Note $100, $200, $300 posted to the respective WBS via CATA

35 of 38

Double-click

Value Category view

36 of 38

Cost Element 615000 was assigned to Value Category 615 in the IMG (OPI2)

37 of 38

Double-click

Business Trasanction view

38 of 38

$185 + $600