1 of 35

ABES Engineering College, Ghaziabad

1

Project Presentation

On

Reducing Defects of Bush by using DMAIC method

​

Under the Supervision of

Dr. Ravi Shankar Raman

By:-

Vaibhav Kumar Bhaskar Yoginder Pal

Saurabh Tripathi Sparsh Kataria

Raj Gaurav Panday

2 of 35

Contents

  • 1Introduction
  • 1.1 Six Sigma
  • 1.2 Literature Survey
  • 1.2 About the company

​

  • 2 Objectives

​

  • 3 Methodology
  • 3.1 Introduction.
  • 3.1.1 DMAIC technique.

2

3 of 35

Continued...

4 Implementation of DMAIC

  • 4.1 Define
  • 4.2 Measure
  • 4.2. 1.Data Collection
  • 4.2.1(a)X bar and R bar Chart
  • 4.3 Analyze
  • 4.3.1 Pareto Chart
  • 4.3.2 Cause and Effect Diagram
  • 4.4 Improve
  • 4.5 Control
  • 5 Bush and Machines used
  • 6 CONCLUSION
  • 7.REFRENCES

4 of 35

Introduction

4

Six Sigma is a set of techniques and tools for process improvement.

It seeks to improve the quality of the output.

It uses a set of quality management methods.

A Six sigma process is one in which 99.74% of al opportunities to produce some feature of a part are statistically expected to be free of defects.

DMAIC is used as the part of six sigma in the project.

5 of 35

Literature Survey

Ravi Shankar Raman at el[1] as discussed, that DMAIC is a methodology which is used to identify the root causes because of which the defects are caused. The Six Sigma Methodology is one of the systems which helps in the decline of the ongoing number of disfigurements of the solicitation for 3.4 flaws per million significant entryways in the arrangement of the thing, creation besides, the organization collaboration (Schroeder et al., 2009). The Six Sigma is a conscious and facilitated decisive reasoning instrument for key systems, new thing and organization progression that depends upon the utilization of the consistent strategies to further develop the outcome factors. The research is in the focus of the quality improvement of the process of the capacitor manufacturing through 6 sigmawere the analysis is taken place in a manufacturing company.

​

Mr. Amit Verma at el[2] as discussed Six Sigma is an amazing top notch improvement business system that engages relationship to use essential yet surprising dependable techniques to depict, measure, research, improve and control process for achieving useful significance. The Six Sigma strategy is an inconceivable additionally, adaptable course of action of achieving, keeping up and widening the business accomplishment. Six Sigma is dominatingly chosen figuring out the client's essentials and need, organized

5

6 of 35

Continued...

of real factors and appraisals assessment, and prepared strategy for making due with organizing, improving and setting up another business, social event and affiliation measures. Six Sigma's part in the absolute of this is to help the board with making the most super productive using least resources. In this research the main objective is how to implement the six sigma in the manufacturing industries

​

Dr. Yadavalli Basavaraj at el[3] as discussed, a suitable execution of this business procedure can provoke inconceivable advantages. The characteristic of this study is to draw out the advantages and to incite focuses that passing units should on to remember. It is an endeavor to follow the latest things on Six Sigma in trading units, which faces a general test. As indicated by Natha et.al

[4] the evaluation philosophy was made by seeing the fitting information source, articulation and picking different case endeavors from different papers in which suitable execution of Six Sigma in a conveying unit was introduced and point by point. In this the main focus is on implementing the 6 sigma on exporting industries.

7 of 35

Continued…

7

Raluca NICOLAE (MĂNESCU) at el[4] as discussed,into an alliance it can

apply different procedures to furthermore cultivate the thing quality for checking and appraisal of gathering processes, to show that by holding under control the cycles it gets an improvement concerning nature of present-day things. In this paper, utilizing the

outline Pareto, the distortions are checked on for a social event association of a drill with CMS exchangeable plates.

​

Yadavalli Basavaraj at el[5] as discussed, to confine the blemishes in

general, plan fishbone outline which shows all of the vital drivers of surrenders and starting there investigate through pareto frame. Before long follow a spellbinding development to lessens the disfigurements and work on the all around nature of the capacitors. This research is done by using mainly the pareto chart and fish bone diagram to identify the defects, reduce them and increase the quality

8 of 35

About the company

NK INDUSTRIES was established in 2000 .

It is a small-scale company based on customized mass production and individualization.

It produces the multiple range of materials precision turned components ex bolts, bush, nuts,pin etc

It has three sections raw material section, manufacturing section, finished product section.

It has highly skilled labours and good management.

9 of 35

Process Map of MetalizedSection

Raw material order(MS freecutting,lubri cant oil etc)

Raw material visual inspection(dim ensions,quality)

Raw material weight calibration

Fabrication of product on TRAUB M/C

Tapping Operation

Cleaning of product

Finished product collection

Visual inspection of finished product

Packing

Dispatch

10 of 35

Objectives

10

To identify root causes of Bush defects and their

remedial actions.

To Improve the Bush manufacturingprocess.

To achieve our objective we concentrate on 3 primary factors W hat, W here and W hy.

WHAT: Improve the Bush manufacturing quality.

WHERE: NK Industries.

WHY:

  1. Reduction in CustomerReturns.
  2. Enhanced productivity.
  3. Customer satisfaction
  4. Improvement of service level.

11 of 35

Methodology Used

11

12 of 35

CONTINUED...

12

DMAIC

  • Define the system, the voice of the customer and their requirements, and the project goals, specifically.
  • Measure key aspects of the current process and collect relevant data.
  • Analyze the data to investigate and verify cause-and-effect relationships.
  • Improve or optimize the current process based upon data analysis.
  • Control the future state process.

Some of the tools used in DMAIC are Brainstorming, Mistake Proofing, Design of Experiments, Pugh Matrix, House of Quality, Failure Modes and Effects Analysis (FMEA), Simulation Software etc.

13 of 35

Define

14 of 35

SIPOC

Supplier

Inputs

Processes

Output

Customer

Mild Steel Rod

Supplier

Mild steel Rod

  • Visual inspection
  • Raw material Inspection
  • Machining

Machined Bush

Manufacturing

industries

15 of 35

Measure

16 of 35

Data collection plan

In the process of data collection, we have considered 5 lots

of manufactured bush

These three lots are taken at an interval of 2 hour

s each .

Every lot contains the 10 bush, so the analysis is done

on 50 bush

We have done the analysis of radius on 30 bush.

The table on next slide contains the data of analysis of rad

ius and their readings

17 of 35

Data Collection

Sample No.

I

II

III

IV

V

1

20.96

19.52

20.56

19.23

20.11

2

20.98

19.42

20.94

18.98

19.11

3

20.97

20.98

21.63

20.8

21.2

4

20.96

20.96

20.97

20.7

21.32

5

20.97

21.04

19.56

20.9

19.42

6

19.22

20.94

20.97

21.32

19.98

7

20.96

22.32

21.35

21.11

22.35

8

21.05

21.08

20.98

21.06

20.88

9

21.06

21.02

22.36

20.78

22.56

10

20.98

19.42

19.84

20.66

21.23

18 of 35

X bar and R bar Chart

19 of 35

Process Capability Chart

20 of 35

Analyze

21 of 35

Cause and Effect Diagram

22 of 35

Various Rejections

22

The main rejection which was observed was the radius of the Bush. Our project is also done to control the rejection of Bush with help of DMAIC .

The radius of bush was coming more the size provided many times in our analysis

The other defects which can be neglected are:-

-length

-surface finish

-bur in thread

-external thread

23 of 35

Pareto Chart

24 of 35

Improve

25 of 35

Data collection after improvement

Sample No.

I

II

III

IV

V

1

21.56

20.92

20.96

21.11

20.98

2

20.22

20.76

21.68

20.65

21.03

3

20.97

21.63

21.63

22.65

20.98

4

20.96

20.96

20.97

21.88

20.88

5

20.12

21.04

22.32

21.09

20.38

6

20.98

20.94

20.97

21.08

20.98

7

20.96

21.09

20.96

20.88

21.69

8

21.65

21.08

20.36

20.98

20.88

9

22.03

21.02

20.96

20.78

21.23

10

22.55

20.65

21.56

20.12

20.32

​

​

​

​

​

​

26 of 35

27 of 35

Control

Control phase is basically the application of solutions directed by the process enhancement and improvements by the team, where they discuss the solving technique to sustain the improvements. By making control charts, documentation, communicating with all who are included and will affect the process improvement and discussion of directions and guidance or suggestion is some of the main aspects of the control phase

28 of 35

BUSH

28

29 of 35

Different types of machine used in the production

1.Center Less Grinding machine

2.Taping Machine

3.Slotting Machine

4.Drilling machine

5.Traub Machine

30 of 35

DIFFERENT PARTS OF TRAUB MACHINE & SETUP

Loop tool holder

Collet and tools

Controller

Drum set

Tool Shaft

Gear setup

Machine speed and gearing rules

31 of 35

Traub Machine

Traub machine is mostly used

for manufacturing of metal turned parts. many field are been benificiated by it. some items manufacture on traub are washers, nut, bolts, pins, studs etc all these item can be manufactured in different sizes andtype as per requirement.

31

32 of 35

Working of TRAUB Machine

The traub machine has 4 tool station, loop tool holder and a driller slot by which different types of operations are performed ,first the settings of tool station is set which is dependent on product ,the number of operations needed ,the controller according to dimension of the product ,the timing of each tool so that they don't collide during any operation and then the speed and revolution parameters is decided which depends on the product size and its hardness for example a product size is small then the speed can be 98 piece per hour or even can be increased to 180 piece per hour but if piece is large then the machine speed should be decreased and in case of revolution harder the material lesser will be the revolution.smaler the size greater the speed of machine and harder the raw material revolution per minute will be decreased which result in speed decrement. After setting parameters the ms free cutting rod is operated on the machine and primary drumset allow the length of rod which is to be operated to make first piece through the collet and and now each tool station do their operation by inward and outward movement. the shafts and drumset are responsible for this movement, the drum at every 220degree move inward and then outward ,the worker also keep in mind that all the operation on product should be done in one full rotation of drum otherwise the tool will break and machine will not function.

33 of 35

References

33

  • [1] Ravi Shankar Raman and Yadavalli Basavaraj Defect reduction in a capacitor manufacturing process through Six Sigma concept: A case study Management Science Letters 9 (2019)

​

  • [2] Dr. Ravi Shankar Raman1 & Mr. Amit Verma2 Application and Implementation of Six Sigma in Manufacturing Industries: A Review JOURNAL OF ENGINEERING, COMPUTING & ARCHITECTURE Volume 10, Issue 10, 2020

34 of 35

Continued…

34

  • [3] Dr. Yadavalli Basavaraj, Aditya Prakash, Akash Garg, Ravi Shankar Raman, Analysis of Six Sigma Methodology in Exporting Manufacturing Organizations and Benefits Derived: A Review 3 rd IEEE International Conference on "Computational Intelligence and Communication Technology" (IEEE-CICT 2017)

​

  • [4] Raluca NICOLAE (MĂNESCU), Anişor NEDELCU, Adela-Eliza DUMITRAŞCU ”Transilvania” University of Brasov, Romania IMPROVEMENT THE QUALITY OF INDUSTRIAL PRODUCTS BY APPLYING THE PARETO CHART Review of the Air Force Academy No 3 (30) 2015

​

  • [5] Ravi Shankar Raman, Yadavalli Basavaraj quality Improvement of Capacitors through Fishbone and Pareto Techniques International Journal of Recent Technology and Engineering (IJRTE) ISSN: 2277-3878, Volume-8 Issue-2, July 2019

35 of 35

THANK YOU.