MANAGEMENT OF A CONSTRUCTION �PROJECT�
AIM & OBJECTIVES��Aim: ANALYSIS OF INTERIM CLAIMS & COST VALUE COMPARISONS��objectives: �At the end of the lesson, the students should be able to:�
1) Identify best practices for managing interim claims.
2) Analyse the impact of accurate cost value comparisons on project outcomes.
ANALYSIS OF INTERIM CLAIMS
3
INTRODUCTION
4
ANALYSIS OF INTERIM CLAIMS
5
Preliminary Items
ANALYSIS OF INTERIM CLAIMS
6
Measured work by trade or element breakdown
ANALYSIS OF INTERIM CLAIMS
7
Nominated subcontract values
ANALYSIS OF INTERIM CLAIMS
8
Materials on site
SELF-ASSESSMENT TASK
9
SCENARIO
Project team can apply each of these cost elements to budget and control expenditure: preliminary items, measured work by trade, nominated subcontract values, and materials on site.
TASK: For each element,
Cost
Value
Comparisons
10
COST VALUE COMPARISONS
COST FROM MANAGEMENT INFORMATION SYSTEMS (MIS)
MONTHLY VALUATIONS RECONCILED WITH PROJECT COSTS
11
COST VALUE COMPARISONS
12
CASH FLOW FORECASTING
COST VALUE COMPARISONS
13
PROFIT AND LOSS PROJECTIONS
EXAMPLE – PROFIT & LOSS
14
SCENARIO
For a domestic single‑storey extension project, you are given summary financial data for two work packages: (1) groundworks and (2) roof construction.
TASK
Using the monthly construction profit and loss template provided,
Given data:
Given data:
SOLUTION – PROFIT & LOSS
15
SELF-ASSESSMENT TASK (PART A) – PROFIT & LOSS
16
Project Overview
You are the quantity surveyor for a small construction firm undertaking a single-storey rear extension to a semi-detached house in Cardiff, UK. The total contract value is £120,000, with the project spanning 4 months (January to April). The extension includes groundworks and foundations, external walls, roof construction, mechanical and electrical (M&E) installations, internal finishes, and external works (such as paving and drainage). The firm has allocated overheads and other expenses across the project based on historical data.
Task for Students
Using the provided profit and loss spreadsheet (focus on the Monthly Profit & Loss sheet for January to April), complete the profit and loss statement for the entire project. Enter the revenue (from billing milestones) and job costs for each building element as a separate "Job" (e.g., Job 1 = Groundworks, Job 2 = Walls, etc.). Allocate overhead expenses proportionally across the months (total overheads £8,000; assume even distribution of £2,000 per month). Calculate gross profit, total expenses (including overheads), and net profit/loss for the project.
SELF-ASSESSMENT (PART B) – PROFIT & LOSS
17
Revenue (Total Contract Value Breakdown by Element – Billed Monthly):
Total for project (January-April): £8,000
References/Bibliography