1.0 Station Wise Progress (Division level Details)
{Name of Division- Pune}
o
S. Name of
N Amrit Station
Sanctioned Cost (Rs in crore)
Executing Authority
Physical Progress (%)
Financial Progress (%)
Reasons for significant difference in physical and financial progress (if any )
TDC
Remarks
1
Kedgaon
12.55
CAO/C/RSP
100
99.3
Mismatch in physical and financial progress due to outstanding contractor invoices
Completed on –28.02.25
FOB- NA
2
Lonand
10.48
CAO/C/RSP
100
99.73
Completed on –
28.02.25
FOB- NA
3
Phaltan
0.92
CAO/C/RSP
100
99.00
Soft upgradation and COP work completed on 08.03.2025, 12m FOB: -NA
Phase-1 Work Completed
4
Baramati
11.40
CAO/C/RSP
100
99.00
SOFT- Completed on –
30.09.25
FOB- NA
5
Karad
12.51
CAO/C/RSP
100
99
Soft & COP: 30.09.2025 12m FOB: -NA
Phase-1 Work Completed
6
Wathar
7.97
CAO/C/RSP
100
99
Soft & COP: 30.09.2027 (TDC is
given for Proposed additional work)
3m FOB: - Being constructed by construction dept.
31.05.2028
Phase-1 Work Completed
7
Hadapsar
47.88
CAO/C/RSP
97
95
Soft works, FOB & Skywalk
Completed on :Nov.2025
Lift & ESC in circulating area for divyangjan compliance has been completed on 17.06.26, Lift on PF 1
30.09.26, Escalator on PF 2&3 - 30.09.2026
Inaugurated on 22.05.2025
Inaugurated on 22.05.2025
Inaugurated on 22.05.2025
1.0 Station Wise Progress (Division level Details)
{Name of Division- Pune}
S.No | Name of Amrit Station | Sanctione d Cost (Rs in crore) | Executing Authority | Physical Progress (%) | Financial Progress (%) | Reasons for significant difference in physical and financial progress (if any ) | TDC | Remarks |
8 | Talegaon | 40.34 | CAO/C/RSP | | | Mismatch in physical and | Soft: 30.09.2026 | |
| 63 | 52.8 | financial progress due to outstanding contractor | 06 m FOB :31.12.2026, Lift & ESC: 31.03.2027 | ||||
| | | | | | invoices | | |
9 | Kopargaon | 29.94 | CAO/C/RSP | | | Soft : 31.03.2027 | | |
| 88 | 46 | | 6 m FOB: - 31.12.2027, Lift & | ||||
| | | | | | | escalators - 31.03.2028 | |
10 | Belapur | 31.96 | CAO/C/RSP | 73 | 50 | | Soft: 31.08.2026 6 m FOB: - 31.03.2027 Lift & | |
| | | | | | | Escalator - 15.12.2027 | |
11 | Chinchwad | 20.44 | CAO/C/RSP | | | | Soft: 31.08.2026 | |
| | | | | | | Old FOB Extension | |
| | | | 80 | 74 | | :31.12.2026, Lift & ESC: | |
| | | | | | | 20.02.2027 | |
12 | Akurdi | 33.83 | CAO/C/RSP | 68 | 61 | | Soft: 30.09.2026 12m FOB: 31.12.2026 | |
| | | | | | | Escalator-15.03.2027 | |
13 | Ahmednagar | 30.92 | CAO/C/RSP | | | | Soft: 30.08.2026 | |
| | | | 87 | 57 | | 6 m FOB: - 31.12.2026 Lift & Escalator - 15.12.2027 | |
14 | Uruli | 19.79 | CAO/C/RSP | 73 | 64 | | Soft: 30.09.2026 12m FOB: - NA | |
| | | | | | | LIFT & ESC: NA |
1.0 Station Wise Progress (Division level Details)
{Name of Division- Pune}
S. No | Name of Amrit Station | Sanctioned Cost (Rs in crore) | Executing Authority | Physical Progres s (%) | Financial Progress (%) | Reasons for significant difference in physical and financial progress (if any ) | TDC | Remarks |
15 | Hathkanangle | 6.00 | CAO/C/RSP | | | Mismatch in physical and | Ramp & Soft: | |
| 99 | 98 | financial progress due to outstanding contractor | 31.03.2028 (TDC given for Proposed additional | ||||
| | | | | | invoices | work) | |
16 | Sangli | 24.20 | CAO/C/RSP | | | | Soft: 31.12.26 | |
| | | | | | | 12m FOB: 31.01.2027 | |
| | | | 83 | 80 | | LIFT & ESC - | |
| | | | | | | 30.09.2027 | |
17 | Kolhapur | 43.03 | CAO/C/RSP | | | | Soft : 31.10.2026 | |
| 66 | 52 | | 12m FOB: 31.12.2026 LIFT & Escalator – | ||||
| | | | | | | 30.06.2027 | |
18 | Dehu Road | 8.05 | CAO/C/RSP | | | | Soft & COP : | |
| 30 | 28 | | 31.03.2028 Lift & FOB: 31.03.2028 | ||||
19 | Satara | 34.31 | CAO/C/RSP | | | | Soft: 31.12.2026 | |
| | | | 63 | 61 | | 12m FOB: 31.01.2027 LIFT & ESC - | |
| | | | | | | 30.09.2027 | |
20 | Daund | 14.24 | CAO/C/RSP | 80 | 73 | | Soft: 31.03.2028 FOB: NA | |
1.1 Targeted Amrit Stations (Division level Details)
Name of Stations completed in all respect up to December 2025 | Name of Station targeted for completion (includes all sanctioned works) | Name of Station targeted for completion in 2026-27 (includes all sanctioned works) | Remarks | |||||
Jan 2026 (in all respect) | Jan 2026 (Without FOB/ Lift/ ramp) | Feb 2026 (in all respect ) | Feb 2026 (Without FOB/ Lift/ ramp) | March 2026 (in all respect) | March 2026 (Without FOB/ Lift/ ramp) | |||
Lonand Kedgaon Baramati Phaltan | | {include NAME of all stations including EPC contracts) | {includ e NAME of all station s includi ng EPC contrac ts) | {include NAME of all stations including EPC contracts ) | {include NAME of all stations including EPC contracts) | {include NAME of all stations including EPC contracts) | {include all stations including EPC contracts) Hadapsar Uruli Talegaon Chinchwad Akurdi | Name of Station targeted for completion in 2027-28 (includes all sanctioned works) Kolhapur, Sangli, Belapur Satara, Karad, Ahmednagar, Hatkanagle, Dehu Road, Daund, Wathar, Kopargaon and Name of Station targeted for completion in 2028-29 (includes all sanctioned works) |
{Count of Stations} 04 | {Count of Stations} 00 | {Count of Stations} 00 | {Count of Station s} 00 | {Count of Stations} 00 | {Count of Stations} 00 | {Count of Stations} 00 | {Count of Stations} 05 | Count of Stations} 11 |
{Name of Division- Pune }
1.2 Station Wise Review
(Division level Details)
S. No | Name of Amrit Station | Executing Authority | Last Weekly review by DRM | Last review by CE/SD | No. of Inspection by Multidisciplinary teams in last 3 months | Last Fortnightly review by AGM/GM | Details of Unresolved issues (if any) |
1 | Talegaon | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | 21.07.2026 | - |
2 | Akurdi | CAO/C/RS P | 27.07.2026 | 11.07.2026 | | - | |
3 | Dehu Road | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
4 | Chinchwad | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
5 | Hadapsar | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
6 | Uruli | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
7 | Kedgaon | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
8 | Baramati | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
9 | Lonand | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
10 | Wathar | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - |
{Name of Division- Pune}
1.2 Station Wise Review
(Division level Details)
S.N o | Name of Amrit Station | Executing Authority | Last Weekly review by DRM | Last review by CE/SD | No. of Inspection by Multidisciplinary teams in last 3 months | Last Fortnightly review by AGM/GM | Details of Unresolved issues (if any) |
11 | Satara | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | 21.07.2026 | - |
12 | Karad | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
13 | Sangli | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
14 | Hathkanangl e | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
15 | Kolhapur | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
16 | Phaltan | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
17 | Kopergaon | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
18 | Belapur | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
19 | Daund | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - | |
20 | Ahmednagar | CAO/C/RS P | 27.07.2026 | 22.06.2026 | | - |
{Name of Division- Pune}
1.3 Stations with pending Master Plan approval (Division level Details)
{Name of Division- Pune}
S. No | Name of Amrit Station | Executing Authority | Status of Master Planning | Division Approval status | Zonal HQ approval status | Tentative Cost of Works proposed (Rs. Cr.) | TDC for Master Plan approval | Remarks/ Issues for the delay |
1 | Talegaon | CAO/C/RSP | | Under Process | Under Process | 40.34 | 30.09.2026 | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please |
2 | Dehu Road | CAO/C/RSP | | Under Process | Under Process | 8.05 | 30.09.2026 | |
3 | Akurdi | CAO/C/RSP | | Under Process | Under Process | 33.83 | 30.09.2026 | |
4 | Chinchwad | CAO/C/RSP | | Under Process | Under Process | 20.44 | 30.09.2026 | |
5 | Hadapsar | CAO/C/RSP | | Under Process | Under Process | 22.86 | 30.09.2026 | |
6 | Uruli | CAO/C/RSP | | Under Process | Under Process | 12.86 | 30.09.2026 | |
7 | Kedgaon | CAO/C/RSP | | Under Process | Under Process | 12.55 | 30.09.2026 | |
8 | Baramati | CAO/C/RSP | | Under Process | Under Process | 11.40 | 30.09.2026 | |
9 | Lonand | CAO/C/RSP | | Under Process | Under Process | 10.48 | 30.09.2026 | |
10 | Wathar | CAO/C/RSP | | Under Process | Under Process | 7.97 | 30.09.2026 | |
11 | Satara | CAO/C/RSP | | Under Process | Under Process | 32.31 | 30.09.2026 | |
12 | Karad | CAO/C/RSP | | Under Process | Under Process | 12.51 | 30.09.2026 | |
13 | Sangli | CAO/C/RSP | | Under Process | Under Process | 24.20 | 30.09.2026 | |
14 | Hathkalangale | CAO/C/RSP | | Under Process | Under Process | 6.0 | 30.09.2026 | |
15 | Kolhapur | CAO/C/RSP | | Under Process | Under Process | 43.03 | 30.09.2026 | |
16 | Phaltan | CAO/C/RSP | | Under Process | Under Process | 0.76 | 30.09.2026 | |
17 | Kopergaon | CAO/C/RSP | | Under Process | Under Process | 29.94 | 30.09.2026 | |
18 | Belapur | CAO/C/RSP | | Under Process | Under Process | 31.96 | 30.09.2026 | |
19 | Ahmednagar | CAO/C/RSP | | | 26.06.2025 | 30.92 | | |
20 | Daund | CAO/C/RSP | | | 26.06.2025 | 14.24 | | |
Amrit Station Specific Details
{1. Talegaon}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 1
Talegaon}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 14.9306 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 1 Talegaon }
Updated Master Plan
2.3 Master Plan (Station specific details)
{Name of Station 1 Talegaon}
{Name of Station 1
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Talegaon}
2.5 Brief Scope of Works (Station specific details)
{Name of Station 1 Talegaon}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sq m) | TDC |
1 | {New Building/Improvement to | Improvement & New | 40.39 | 392.53 | 1418.83 | Sqm | Soft: |
| Bldg} | facility | | | | | 30.09.2026 06 m FOB |
2 | {Circulating Area} | Improvement & New facility | | 200 | 4992.7 | Sqm | :31.12.2026, |
| | | | | | Lift & ESC: | |
| 31.03.2027 | ||||||
3 | {FOB} | New facility | - | 1 | Nos | ||
4 | {PF Shelter} | Improvement & New facility | | 3228 | 8640 | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | 9630 | 8980 | sqm | |
6 | {Lift/Escalator} | New facility | | - | Lift: 03 | Nos | |
| | | | | Esc: 03 | | |
7 | {Furniture} | New facility | | - | - | | |
8 | {Art and Culture} | NA | | - | - | | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 163 | 711 | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 2.08 | PF NO. 1 – 1 No PF NO. 2 –1 Nos | Nos | |
| | | | | Waiting room Toiet- 1 No | | |
11 | {Development of Second | Improvement | | - | - | - | |
| Entry} | | | | | | |
2.6 Improvement of Existing Assets Being Retained (Station specific details)
Before Development
{Name of Station 1
Talegaon}
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 1
Talegaon}
Station Building Works
|
Portico |
|
Booking office |
|
Portico (Second Entry) |
|
Details of Activity (Night View) |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Talegaon}
FOB work
{Name of Station 1
FOB work
Details of Activity
Details of Activity
FOB Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 1
Talegaon}
Circulating Area/Parking Area
Circulating Area/Parking Area
Circulating Area/Parking Area Development
Add slide as per
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 1
PF Surfacing & PF Shelter
Talegaon}
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
{Name of Station 1
2.7 Completed/ Work in Progress Photos (Station specific details)
Talegaon}
Waiting Hall |
|
Waiting Hall |
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet PF 2
{Name of Station 1
Talegaon}
Toilet PF 2
Toilet PF 1
Toilet PF 1
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 1 Talegaon}
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 1 Talegaon}
Toilet
Booking office (Ramp)
Toilet (Ramp)
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 2 Akurdi}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 2
Akurdi}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 5.6077 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 2 Akurdi }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 2 Akurdi}
2.4 Status of Plans/ Drawings Approval (Station specific details)
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 2 Akurdi}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Akurdi}
Before Development
{Name of Station 2
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 2 Akurdi}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility ( Area) | Developed New Facility including Existing (Area) | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement &New facility | 33.83 | 386 | 752.48 Sqm | Sqm | Soft: 30.09.2026 12m FOB: 31.12.2026 Escalator-15.03.2027 |
2 | {Circulating Area} | Improvement &New facility | | 460 | 4986.45 Sqm | Sqm | |
3 | {FOB} | New facility | | - | 1 | Nos | |
4 | {PF Shelter} | Improvement &New facility | | 1024 | 2741.08 Sqm | Sqm | |
5 | {PF Surfacing} | Improvement &New facility | | 4200 | 6511.17 Sqm | Sqm | |
6 | {Lift/Escalator} | New facility | | Lift: 02 | Lift: NA Esc: 04 | Nos | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | - | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement &New facility | | NA | 315.25 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement &New facility | | 02 no | PF 1 : 02 PF 2: 01 | Nos | |
11 | {Development of Second Entry} | Improvement | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 2 Akurdi}
Station Building Works
|
Station Building Works |
|
Station Building Works |
|
Station Building Works |
|
Station Building Works |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Akurdi}
FOB
{Name of Station 2
FOB Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 2
Akurdi}
Circulating Area/Parking Area Development
Add slide as per
|
Parking Area (LHS Side) |
|
Circulating Area (RHS Side) |
|
Parking Area (LHS Side) |
|
Circulating Area (RHS Side) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
PF Surfacing & PF Shelter
{Name of Station 2
Akurdi}
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter (Night View)
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 2
Akurdi}
|
LHS- Waiting Hall |
|
LHS- Waiting Hall |
|
RHS- Waiting Hall |
|
RHS- Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 2 Akurdi}
Toilet
Toilet
Toilet
Toilet
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 2 Akurdi}
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 2 Akurdi}
Toilet
Toilet
Toilet
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 3. Dehu Road}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station
3.Dehu Road}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 15.6566 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 3. Dehu Road}
Updated Master Plan
2.3 Master Plan (Station specific details)
{Name of Station 3. Dehu Road}
2.4 Status of Plans/ Drawings Approval (Station specific details)
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 3. Dehu Road}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
{Name of Station 3.
Dehu Road }
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 3. Dehu Road}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New facility | 8.05 | - | 752.48 Sqm | Sqm | Soft & COP : 31.03.2028 FOB: NA |
2 | {Circulating Area} | Improvement & New facility | - | 4986.45 Sqm | Sqm | ||
3 | {FOB} | Planned in Phase- II | - | 1 | Nos | ||
4 | {PF Shelter} | Improvement & New facility | 2160 | 2741.08 Sqm | Sqm | ||
5 | {PF Surfacing} | Improvement & New facility | 6600 | 6511.17 Sqm | Sqm | ||
6 | {Lift/Escalator} | NA | - | NA | NA | ||
7 | {Furniture} | New Facility | - | - | - | ||
8 | {Art and Culture} | NA | - | - | - | ||
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | 64 | 0 | Sqm | ||
10 | {Toilet (New/ Renovation)} | Improvement & New facility | 30.4 | PF 1 : 01 PF 2: 01 | Nos | ||
11 | {Development of Second Entry} | Improvement | - | - | - |
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 3. Dehu Road}
Station Building Works
Add slide as per applicability
|
Downside booking office |
|
Upside Booking office |
|
DN Side approach road with parking area |
|
Downside booking office |
2.7 Completed/ Work in Progress Photos (Station specific details)
Platform Up-gradation
{Name of Station 3
Dehu Road}
Platform Up-gradation
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
Platform Up-gradation |
|
Platform Up-gradation |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 3 Dehu
Road}
Toilet
Add slide as per
|
Toilet |
|
Toilet |
|
Toilet |
|
Toilet |
applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 3 Dehu Road}
Amrit Station Specific Details
{Name of Amrit Station 2. Chinchwad}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 4
Chinchwad }
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1. | Construction of balance work under ABSS in Pune Division. | 13.7414 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 4 Chinchwad }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 4 Chinchwad
}
{Name of Station 4
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Chinchwad}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Chinchwad}
{Name of Station 4
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 4 Chinchwad}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New facility | 20.40 | 234 | 1175.37 | Sqm | Soft: 31.08.2026 Old FOB Extension :31.12.2026, Lift & ESC: 20.02.2027 |
2 | {Circulating Area} | Improvement & New facility | | 616 | 5197.23 | Sqm | |
3 | {FOB} | Improvement | | 01 | | Nos | |
4 | {PF Shelter} | Improvement & New facility | | 2262 | 2272 | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | 14536 | 9425.52 | Sqm | |
6 | {Lift/Escalator} | New facility | | - | Lifts : 04 Escalator: 02 | Nos | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 104 | 23.02 | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 02 | 03 | No | |
11 | {Development of Second Entry} | Improvement | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Station Building Works
{Name of Station 4
Chinchwad}
Station Building Works
Station Building Works
Station Building Works
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 4
Chinchwad}
FOB Extension
FOB work
|
FOB |
|
FOB |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 4
Chinchwad}
Circulating Area/Parking Area Development
Add slide as per
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Chinchwad }
PF Surfacing & PF Shelter
{Name of Station 4
PF Surfacing & PF Shelter
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
PF Surfacing & PF Shelter |
|
Details of Activity (Night VIew) |
applicability
{Name of Station 4
2.7 Completed/ Work in Progress Photos (Station specific details)
Chinchwad}
|
Waiting Hall |
|
Waiting Hall |
|
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
|
Toilet |
|
{Name of Station 4
Chinchwad}
Toilet
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 4
Chinchwad}
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 4 Chinchwad}
Escalator ramp
Ramp for divyangjan
|
Ramp for divyangjan |
|
Divyangjan Booking counter (Ramp) |
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 5. Hadapsar}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 5
Hadapsar}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Provision and development of Second Entry including land acquisition | 252.09 | CAO/C/RSP | Proposal sent for approval |
2 | 6m Wide FOB towards Pune end | 14.18 | CAO/C/RSP | Proposal sent for approval |
3 | Construction of PF No 4 | 32.91 | CAO/C/RSP | GM approval done, Pending for finance concurrence |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 5 Hadapsar }
Updated Master Plan
2.3 Master Plan (Station specific details)
{Name of Station 5 Hadapsar }
{Name of Station 5
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Hadapsar }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 5
Hadapsar }
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
2.6 Brief Scope of Works (Station specific details)
{Name of Station 5
Hadapsar }
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New facility | 47.88 | 152.6 | 1300 | Sqm | Soft works, FOB & Skywalk |
| | | | | | | Completed on |
2 | {Circulating Area} | New facility | NA | 7890 | Sqm | ||
| :Nov 2025 | ||||||
3 | {FOB} | New facility | | | 1 Nos | Nos | Lift & ESC in |
| circulating area | ||||||
| | | | | | ||
4 | {PF Shelter} | Improvement & New facility | | 2112 | 5500 | Sqm | for divyangjan Compliance has been completed on 17-06-2026 Lift |
| | | | | | | on PF 1 - 30.09.26, Escalator on |
5 | {PF Surfacing} | Improvement & New facility | 10800 | 15000 | Sqm | ||
6 | {Lift/Escalator} | New facility | | - | Lift: 02 Escalator : 03 | Nos | PF 2&3 - 30.09.2026 |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | New facility | | 0 | 10 | Nos | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 46.55 | 150 | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 1 | 02 | Nos | |
11 | {Development of Second Entry} | Planned in Phase-II | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Station Building Works
{Name of Station 5
Hadapsar }
Station Building Works
Station Building Works
Station Building Works |
|
Station Building Works (Night View) |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
FOB
{Name of Station 5
Hadapsar }
SKYWALK
SKYWALK
SKYWALK STAIRCASE
FOB/SKYWALK Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area/Parking Area
{Name of Station 2 5
Hadapsar }
Circulating Area/Parking Area
Circulating Area/Parking Area Development
Add slide as per
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area (Night VIew) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Platform Up-gradation
{Name of Station 5
Hadapsar }
Platform Up-gradation
Platform Up-gradation
Platform Up-gradation (Night VIew)
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 5
Hadapsar }
Waiting Hall
VIP Waiting Hall
VIP Waiting Hall
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet in VIP Waiting room
{Name of Station 5
Hadapsar }
Toilet
Toilet
Toilet
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details) {Name of Station 5 Hadapsar }
2.7 Completed/ Work in Progress Photos (Station specific details)
Ramp for Divyangjan
{Name of Station 5 Hadapsar }
Toilet for Divyangjan
Low height booking office
Tactile Path
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 5 Hadapsar }
Art & Culture
|
Art & Culture |
|
Art & Culture |
Art & Culture
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Signages/ TIB
{Name of Station 5 Hadapsar }
Signages/ TIB
Signages/ TIB
Signages/ TIB
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 6. Uruli}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 6
Uruli}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
| N/A | N/A | N/A | N/A |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
{Name of Station 6 Uruli }
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
2.2 Station Views (Station specific details)
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 6 Uruli}
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on heard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 6
2.4 Status of Plans/ Drawings Approval (Station specific details)
Uruli}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 6
Uruli}
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 6 Uruli}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New facility | 12.86 | 451.2 | 250 Sqm | Sqm | Soft: 30.09.2026 12m FOB: - NA LIFT & ESC: NA |
2 | {Circulating Area} | Improvement & New facility | | 740 | 1220.5 Sqm | Sqm | |
3 | {FOB} | NA | | - | NA | NA | |
4 | {PF Shelter} | Improvement & New facility | | 836 | 6336 sqm | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | 7624 | 7602 Sqm | Sqm | |
6 | {Lift/Escalator} | NA | | - | NA | NA | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 56.16 | 60.35 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 2 | PF 1: 01 PF 2 : 01 Waiting Room : 02 | Nos | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Entrance
{Name of Station 6 Uruli}
Entrance Facade
Entrance Facade
Entrance Facade
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Details of Activity
{Name of Station 6
Uruli}
|
Details of Activity |
|
|
Details of Activity |
Details of Activity (Night VIew)
Circulating Area/Parking Area Development
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Platform Up-gradation
{Name of Station 6
Uruli}
|
Platform Up-gradation |
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
Platform Up-gradation |
|
Platform Up-gradation |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 6
Uruli}
|
Waiting Hall |
|
Waiting Hall |
|
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 6
Uruli}
Toilet
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 6 Uruli}
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 6 Uruli}
|
Toilet |
|
ramp |
|
Tactile path |
|
Low Hight water booth |
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 7 Kedgaon}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 7
Kedgaon}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
| N/A | N/A | N/A | N/A |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 7 Kedgaon}
{Name of Station 7 Kedgaon}}
Updated Master Plan (approved by GM)
2.3 Master Plan (Station specific details)
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 7
2.4 Status of Plans/ Drawings Approval (Station specific details)
Kedgaon }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
{Name of Station 7
Kedgaon }
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 7
Kedg
on }
S.No | a Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctione d Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement/ New facility | 12.54 | 340 | 160 | sqm | Soft upgradation |
| | | | | | | and COP work completed |
2 | {Circulating Area} | Improvement/ New facility | 800 | 1300 | sqm | ||
| | | | | | ||
3 | {FOB} | NA | | Available | Ramp on existing FOB on PF-1 & 2 -02 Nos. | nos. | on 28.02.2025, 12m FOB: - NA |
| | | | | | ||
4 | {PF Shelter} | Improvement/ New facility | | 821 | 7220 | sqm | Station Inaugurated |
| | | | | | | on - 23.05.2025. |
5 | {PF Surfacing} | Improvement/ New facility | 3150 | 4900 | sqm | ||
6 | {Lift/Escalator} | NA | | NA | NA | NA | |
7 | {Furniture} | New facility | | Available | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement/ New facility | | 32.57 | 32.57 | sqm | |
10 | {Toilet (New/ Renovation)} | Improvement/ New facility | | 01 block | 99.34 | sqm | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Station Building Works
{Name of Station 7
Kedgaon }
Station Building Works
Station Building Works
Station Building Works(Night VIew)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area/Parking Area
{Name of Station 7
Kedgaon }
Circulating Area/Parking Area
Circulating Area/Parking Area
Circulating Area/Parking Area(Night VIew)
Circulating Area/Parking Area Development
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
PF Surfacing & PF Shelter
{Name of Station 7
Kedgaon }
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
PF Surfacing & PF Shelter |
|
PF Surfacing & PF Shelter |
|
PF Surfacing & PF Shelter (Night View) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 7
Kedgaon }
Waiting Hall
|
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 7
Kedgaon }
Toilet
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 7 Kedgaon }
2.7 Completed/ Work in Progress Photos (Station specific details)
Divyangjan toilet- Ramp For Disabled Person
{Name of Station 7 Kedgaon }
Toilet
Toilet
Tactile provided for blind person
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Signages/ TIB
{Name of Station 7 Kedgaon }
Signages/ TIB
|
Signages/ TIB |
|
Signages/ TIB |
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 8. Baramati}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 8
Baramati}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
| NA | NA | NA | NA |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 8 Baramati}
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 8 Baramati}
{Name of Station 8
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Baramati}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 8
Baramati}
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
2.6 Brief Scope of Works (Station specific details)
{Name of Station 8
Baramati}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New facility | 11.40 | 370 | 206 | Sqm | SOFT- Completed on – 30.09.25 FOB- NA |
2 | {Circulating Area} | Improvement & New facility | | 646 | 2491.86 | Sqm | |
3 | {FOB} | NA | | NA | NA | NA | |
4 | {PF Shelter} | Improvement & New facility | | 836 | 2052.04 | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | 7624 | 2792.41 | Sqm | |
6 | {Lift/Escalator} | NA | | - | NA | NA | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | Improvement | | 1 | 0 | Nos | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 16.56 | 102.02 | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 18 Sqm | 01 | Nos | |
11 | {Development of Second Entry} | NA | | NA | NA | NA | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Portico
{Name of Station 8 Baramati}
Portico ( interior)
Portico
Portico (Night VIew)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area/Parking Area
{Name of Station 8
Baramati}
Circulating Area/Parking Area
Circulating Area/Parking Area Development
Add slide as per
Circulating Area/Parking Area |
|
Circulating Area/Parking Area (Night view) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Platform Up-gradation
{Name of Station 8
Baramati}
Platform Up-gradation
Platform Up-gradation
Platform Up-gradation (Night VIew)
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
{Name of Station 8
2.7 Completed/ Work in Progress Photos (Station specific details)
Baramati}
VIP Waiting Hall |
|
Waiting Hall |
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 8
Baramati}
Toilet
Toilet
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 8 Baramati}
{Name of Station 8 Baramati}
2.7 Completed/ Work in Progress Photos (Station specific details)
|
Low height ticket counter |
|
Toilet ramp |
|
Divyangjan Parking |
|
Toilet |
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 8 Baramati}
Art & Culture
|
Art & Culture |
|
Art & Culture |
Art & Culture Work
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 8 Baramati}
Signages/ TIB work
Signages/ TIB work
Signages/ TIB work |
|
Signages/ TIB work |
Signages/ TIB work
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 9. Lonand}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 9
Lonand}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
| NA | NA | NA | NA |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 9 Lonand }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 9 Lonand }
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 9
2.4 Status of Plans/ Drawings Approval (Station specific details)
Lonand }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 9
Lonand }
Before Development
Existing assets being retained (name of element)
Add slide as per applicability
|
After redevelopment ( post repair/ renovation/ refurbishment) |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 9 Lonand
}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 10.48 | 352 | 305.05 | Sqm | Completed on – 28.02.25 FOB- NA |
2 | {Circulating Area} | Improvement | | NA | 3377.47 | Sqm | |
3 | {FOB} | NA | | - | - | Sqm | |
4 | {PF Shelter} | Improvement | | 152 | 2011.15 | Sqm | |
5 | {PF Surfacing} | Improvement | | 8160 | 2447.11 | sqm | |
6 | {Lift/Escalator} | NA | | - | NA | NA | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | New facility | | 37.2 Sqm | 376.79 | Sqm | |
10 | {Toilet (New/ Renovation)} | New facility | | 89 Sqm | PF 1 = 1 | Nos | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
COP work complete
{Name of Station 9
Lonand }
Circulating Area
Portico (Interior) Toilet (Interior)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area
{Name of Station 9
Lonand }
Circulating Area(Night VIew)
|
Circulating Area |
|
Parking Area |
applicability
Circulating Area/Parking Area Development
Add slide as per
2.7 Completed/ Work in Progress Photos (Station specific details)
PF Surfacing
{Name of Station 9
Lonand }
|
PF Shelter |
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
PF Shelter |
|
PF Surfacing & PF Shelter (Night VIew) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 9
Lonand }
Waiting Hall
|
Waiting Hall washroom |
|
Waiting Hall washroom |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 9
Lonand }
|
Toilet |
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
|
Low Height Ticket Booth |
|
Details of Activity |
{Name of Station 9 Lonand }
|
Tactile path |
|
Details of Activity |
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 9 Lonand }
|
Art & Culture |
|
Art & Culture |
|
Art & Culture |
|
Art & Culture |
Art & Culture
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 9 Lonand }
|
IVD |
|
OVD |
|
Signages |
|
TIB |
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 10. Wathar}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 10
Wathar}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1. | Construction of balance work under ABSS in Pune Division. | 7.01 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details) {Name of Station } {Name of Station 10 Wathar}
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 10 Wathar}
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 10
2.4 Status of Plans/ Drawings Approval (Station specific details)
Wathar}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 10
Wathar}
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
2.6 Brief Scope of Works (Station specific details)
{Name of Station 10
Wath
ar}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 7.97 | 692 | 305.05 Sqm | Sqm | Soft & COP: 30.09.2027 |
| | | | | | | 3m FOB: - |
| | | | | | | Being |
2 | {Circulating Area} | Improvement | | 4692 | 3377.47 Sqm | Sqm | |
constructed by | |||||||
3 | {FOB} | New facility (work in progress under Construction | | - | - | | construction dept. 31.05.2028 |
| | department) | | | | ||
4 | {PF Shelter} | New facility/Improvement | | 166 | 2011.15 Sqm | Sqm | |
5 | {PF Surfacing} | New facility/Improvement | | 166 | 2447.11 Sqm | Sqm | |
6 | {Lift/Escalator} | NA | | NA | NA | NA | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement | | 250 | 376.79 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement | | 24 Sqm | PF 1 = 1 Nos | Sqm | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Entry Gate
{Name of Station 10
Wathar}
Station Building
Portico
Portico (Side view)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area
{Name of Station 10
Wathar}
Parking Area
Circulating Area
Details of Activity (Night VIew)
Circulating Area/Parking Area Development
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
PF Surfacing & PF Shelter
{Name of Station 10
Wathar}
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter
PF Surfacing & PF Shelter
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
|
Waiting Hall |
|
Waiting Hall |
|
Waiting Hall |
{Name of Station 10
Wathar}
Waiting Hall
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 10
Wathar}
Toilet
Toilet
Toilet
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet for divyangjan
{Name of Station 10 Wathar}
Low Height water booth
Tactile path
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 10 Wathar}
Signages/ TIB
Signages/ TIB
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 11. Satara}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 11
Satara}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Lift – 02 no's | 2.4 | CAO/C/RSP | Proposal sent for approval |
2 | Construction of Balance work of soft upgradation | 19.5499 | CAO/C/RSP | Proposal sent for approval |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Proposed After Redevelopment
Before Development
{Name of Station 11 Satara }
Proposed After Redevelopment
Proposed After Redevelopment
Updated Master Plan
2.3 Master Plan (Station specific details)
{Name of Station 11 Satara}
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 11
2.4 Status of Plans/ Drawings Approval (Station specific details)
Satara}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station
11 satara}
|
Before Development |
|
|
After redevelopment
Existing assets being retained (name of element)
Add slide as per applicability
2.6 Brief Scope of Works (Station specific details)
{Name of Station 11 satara}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 32.31 | 462.38 | New Building = 802 Sqm Improvement to Bldg = 416 | Sqm | Soft: 31.12.2026 12m FOB: |
| | | | | Sqm | | 31.01.2027 |
| | | | | | | LIFT & ESC - 30.09.2027 |
2 | {Circulating Area} | Improvement & New facility | 3200 | 5097.11 Sqm | Sqm | ||
3 | {FOB} | New facility | | NA | 1 Nos | Nos. | |
4 | {PF Shelter} | Improvement & New facility | | 3090 Sqm | 5010 Sqm | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | - | 5950 Sqm | Sqm | |
6 | {Lift/Escalator} | New facility | | - | Lift = 3 ESC = 6 | Nos. | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 28 Sqm | 76.56 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 02 | PF 1 & 2 = 1, PF 3 & 4 = 1, | Nos. | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 11
Satara}
Station Building Works
Station Building Works
|
Station Building Works |
|
Entry Gate |
Exit gate
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 11
Satara}
FOB
FOB Works
|
FOB |
|
FOB |
|
FOB |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 11
Satara}
Circulating Area/Parking Area Development
Add slide as per
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 11
Satara}
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Platform Up-gradation |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 11
Satara}
Waiting Hall
|
Waiting Hall |
|
Waiting Hall |
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 11
Satara}
Toilet
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 11
Satara}
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 11 Satara}
Art & Culture
|
Art & Culture |
|
Art & Culture |
Art & Culture
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 12. Karad}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 12
Karad}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
| NA | NA | NA | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 12 Karad }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 12 Karad}
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 12
2.4 Status of Plans/ Drawings Approval (Station specific details)
Karad}
2.5 Improvement of Existing Assests Being Retained (Station specific details)
{Name of Station 12
Karad}
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 12 Karad}
S.N o | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sq m) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 12.51 | 568.5 | 847.63 Sqm | Sqm | Soft & COP: 30.09.2025 |
| 12m FOB: - NA | ||||||
2 | {Circulating Area} | Improvement & New facility | 133 | 5842.55 Sqm | Sqm | ||
3 | {FOB} | NA | | - | - | Nos | |
4 | {PF Shelter} | Improvement & New facility | | - | 3187.6 Sqm | Sqm | |
5 | {PF Surfacing} | Improvement | | - | 6723.64 Sqm | Sqm | |
6 | {Lift/Escalator} | NA | | NA | NA | NA | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 36.1 | 305.25 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 12.5 Sqm | 2 | Nos | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Station Building
{Name of Station 12
Karad}
Station Building
Entry gate
Station Building (Night VIew)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area/Parking Area
{Name of Station 12
Karad}
Circulating Area/Parking Area
Circulating Area/Parking Area Development
Add slide as per
|
Circulating Area/Parking Area |
|
Circulating Area(Night VIew) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 12
Karad}
PF Surfacing & PF Shelter
Details of Activity (Night VIew)
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 12
Karad}
Waiting Hall
Waiting Hall
Waiting Hall (Toilet)
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 12
Karad}
|
Toilet |
|
Toilet |
|
Divyangjan Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 12
Karad}
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 12 Karad}
Low height water booth
Tactile path
|
Tactile path |
|
Toilet for divyangjan |
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 12 Karad}
Art & Culture
|
Art & Culture |
|
Art & Culture |
Art & Culture
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Signages/ TIB
{Name of Station 12 Karad}
Signages/ TIB
|
Signages/ TIB |
|
Signages/ TIB |
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 12. Sangli}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 14
Sangli}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | COP at PF 02 & 03 | 5 Cr | CAO/C/RSP | Work In Progress |
1 | Construction of balanced work for soft upgradation in sangli station + proviaion of horticulture for 20 stations | 19.6176 | CAO/C/RSP | Proposal sent for approval |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 14 Sangli }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 14 Sangli }
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
{Name of Station 14
2.4 Status of Plans/ Drawings Approval (Station specific details)
Sangli }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 14
Sangli }
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 14 Sangli
}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement & New Facility | 22.20 | 457 | 257.64 Sqm | Sqm | Soft: 31.12.26 12m FOB: 31.01.2027 LIFT & ESC - 30.09.2027 |
2 | {Circulating Area} | Improvement & New Facility | | NA | 5163.41 Sqm | Sqm | |
3 | {FOB} | New facility | | - | 1Nos | Nos | |
4 | {PF Shelter} | Improvement & New Facility | | 800 | 4356Sqm | Sqm | |
5 | {PF Surfacing} | Improvement & New Facility | | 7056 | 8202.50 Sqm | Sqm | |
6 | {Lift/Escalator} | New facility | | - | Lift = 3 ESC = 4 | Nos | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New Facility | | 111.09 | 126.63 Sqm | Sqm | |
10 | {Toilet (New/ Renovation)} | New facility | | 14 | PF1 = 1 No PF2 = 1No | Nos | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14
Sangli }
Station Building Works
Station Building Works (Booking office)
Station Building Works
|
Entry gate |
|
Station Building Works |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14
Sangli }
FOB Works
|
FOB PF 1 |
|
FOB PF4/5 |
|
FOB PF 2/3 |
|
Details of Activity |
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Parking Area
{Name of Station 14
Sangli }
Circulating Area |
|
Circulating Area |
Parking Area
Circulating Area/Parking Area Development
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14
Sangli }
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Details of Activity (Night VIew) |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14
Sangli }
Waiting Hall
| |
Waiting Hall | |
| |
Waiting Hall | |
Waiting Hall
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Toilet
{Name of Station 14
Sangli }
Toilet
|
Toilet |
Toilet
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 14
Sangli }
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14 Sangli }
|
Toilet for Divyangjan (Ramp) |
|
Tactile path |
|
Divyangjan Ramp |
|
Toilet |
Divyangjan Facilities
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 14 Sangli }
Art & Culture
|
Art & Culture |
Art & Culture
Art & Culture
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 14 Sangli }
|
Signages/ TIB |
|
Signages/ TIB |
|
Signages/ TIB |
|
Signages/ TIB |
Signages/ TIB
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station
15. Hatkanangale}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 15
Hatkanangale}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balanced work under ABSS in Pune Division. | 19.0228 | CAO/C/RSP | Proposal sent for approval |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 15 Hatkanangale }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 15
Hatkanangale }
{Name of Station 15
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Hatkanangale }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
{Name of Station 15
Hatkanangale }
Existing assets being retained (name of element)
Add slide as per applicability
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
|
Before Development |
|
After redevelopment ( post repair/ renovation/ refurbishment) |
2.6 Brief Scope of Works (Station specific details)
{Name of Station 15
Hatkanangale }
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 8.05 | - | 303.80 Sqm | Sqm | Soft: 31.03.2028 FOB: NA |
2 | {Circulating Area} | New facility/Improvement | - | 1081.49 | Sqm | ||
3 | {FOB} | NA | 01 | 01 | No | ||
4 | {PF Shelter} | New facility/Improvement | - | 2226.66 Sqm | Sqm | ||
5 | {PF Surfacing} | New facility/Improvement | - | 4778.68 Sqm | Sqm | ||
6 | {Lift/Escalator} | NA | NA | NA | NA | ||
7 | {Furniture} | New Facility | - | - | - | ||
8 | {Art and Culture} | NA | - | - | - | ||
9 | {Waiting Hall (New/ Renovation)} | New facility | - | - | - | ||
10 | {Toilet (New/ Renovation)} | New facility | - | 109.15 Sqm | Sqm | ||
11 | {Development of Second Entry} | NA | - | - | - |
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 15
Hatkanangale }
Station Building Works
Add slide as per applicability
|
Station Building Works |
|
Station Building Works |
|
Station Building Works (Entry gate) |
|
Station Building Work |
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 15
Hatkanangale }
Circulating Area/Parking Area Development
Add slide as per
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
|
Circulating Area/Parking Area |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 15
Hatkanangale }
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Platform Up-gradation |
|
Platform Up-gradation |
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 15
Hatkanangale }
Waiting Hall
|
Waiting Hall |
Waiting Hall
Waiting Hall
Add slide as per applicability
{Name of Station 15
2.7 Completed/ Work in Progress Photos (Station specific details)
Hatkanangale }
|
Toilet |
|
Toilet |
|
Toilet |
|
Toilet |
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 15
Hatkanangale }
2.7 Completed/ Work in Progress Photos (Station specific details)
Divyangjan Toilet
{Name of Station 15
Hatkanangale }
Divyangjan Toilet
|
Divyangjan Toilet |
|
Divyangjan Toilet |
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station 16. Kolhapur}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Name of Station 16
Kolhapur}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balanced work under ABSS in Pune division + Horticulture operations for inauguration of all the stations under GSU/PA | 19.7346 | CAO/C/RSP | Proposal sent for approval |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Name of Station 16 Kolhapur }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Name of Station 16 Kolhapur }
{Name of Station 16
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval (Station specific details)
Kolhapur }
2.5 Improvement of Existing Assests Being Retained (Station specific details)
Before Development
{Name of Station 16
Kolhapur }
Before Development
After redevelopment ( post repair/ renovation/ refurbishment)
After redevelopment ( post repair/ renovation/ refurbishment)
Existing assets being retained (name of element)
Add slide as per applicability
2.6 Brief Scope of Works (Station specific details)
{Name of Station 16
Kolh
pur }
S.No a | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | 43.03 | - | 4192 | sqm | Soft : 31.10.2026 12m FOB: 31.12.2026 LIFT & Escalator – 30.06.2027 |
2 | {Circulating Area} | Improvement & New facility | | 6100 | 10733 | Sqm | |
3 | {FOB} | New facility | | 01 | 01 | Nos | |
4 | {PF Shelter} | Improvement & New facility | | 5779 | 3000 | Sqm | |
5 | {PF Surfacing} | Improvement & New facility | | 10240 | 10720 | sqm | |
6 | {Lift/Escalator} | New facility | | - | Lift-2 Esc-4 | no | |
7 | {Furniture} | New facility | | - | - | - | |
8 | {Art and Culture} | NA | | - | - | - | |
9 | {Waiting Hall (New/ Renovation)} | Improvement & New facility | | 125 Sqm | - | | |
10 | {Toilet (New/ Renovation)} | Improvement & New facility | | 22 Sqm | Pf 1- 01 Pf2/3 - 01 | no | |
11 | {Development of Second Entry} | NA | | - | - | - | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Station Building Works
{Name of Station 16
Kolhapur }
Station Building Works
Station Building Works
Details of Activity (Night VIew)
Station Building Works
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Name of Station 16
Kolhapur }
FOB Works
|
FOB |
|
FOB |
|
FOB |
|
|
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Circulating Area/Parking Area |
|
|
{Name of Station 16
Kolhapur }
Circulating Area/Parking Area
Details of Activity (Night VIew)
Circulating Area/Parking Area Development
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Platform Up-gradation
{Name of Station 16
Kolhapur }
Platform Up-gradation
Platform Up-gradation
Details of Activity (Night VIew)
Platform Up-gradation (PF Surfacing & PF Shelter)
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Waiting Hall
{Name of Station 16
Kolhapur }
Waiting Hall
Waiting Hall
Waiting Hall
Waiting Hall
Add slide as per applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
General Toilet
{Name of Station 16
Kolhapur }
Toilet at PF No. 01
Toilet
Toilet at PF No. 2/3
Toilet
Add slide as per applicability
2.7. Divyangjan Route Plan (Station specific details)
{Name of Station 16
Kolhapur }
2.7 Completed/ Work in Progress Photos (Station specific details) {Name of Station 16 Kolhapur }
Divyangjan Facilities
|
|
Divyangjan Facilities
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
Art & Culture
{Name of Station 16 Kolhapur }
|
Art & Culture |
|
Art & Culture |
Art & Culture
Art & Culture
Add slide as per
applicability
Amrit Station Specific Details
{KOPERGAON}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Kopargaon}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 9.4871 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views
STATION FRONT FACADE After Redevelopment
STATION FRONT FACADE After Redevelopment
{KOPERGAON }
|
STATION FRONT FACADE Before Development |
|
STATION FRONT FACADE Before Development |
Updated Master Plan (approved by GM)
2.3 Master Plan
{KOPERGAON }
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval
{KOPERGAON }
2.5 Improvement of Existing Assets Being Retained
Before Development of Sleeper Waiting hall
{KOPERGAON }
After Development of Sleeper Waiting hall
Existing assets being retained
Before Development
After Development
2.6 Brief Scope of Works (Station specific details)
{Kopargaon}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement | Improvement | | (Quantity) | (Quantity) | | Soft : 31.03.2027 6 m FOB: - 31.12.2027, Lift & escalators - 31.03.2028 |
| to Bldg} | | | | | ||
| | | 29.94 | | | ||
2 | {Circulating Area} | Improvement | | | | ||
3 | {FOB} | New facility | | | | | |
4 | {PF Shelter} | Improvement | | | | | |
5 | {PF Surfacing} | Improvement | | | | | |
6 | {Lift/Escalator} | Improvement | | - | Lift:03 | Nos | |
| | | | | Esc: 02 | | |
7 | {Furniture} | New facility | | | | | |
8 | {Art and Culture} | NA | | | | | |
9 | {Waiting Hall (New/ | Improvement | | | | | |
| Renovation)} | | | ||||
10 | {Toilet (New/ Renovation)} | New facility | | | | | |
11 | {Development of Second | NA | | | | | |
| Entry} | | | ||||
12 | Add or delete items as per | | | | | | |
| applicability | |
2.7 Completed Photos ( Booking Office )
Booking Office Before Redevelopment.
{KOPERGAON}
Booking Office After Redevelopment.
Booking Office Works
2.7 Work in Progress Photos (Circulating Area/Parking Area )
Circulating Area Before Redevelopment
{KOPERGAON}
Compound Wall of Circulating Area
Circulating Area After Redevelopment
Circulating Area/Parking Area Development
Circulating Area After Redevelopment
2.7 Work in Progress Photos (PF Surfacing & PF Shelter)
PF Surfacing Before redevelopment
{KOPERGAON }
PF Surfacing After redevelopment
PF Shelter Before redevelopment
PF Shelter After redevelopment
Platform Up-gradation (PF Surfacing & PF Shelter)
2.7 Completed/ Work in Progress Photos
Waiting Hall After Redevelopment
{KOPERGAON }
Waiting Hall After Redevelopment
Waiting Hall
Waiting Hall After Redevelopment
Waiting Hall After Redevelopment
2.7 Completed/ Work in Progress Photos
{KOPERGAON}
Toilet Work is in Progress
Toilet
Toilet Work is in Progress
Toilet Work is in Progress
Toilet Work is in Progress
2.7. Divyangjan Route Plan
{KOPERGAON}
2.7 Completed/ Work in Progress Photos
{KOPERGAON}
Divyangjan Facilities
Divyangjan Ramp
Divyangjan Tiles on Platform
Divyangjan Tiles near Booking Office
Divyangjan Tiles
Amrit Station Specific Details
{Name of Amrit Station Belapur}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Belapur}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 13.4446 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views
STATION ENTRANCE GATE Before Development
CIRCULATINGAREA Proposed view After Redevelopment
STATION ENTRANCE GATE Proposed view After Redevelopment
CIRCULATING AREA Before Development
{BELAPUR- 2 }
Updated Master Plan (approved by GM)
2.3 Master Plan
{BELAPUR - 2}
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Mater plan was approved by all Bos & DRM/PA initially on hard copy. However, after meeting with railway board, master plan is rectified/ updated as per instructions and put up for approval please. |
Circulation Plan | Yes | Yes | - |
Divyangjan route Plan | Yes | Yes | - |
Signage layout Plan | Yes | Yes | - |
Material Finish and Schedule | Yes | Yes | - |
Drainage Plan | Yes | Yes | - |
Furniture | No | No | - |
Art & Culture | No | No | - |
| | | |
2.4 Status of Plans/ Drawings Approval
{BELAPUR - 2}
2.5 Improvement of Existing Assests Being Retained
Before Development Waiting Hall
{BELAPUR - 2}
Before Development Entry Gate
After redevelopment Waiting Hall
After redevelopment Entry Gate
Existing assets being retained
2.6 Brief Scope of Works (Station specific details)
{Belapur}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctione d Cost (Rs, crore) | Existin g Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement | New facility | 31.96 | (Quanti | (a). 307.86 | Sqm. | Soft: |
| to Bldg} | | | ty) | b). 335.49 | Sqm. | 31.08.2026 |
| | | | | | | 6 m FOB: - |
| | | | | | | 31.03.2027 Lift |
2 | {Circulating Area} | Improvement | | 350 | Sqm | ||
| & Escalator - | ||||||
| | | | | | ||
3 | {FOB} | New facility | | 6.0 m wide FOB GAD | 15.12.2027 | ||
| | | | under approval. | | ||
4 | {PF Shelter} | New facility | | | PF No. 01 - 09 Bay. | Sqm. | |
| | | | PF No. 02 - 04 Bay | Sqm. | | |
5 | {PF Surfacing} | Improvement | | | PF No. 01 - 09 Bay. | Sqm. | |
| | | | PF No. 02 - 04 Bay | Sqm. | | |
6 | {Lift/Escalator} | New facility | | - | Lift:03 | Nos | |
| | | | | Esc: 04 | | |
7 | {Furniture} | New facility | | | | | |
8 | {Art and Culture} | New facility | | | | | |
9 | {Waiting Hall (New/ | Improvement | | | | | |
| Renovation)} | | | | |||
10 | {Toilet (New/ Renovation)} | New facility | | | 200 | Sqm | |
11 | {Development of Second | | | | In Second Phase | | |
Entry} | | |
2.7 Work in Progress Photos
Existing Station Building
{BELAPUR - 2}
Station Building Work in progress
Existing Station Building front façade work is in progress
Station Building Work in progress
Station Building Works
2.7 Completed/ Work in Progress Photos (Circulating Area)
Before Redevelopment of CIRCULATING AREA
{BELAPUR }
CIRCULATING AREA Work in Progress
CIRCULATING AREA Work in Progress
Circulating Area
CIRCULATING AREA Work in Progress
2.7 Completed/ Work in Progress Photos (Station specific details)
{BELAPUR }
COP of PF no - 01 COP of PF no - 02
Platform Up-gradation (PF Surfacing & PF Shelter)
COP of PF no - 02
coping chequer tile PF no - 01
2.7 Completed (Waiting Hall )
{BELAPUR }
Before Redevelopment of Waiting Hall | | |
After Redevelopment of Waiting Hall | ||
| ||
After Redevelopment of Waiting Hall | | After Redevelopment of Waiting Hall |
Waiting Hall | ||
2.7 Completed (Toilet)
{BELAPUR }
Toilet
Toilet Work
Toilet
Toilet
Toilet
2.7. Divyangjan Route Plan
{BELAPUR }
Amrit Station Specific Details
{Daund Station}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Daund station }
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 9.2961 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Proposed After Redevelopment
North side
South side -entry
{Daund station }
2.3 Master Plan (Station specific details)
Updated Master Plan (approved by GM)
{Daund station }
2.4 Status of Plans/ Drawings Approval (Station specific details)
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Approved by DRM, PA. |
Circulation Plan | Yes | Yes | |
Divyangjan route Plan | Yes | Yes | |
Signage layout Plan | Yes | Yes | |
Material Finish and Schedule | Yes | Yes | |
Drainage Plan | Yes | Yes | |
Furniture | No | No | |
Art & Culture | No | No | |
| | | |
{Daund station }
2.6 Brief Scope of Works (Station specific details)
{Daund station }
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement to Bldg} | Improvement | | | | Soft: 31.03.2028 FOB: NA | |
2 | {Circulating Area}/Station Approach road | Improvement | | | 9050 | Sqm | |
3 | {FOB} | New facility | 14.24 | | | | |
4 | {PF Shelter} | Improvement | | 7800 Sqm | 4500 | Sqm | |
5 | {PF Surfacing} | Improvement | | | 3000 | Sqm | |
6 | {Lift/Escalator} | NA | | Lift: 04 | NA | Nos | |
7 | {Furniture} | New facility | | | | | |
8 | {Art and Culture} | NA | | | | | |
9 | {Waiting Hall (New/ Renovation)} | Whether New facility/ Improvement | | | | | |
10 | {Toilet (New/ Renovation)} | Whether New facility/ Improvement | | | 50 | Sqm | |
11 | {Development of Second Entry} | - | | | | | |
12 | Add or delete items as per applicability | | | | | | |
2.7 Completed/ Work in Progress Photos (Station specific details)
Pf no 3 burn granite work
{Daund station }
Pf no 3 burn granite work
Platform Up-gradation (PF Surfacing)
Add slide as per applicability
| |
| |
| |
Platform Up-gradation (PF Shelter)
2.7 Completed/ Work in Progress Photos (Station specific details)
{Daund Station}
Waiting Hall
Add slide as per
applicability
2.7 Completed/ Work in Progress Photos (Station specific details)
{Daund station }
|
URINALS |
Toilet
Add slide as per
|
IWC |
|
COUNTER TOP WASH BASIN |
EWC
applicability
2.7. Divyangjan Route Plan (Station specific details)
{Daund Station}
2.7 Completed/ Work in Progress Photos (Station specific details)
{Daund station }
VIP siding-Tactile pathway
|
Pf no -1 Tactile pathway |
|
Pf no -1 Tactile pathway |
| |
| |
Pf no -3 Tactile pathway | |
Divyangjan Facilities
Add slide as per applicability
Amrit Station Specific Details
{Name of Amrit Station Ahmednagar}
2.1 Station Wise Progress: Extra Work Proposed/ To be Proposed
{Ahmednagar}
S.No | Name of work | Cost ( crore) | Executing Authority | Status of Work |
1 | Construction of balance work under ABSS in Pune division | 13.7795 | CAO/C/RSP | Submitted to competent authority for sanction. |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
2.2 Station Views (Station specific details)
Before Development
Proposed After Redevelopment
Proposed After Redevelopment
Before Development
{Ahmednagar}
Updated Master Plan (approved by GM)
2.3 Master Plan (Station specific details)
{Ahmednagar}
2.4 Status of Plans/ Drawings Approval (Station specific details)
Item | Plan/ Drawing prepared (Y/N) | Plan/ Drawing approved by Competent Authority (Y/N) | Remarks |
Master Plan (approved by GM) | Yes | Yes | Approved by DRM, PA. |
Circulation Plan | Yes | Yes | |
Divyangjan route Plan | Yes | Yes | |
Signage layout Plan | Yes | Yes | |
Material Finish and Schedule | Yes | Yes | |
Drainage Plan | Yes | Yes | |
Furniture | No | No | |
Art & Culture | No | No | |
| | | |
{Ahmednagar}
Upper Class Waiting Hall Before Development
2.5 Improvement of Existing Assets Being Retained
{AHMEDNAGAR - 1}
SM Office Before Development
Upper Class Waiting Hall After redevelopment
|
SM Office After redevelopment |
Existing assets being retained (Upper class waiting area & SM
Office )
2.6 Brief Scope of Works (Station specific details)
{Ahmednagar}
S.No | Scope of Work Description {add/modify items as relevant to the station} | Whether New facility/Improvement | Sanctioned Cost (Rs, crore) | Existing Facility | Developed New Facility | Unit (m/no/sqm) | TDC |
1 | {New Building/Improvement | Improvement | 30.92 | (Quantity) | (Quantity) | | Soft: 30.08.2026 6 m FOB: - 31.12.2026 Lift & Escalator - 15.12.2027 |
| to Bldg} | | | | | ||
2 | {Circulating Area} | Improvement | | | | | |
3 | {FOB} | New facility | | | | | |
4 | {PF Shelter} | Improvement | | | | | |
5 | {PF Surfacing} | Improvement | | | | | |
6 | {Lift/Escalator} | New facility | | - | Lift:03 | Nos | |
| | | | | Esc: 06 | | |
7 | {Furniture} | New facility | | | | | |
8 | {Art and Culture} | NA | | | | | |
9 | {Waiting Hall (New/ | Improvement | | | | | |
| Renovation)} | | | ||||
10 | {Toilet (New/ Renovation)} | New facility | | | | | |
11 | {Development of Second | NA | | | | | |
| Entry} | | | ||||
12 | | | | | | |
2.7 Completed/ Work in Progress Photos
Service Building – A Redevelopment – work in progress
{AHMEDNAGAR - 1}
Service Building – A Redevelopment – work in progress
Service Building – A Redevelopment – work in progress
Service Building - A
Service Building – A Redevelopment – work in progress
2.7 Completed/ Work in Progress Photos
{AHMEDNAGAR - 1}
Service Building – B before Redevelopment
Service Building – B After Redevelopment – work in progress
Service Building – B After Redevelopment – work in progress
Service Building – B After Redevelopment – work in progress
2.7 Work in Progress Photos
Circulating Area before redevelopment
{AHMEDNAGAR - 1}
Circulating Area After Redevelopment
Parking Area Before Redevelopment Parking Area After Redevelopment
Circulating Area & Parking Area Development
2.7 Completed/ Work in Progress Photos
{AHMEDNAGAR - 1}
Platform Up-gradation (PF Shelter) Work Completed
PF Shelter after Redevelopment
PF Shelter after Redevelopment
PF Shelter after Redevelopment
PF Shelter after Redevelopment
2.7 Completed/ Work in Progress Photos
Before Redevelopment of Waiting hall
{AHMEDNAGAR - 1}
After Redevelopment of Waiting hall
After Redevelopment of Waiting hall
After Redevelopment of Waiting hall
Waiting Hall
2.7 Completed/ Work in Progress Photos
{AHMEDNAGAR - 1}
Toilet (Work is in progress)
Redevelopment of Toilet
Redevelopment of Toilet
Redevelopment of Toilet
Redevelopment of Toilet
2.7. Divyangjan Route Plan
{AHMEDNAGAR - 1}
2.7 Completed/ Work in Progress Photos
{AHMEDNAGAR - 1}
Divyangjan Facilities Work In Progress
Divyangjan Ramp Work in Progress
Divyangjan Parking area
Divyangjan of Toilet Work in Progress | |
| |
Divyangjan Toilet | |