Scope of Works & Method

of Construction

6

Project Management & planning

3

Ambassadori

Batumi

Island

4

General

Information

Our Today’s Topics

1

About Us

2

Our projects

4 of 74

We have 22 years of experience in construction and engineering

Initially, we performed work as “Promer", however, since 2022, we continue to operate as

„FK Development“

The company has completed projects both in Georgia and abroad.

About Us

Now we are building the latgest investment project in the region:

“Ambassadori Batumi Island

5 of 74

Our projects

Among the projects implemented in Georgia are:

 

GIMG BATUMI HOTEL & RESORT

BATUMI PALACE OF JUSTICE

CASTLE OVER THE SEA HOTEL

GURJAANI HOUSE OF JUSTICE

KVALERI PALACE OF JUSTICE TRAINING CENTER

6 of 74

Projects implemented in Russia:

RAMSTORE SHOPPING CENTER

YUJNI SHOPPING CENTER

CITY CENTER II SHOPPING CENTER

7 of 74

Projects in Russia:

DOMO BUSINESS CENTER

ASTOR PLAZA

MEGA SHOPPING CENTER

PAKROVSKY HILLS

8 of 74

Projects implemented in Kazakhstan:

KARAGANDA

SHOPPING CENTER

GORYANA DOLINA ELITE HOUSES

KARAGANDA ELITE HOUSES

AKSAY SHOPPING CENTER

9 of 74

AMBASSADORI BATUMI ISLAND

FOR

10 of 74

11 of 74

THE ANCHOR

AMBASSADORI BATUMI ISLAND

Max. 2 NM

THE BATUMI

COMMERCIAL PORT

12 of 74

2021-11-04

2021-11-09

2021-11-09

project

13 of 74

2021-11-17

project

14 of 74

Our renders

15 of 74

16 of 74

17 of 74

18 of 74

19 of 74

20 of 74

UKSEL PROJE, ARUP

MASTER

PLANNER

AMBASSADORI BATUMI ISLAND

NAME OF THE PROJECT

FK Development LLC

General Constuction Contractor

21 of 74

Project phases

03

01

02

Arrangement of mobilization and embankment area

Filling the island with filler material by cathersection and hoppersection

Arrangement of the body of the island with building stone

22 of 74

23 of 74

24 of 74

METHOD OF CONSTRUCTION FOR BREAKWATERS

25 of 74

26 of 74

QUARRY RUN CORE

1- LOADING THE SPLIT DUMP BARGE THROUGH THE LOADING JETTY

2- POSITIONING THE SPLIT DUMP BARGE BY THE SURVEY TEAM

3- DUMPING THE MATERIAL AT PROPER LOCATION

SEA SIDE

-3.5

LEE SIDE

NATURAL SEA BED

QUARRY RUN PLACEMENT BY USE OF MARINE VESSELS

(SPLIT DUMP BARGE)

TOE

STAGE - 1

27 of 74

NATURAL SEA BED

SEA SIDE

STAGE - 2

LEE SIDE

1- LOADING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE THROUGH THE LOADING JETTY

2- POSITIONING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE BY THE SURVEY TEAM

3- DUMPING THE MATERIAL AT PROPER LOCATION

QUARRY RUN PLACEMENT BY USE OF MARINE VESSELS

(BACK-HOE EXCAVATORS EQUIPPED FLAT BARGES)

QUARRY RUN CORE

28 of 74

QUARRY RUN CORE

QUARRY RUN CORE

NATURAL SEA BED

NATURAL SEA BED

LEE SIDE

SEA SIDE

+3

+3

1- LOAD AND TRANSPORT THE 1-500Kg MATERIAL FROM STORAGE AREA BY TRUCKS

2- DUMP THE MATERIAL BY THE GUIDANCE OF RIGGERS OR FOREMEN

3- LEVEL THE MATERIAL BY THE GUIDANCE OF SURVEY TEAM USING DOZERS / LOADERS

QUARRY RUN PLACEMENT BY USE OF LAND EQUIPMENT

(TRUCKS, DOZERS, LOADERS)

STAGE - 3

29 of 74

NATURAL SEA BED

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

CREST WIDTH OF

QUARRY RUN

TOP VIEW

STAGE - 4

1- EXTEND THE CREST WIDTH FOR MINIMUM 6 METER BY DUMPING QUARRY MATERIAL AT THE LEE SIDE EVERY 150 METER

2- PRIOR TO COMPLETION OF BREAKWATER PROGRESS, POCKETS WILL BE REMOVED

QUARRY RUN PLACEMENT BY USE OF LAND EQUIPMENT (TRUCKS, DOZERS, LOADERS)

30 of 74

NATURAL SEA BED

QUARRY RUN

LEE SIDE

SEA SIDE

STAGE - 5

1- PREPARATION OF QUARRY RUN SLOPES, FOR THE FILTER STONE PLACEMENT BY USE OF LONG REACHED BOOM BACK-HOE EXCAVATORS

LEVELLING OF QUARRY RUN FILLING BY USE OF LAND EQUIPMENT (LONG REACHED BOOM BACK-HOE EXCAVATORS)

QUARRY RUN CORE

31 of 74

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

FİLTER

STONES

FILTER STONES

FILTER STONES

STAGE - 6

1- PLACEMENT OF FILTER STONE BY USE OF LONG REACHED BOOM BACK-HOE EXCAVATORS

2- LOADING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE THROUGH THE LOADING JETTY

3- POSITIONING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE BY THE SURVEY TEAM

4- DUMPING THE MATERIAL AT PROPER LOCATION

FILTER STONE PLACEMENT BY USE OF MARINE VESSELS & LAND EQUIPMENT (BACK-HOE EXCAVATORS MOUNTED FLAT BARGES, TRUCKS, DOZERS, LOADERS, LONG REACHED BOOM BACK-HOE EXCAVATORS)

32 of 74

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

GRAB

ARMOUR STONE

ARMOUR STONE

STAGE - 7

1- PLACEMENT OF FILTER STONE BY USE OF GRAB EQUIPPED LATTICE BOOM CRAWLER CRANE

2- LOADING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE THROUGH THE LOADING JETTY

3- POSITIONING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE BY THE SURVEY TEAM

4- DUMPING THE MATERIAL AT PROPER LOCATION

5- PLACEMENT OF ARMOUR STONE BY USE OF LONG REACHED BOOM BACK-HOE EXCAVATORS

ARMOUR STONE PLACEMENT BY USE OF MARINE VESSELS & LAND EQUIPMENT (BACK-HOE EXCAVATORS MOUNTED FLAT BARGES, FLAT BED TRAILERS, LOADERS, LONG REACHED BOOM BACK-HOE EXCAVATORS, CRAWLER CRANES)

33 of 74

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

ARMOUR

STONE

STAGE - 8

1- PLACEMENT OF ARMOUR & TOE STONES BY USE OF GRAB EQUIPPED LATTICE BOOM CRAWLER CRANE

2- LOADING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE THROUGH THE LOADING JETTY

3- POSITIONING THE BACK-HOE EXCAVATORS EQUIPPED FLAT BARGE BY THE SURVEY TEAM

4- DUMPING THE MATERIAL AT PROPER LOCATION

ARMOUR & TOE STONE PLACEMENT BY USE OF MARINE VESSELS & LAND QUIPMENT (BACK-HOE EXCAVATORS MOUNTED FLAT BARGES, FLAT BED TRAILERS, LOADERS, CRAWLER CRANES)

ARMOUR STONE

FOR TOE

34 of 74

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

STAGE - 9

1- RISING UP THE FILTER STONES OF THE SEA SIDE OF BREAK WATER BY USE OF BACK-HOE EXCAVATORS

2-RISING UP THE ARMOUR STONES OF THE SEA SIDE OF BREAK WATER BY USE OF BACK-HOE EXCAVATORS

3- CHECKING THE PLACEMENT LEVELS OF ARMOUR & TOE STONES, PRIOR THE PLACEMENT OF CONCRETE ARMOUR BLOCKS BY THE SURVEY TEAM WITH SOUNDING BASKET & ECHOSOUNDER

4- RECORD AND REPORT THE SURVEY RESULTS

5- INSPECTION BY THE DIVERS FOR ARMOUR & TOE STONES, PRIOR THE PLACEMENT OF CONCRETE ARMOUR BLOCKS

RISING UP THE ARMOUR STONES, PRIOR TO PLACEMENT OF CONCRETE ARMOUR BLOCKS BY USE OF BACK-HOE EXCAVATOR

35 of 74

NATURAL SEA BED

QUARRY RUN CORE

LEE SIDE

SEA SIDE

STAGE - 10

1- PLACEMENT OF ACCROPODE (CONCRETE ARMOUR BLOCKS) BY USE OF LATTICE BOOM CRAWLER CRANE (LAND OPERATION)

2- PLACEMENT OF ACCROPODES (CONCRETE ARMOUR BLOCKS) BY USE OF LATTICE BOOM CRAWLER CRANE MOUNTED FLAT BARGES (MARINE OPERATION)

3- DIVERS ARE THE TEAM MEMBER FOR MARINE OPERATIONS, INSPECTOR ONLY FOR LAND OPERATIONS

PLACEMENT OF ACCRAPODES (CONCRETE ARMOUR BLOCKS) BY USE OF MARINE VESSELS & LAND EQUIPMENT (LATTICE BOOM CRAWLER CRANES MOUNTED FLAT BARGES, LATTICE BOOM CRAWLER CRANES)

ACCROPODES

36 of 74

Dumping of The Core Material

Shaping of the Core and Side Slopes

Placement of the Armour Rocks

BREAKWATER

37 of 74

ROCK ARMOUR PLACEMENT

38 of 74

PLACING ARMOUR STONE WITH GRAB & BACKHOE

39 of 74

Breakwater

40 of 74

BREAKWATER CONSTRUCTION

41 of 74

42 of 74

ARTIFICIAL ARMOUR UNITS

43 of 74

ANTIFER INSTALLATION

44 of 74

TETRAPOD INSTALLATION

45 of 74

Placement of Corelocs

Posibloc System for Coreloc Placement

Underlayer is Ready to Place Coreloc

46 of 74

CORELOC INSTALLATION

47 of 74

CAB (Accrapode) installation by the means of GPS guided Posibloc or Echoscope”

48 of 74

RECLAMATION & REVETMENT WORKS, DREDGING & RECLAMATION WORKS

49 of 74

50 of 74

RAINBOWING by the means of TSHD

51 of 74

DREDGING & PUMPINGby the means of TSHD

52 of 74

DREDGING & RECLAMATION

53 of 74

METHOD OF CONSTRUCTION

FOR QUAY WALL

54 of 74

SCOUR PROTECTION

CONSTRUCTION METHOD OF QUAY WALL

NATURAL SEA BED

FIRST GROUP CONCRETE BLOCKS

SECOND GROUP CONCRETE BLOCKS

CAPPING BEAM

BACKFILL MATERIAL

ROCK FILL

ROCK FILL

GRAVEL BACKFILL

FİLTRE VE GEOTEKSTİL

MEAN SEA LEVEL

+ 2.50

FENDER

Geotextile & Blind Stone

QUARRY RUN CORE

PLACED WITH MARINE VESSELS

QUARRY RUN

TOE

QUARRY RUN CORE

PLACED WITH LAND VEHICLES

LEVELLED CRUSHED STONE

FILTER STONE

55 of 74

PRECAST YARD FOR CONCRETE QUAY WALL BLOCKS

56 of 74

SHUTTERING FOR CONCRETE BLOCKS OF QUAY WALL

57 of 74

STEAM CURING

58 of 74

STOCKED CONCRETE BLOCKS FOR QUAY WALL

59 of 74

TRANSPORTATION OF BLOCKS TO THE PLACEMENT AREA

60 of 74

PLACEMENT OF CONCRETE QUAY WALL BLOCKS

61 of 74

PLACEMENT OF CONCRETE QUAY WALL BLOCKS

62 of 74

63 of 74

64 of 74

UNDERWATER VIEW OF CONCRETE QUAY WALL BLOCKS

65 of 74

SURCHARGE FOR QUAY WALL

66 of 74

SHUTTERING FOR COPE BEAM

67 of 74

POURING OF CONCRETE WITH BUCKETS

68 of 74

FIRST PART OF COPE BEAM ACCOMPLISHED

69 of 74

QUAY WALL READY FOR BERTHING

70 of 74

LOADING-UNLOADING OF SHIPS

71 of 74

QUARRY

72 of 74

73 of 74

74 of 74