SAP Production Planning & Execution
in S/4 2022/2023
setup MRP Area as
APO Location for Advanced Planning
for Storage Location MRP Control
check SLoc Segment in MRP4 view for SLoc 101A
S/4 2022/2023
(MM01)
MRP 4 view at SLoc 101A
NO Longer have Storage Location Segment
S/4 2022/2023
(MM01)
S/4 2022/2023
(MMSC)
MMSC in S/4 also no longer have the MRP 4 SLoc segment data
check SLoc Segment in MRP4 view for SLoc 0001
ECC
EhP8
(MM01)
MRP 4 view at SLoc 101A
contain Storage Location segment in ECC
ECC
EhP8
(MM01)
ECC
EhP8
(MM01)
in ECC, the Storage Location segment in MRP4 data view can be used to configure to IGNORE Storage Location stocks for a specific Material for Planning
However, the MRP4 SLoc segment is not longer available in S/4!
S/4 2022/2023
(OMIR)
ECC
EhP8
(MM01)
Menu path to access OMIR for SLoc MRP no longer possible in S/4
Menu path to access OMIR for SLoc MRP
is active and can be used in ECC
S/4 2022/2023
(OMIR)
OMIR for SLoc MRP no longer possible in S/4
t-code OMIR is available in S/4
BUT no longer can be used to configured Material independent SLoc MRP
ECC
EhP8
(OMIR)
SLoc MRP per Plant (Material independent) was available in ECC
ECC
EhP8
(OMIR)
ECC t-code OMIR configure Storage Locations in a Plant for MRP Control
ECC
EhP8
(OMIR)
ECC t-code OMIR configure Storage Locations in a Plant for MRP Control which is Material independent (ie: ALL Materials in this Plant 1000 SLoc 0002 and SLoc 0003 will be ignore)
ECC
EhP8
(OMIR)
Material master MRP4 SLoc segment was used to setup the Material to ignore MRP Planning for the SLoc 0001
ECC
EhP8
(OMIR)
OMIR (via SPRO) can be used to setup Storage Locations to NOT Planned for MRP at the Plant level for ALL Materials in that Plant
ECC
EhP8
(OMIR)
ALL other Storage Location not setup for MRP Ignore either via Material MRP4 view of SPRO OMIR, the Stocks are displayed here and ARE relevant for MRP Planning
ECC
EhP8
(OMIR)
SLoc stock 0004 (100pc) still available for MRP Planning is used for Net Calculation for MRP Planning
Other SLoc setup for Ignore by MRP via:
0001 (via MRP4 SLoc segment)
0002,0003 (via OMIR)
are NOT used for Planning
ECC
EhP8
(OMIR)
ECC
EhP8
ECC
EhP8
Other SLoc setup for Ignore by MRP via:
0001 (via MRP4 SLoc segment)
0002,0003 (via OMIR)
are NOT used for Planning
ECC
EhP8
Other SLoc setup for Ignore by MRP via:
0001 (via MRP4 SLoc segment)
0002,0003 (via OMIR)
are NOT used for Planning
S/4 2022/2023
MM02
To setup SLoc MRP control (Ignore MRP) looks like can only be achieved via
MRP Area
S/4 2022/2023
MM02
this example will focus on SLoc 0001 to 0004 (non WM SLocs)
MRP Area was introduced in ECC4.0 (early 2000) as an alternative (enhanced) method for SLoc MRP for Materials,
the feature continue
to ECC6.0
and at present also in S/4HANA since 1511.
create MRP Area to setup SLoc 0001 to
Ignore MRP for a Material
MRP Area coding is
5 or more Alphanumeric
Assign SLoc 0001 as default Receiving SLoc for MRP Area 1000_0001
Assign one or more SLoc to the MRP Area 1000_0001 (including SLoc 0001)
Assign one or more SLoc to the MRP Area 1000_0001 (including SLoc 0001)
Assign one or more SLoc to the MRP Area 1000_0001 (including SLoc 0001)
Advanced Planning NOT yet activated for Material M01
Assign MRP Area
1010_0001
for Material M01
Assign MRP Area
1010_0001
for Material M01
MRP Area
1010_0001
set MRP Type “ND”
click “Check” “Adopt”
MRP Exists
SAVE
Plant level
MRP Type is “PD”
GR 100pcs for SLoc 0001, 0002, 0003, 0004
notice MRP Area 1010_0001 (SLoc 0001) is displayed separately in MMBE
MRP Area 1010 means
Plant level means any SLoc not assigned to any MRP Area
MRP Type “PD” (at Plant level)
MRP Area
1010_0001 means for SLoc 0001
MRP Type “ND” (No Planning)
CIF (Core-Interface) used in Classic APO-ECC no longer used to create APO Location (for Plant and MRP Area) in S/4 HANA 2022/2023
in SA38,
run this Program to Create APO Location for new Plants and
new MRP Areas
MRP Area 1010_0001
now extended to
Advanced Planning as
APO Location 1010_001
MRP Area created as APO Location 1010_001 as (Ignore Location Type 1001.. see next slide)
MRP Area created as APO Location 1010_001 as Location Type 1007
Activate Material for
Advanced Planning
Material M01
extended to
APO Location 1010
Material M01
extended to
APO Location 1010_0001
Since Stocks (MRP Elements) exists in the Classic Planning environment before “Advanced Planning” Activation, run this Program to Reconcile all MRP Elements to the Advanced Planning environnement
Enter the current S/4 System
Reconcile SLoc Stocks from the Classic Planning environment to APO Planning environment
Reconcile Stock for the new Material M01 for all SLoc
Reconciled
Plant level
SLoc without MRP Area
MRP Area 1010_0001
SLoc 0001
check equivalent to MD04 S/R List for APO
Product View of Location 1010 (Plant level)
Stocks for all non-MPR Area
Product View of Location 1010_0001 (MRP Area for SLoc 0001)
Stocks for all MPR Area
1010_0001
ie: SLoc 0001
MTS Strategy at the Plant level for Plant level also applied for All MRP Area (but note that MRP Area 1010_0001 with MRP Type “ND” while Plant level MRP Type is “PD”
MRP Area can be entered here, but this example to enter PIR at the Plant level which will not appear in the MRP Area planning
PIR at the Plant level
PIR created at Plant level is not relevant for this MRP Area
PIR created at Plant level is only relevant for Plant level
This SLoc (MRP Area) is NOT Planned (or Ignore for Planning) unless PIR is created for the MRP Area and the MRP Area is assigned with valid MRP Type
No Planning for APO Location 1010_0001
Shortage at Location 1010 (Plant level) for the PIR created at the Plant level
Run the “Product Heuristic”
Product Heuristics executed for the Material at Plant level
PRs created (no Planned Orders for External Procurement) via Product Heuristics
PPDS generated PR is now in S/R List for Plant level 1010
Since no Planning decided for the MRP Area 1010_0001 (SLoc 0001) and PIR or Sales Order etc will not be created for the MRP Area or SLoc 0001, no Planning here in this case
Since no Planning decided for the MRP Area 1010_0001 (SLoc 0001) and PIR or Sales Order etc will not be created for the MRP Area or SLoc 0001, no Planning here in this case