FMEA –Failure Mode and Effect Analysis
FMEA is the analysis of potential failure of a product or process that affects the function partially or completely
Types of FMEA
Design FMEA
Failure modes and then ranking failures according to relative impact on the product.
Process FMEA
Priorities according to the relative impact on the internal or external customer.
Customer.
RPN (Risk priority number) = Severity X Occurrence X Deduction
Cause
Failure mode
Effect
Control
Process
Calculate
RPN
Re-calculate
RPN
Recommended action, if need.
an unacceptable risk and must be reduced.
Define
S, O, D
1) Specifying possibilities
Stages of FMEA documentation
2) Quantifying Risk
3) Correcting high causes
4) Re-evaluating Risk
| | | | | FAILURE MODE AND EFFECTS ANALYSIS | | | | | |
| |||||
| | | | | | | | | | | | | | | |
|
Item: |
| | Responsibility: |
| | FMEA number: |
| |||||||||
Model: |
| | Prepared by: |
| | Page : |
| |||||||||
Core Team: |
| | FMEA Date (Orig): |
| Rev: |
| ||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Process Function | Potential Failure Mode | Potential Effect(s) of Failure | Sev | Class | Potential Cause(s)/ Mechanism(s) of Failure | Occur | Current �Process �Controls | Detec | RPN | Recommended Action(s) | Responsibility and Target Completion Date | Action Results | ||||
Actions Taken | Sev | Occ | Det | RPN | ||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| | | | | FAILURE MODE AND EFFECTS ANALYSIS | | | | | |
| |||||
| | | | | | | | | | | | | | | |
|
Item: | Drill Hole | | Responsibility: | AAA | | FMEA number: | 123456 | |||||||||
Model: | Current | | Prepared by: | BBB | | Page : | 1 of 1 | |||||||||
Core Team: | AAA (Engineering), BBB (Production), CCC (Quality) | | FMEA Date (Orig): | 1/1/2021 | Rev: | 1 | ||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Process Function | Potential Failure Mode | Potential Effect(s) of Failure | Sev | Class | Potential Cause(s)/ Mechanism(s) of Failure | Occur | Current �Process �Controls | Detec | RPN | Recommended Action(s) | Responsibility and Target Completion Date | Action Results | ||||
Actions Taken | Sev | Occ | Det | RPN | ||||||||||||
Drill Blind Hole | Hole too deep | Break through bottom of plate | 7 |
| Improper machine set up | 3 | Operator training and instructions | 3 | 63 |
|
|
|
|
|
| 0 |
| Hole not deep enough | Incomplete thread form | 5 |
| Improper machine set up | 3 | Operator training and instructions | 3 | 45 |
|
|
|
|
|
| 0 |
| hole missing | Tool life | 5 |
| Broken Drill | 5 | None | 9 | 225 | Install Tool Detectors | BBB | 3/1/2021 | 5 | 5 | 1 | 25 |
|
|
|
|
|
|
|
|
| 0 |
|
|
|
|
|
| 0 |
|
|
|
|
|
|
|
|
| 0 |
|
|
|
|
|
| 0 |
Benefits of FMEA