Foundation Build Detail
Procedure
Slight overlap on each corner as boards are >16’
Inset 2” so that level stakes can be added
String on stakes detail
As Built
Procedure
Shallow Frost Protected Footer Strategy
Frame up, then fill inside.
Concrete Quantity
Real Life
Grade is set for 32’x64’ area. First, verify grade with laser.
Make forms- 16’x32’.
2x8 lumber
8”
Wedge to elevate foundation form. Poly if need to close leakage gaps
Mark 4 corners with rebar stakes. Use string, triangulating for a perfect square.
String
Gravel
Remove string on gravel side, rough spread gravel.
2x4 stakes, 16” long
14”
Dig 14” footers
Shallow Frost Protected Footer Strategy - 2
Dig 14”
Test and bury plumbing
Spread gravel including under footing. Scree the gravel with a board to get 4” thickness. Compact the gravel. Put in the box for the plumbing exit under the tub.
Add insulation, screw in to forms from the outside. Add the mudsill anchors, screw them to the top of form and top of insulation.
Add vapor barrier. Add aperture 16” long and 15” wide inner dimension after wood form, using 2x8 lumber. Needs tub overflow pipe to be shortened 2”. Add slab thickening under stairs. Add rebar. Add chairs..
Shallow Frost Protected Footer Strategy - Original Idea
Frame up, then fill inside.
Grade is set for 32’x64’ area. First, verify grade with laser.
Make forms- 16’x32’
2x8 lumber
10”
8”
Dig 10”
Wedge if need to elevate foundation form, or poly if need to close leakage gaps
Dig 14”
Test and Place plumbing
Mark 4 corners with rebar stakes. Add string, triangulating for a perfect square.
String
Gravel
Shallow Frost Protected Footer Strategy - Original Idea
Frame up, then fill inside.
Grade is set for 32’x64’ area. First, verify grade with laser.
Make forms- 16’x32’
2x8 lumber
10”
8”
Dig 10”
Wedge if need to elevate foundation form, or poly if need to close leakage gaps
Dig 14”
Test and Place plumbing
Mark 4 corners with rebar stakes. Add string, triangulating for a perfect square.
String
Gravel
Form Design - Top view
Cover screws with tape to get them out later
Stake
2x8 formwork
2x8 supports every 3-4 feet
Future notes - 3D printed forms for Rosebud, ¼ the concrete used. Rosebud uses 10 yards. Back to stem walls with spread footer. They are designed to hold insulation, rebar supports, and stakes. They are also designed to hold insulation, and to protect the insulation afterwards, thus minimizing the labor associated with the foundation significantly.
Heated
Unheated
Future Work - Solar Concrete
Future notes - 3D printed forms for Rosebud, ¼ the concrete used. Rosebud uses 9.7 yards. Back to stem walls with spread footer. They are designed to hold insulation, rebar supports, and stakes. They are also designed to hold insulation, and to protect the insulation afterwards, thus minimizing the labor associated with the foundation significantly.
For Rosebud, we need 1 cu ft of concrete per foot of foundation length - or 32+32+15+15 - or 94 cu ft. Total of 3.5 yards of concrete, and this can be self-poured.
45 bags of 80 lb readimix.
60 60 lb bags. $3.30/bag - $198.
Portland - $11/94 lb.
7 bags of portland - $77 + $20 + $20- around $117 in materials if you mix your own. Thus, about $400 in materials for the foundation.
Put the savings into running PEX under the floor for a high quality living experience.
How about solar concrete?
1:7 ratio, 14% concrete.
The foundation would need to be engineered, as we’re using 1450 psi lime concrete if no pozzolanic material is added.
Also - pad foundation accepts 1450 psi C10 concrete. Idea
Heated
Unheated
4” gravel
4” gravel
6” Lime
Concrete
Pad
Backfill
Frost Protected Shallow Foundation v2
technical: foundation: slab-on-grade: construction detail
frost protected shallow foundation - v1
Do we need to seal panel?
New Foundation Detail - Part 1 - Formwork
Design
8” Flashing ends at form
Insulation 18” Tall
2” EPS
Graded, Compacted Grade
2x8 Foundation Form
18”
4” slab
4” gravel
10”
12”
12” Cement Board
Needs sharp shovel
Mudsill Anchor
New Foundation Detail - Part 2 - Forms are 32’x16’ on the Inside
Design
Graded Grade
Infill insulation
10” pvc flashing
(16.5 min)
10”
8”
8”
20” total of insulation
Needs sharp shovel to cut soil down
15” Distance from grade to last bend
4” below graded grade. 12” strips of cement board appear to be the best choice.
Flashing
Note that pressure treated lumber corrodes aluminum and galvanized steel.
Flexible flashing can be non-adhesive, so it can be applied at any temperature. The word is that the adhesive should not be relied on for moisture blocking.
Final Finish
Landscape fabric +
gravel
Up to 2’ away from the house keeps weeds from growing next to the house, and makes any termite infestation visible.
Termites and Rodents
Control Joints for Concrete
How to test soil under slab?
Soil Testing
Where to put them?
Cold Temp
Build Up
Frame up, then fill inside.
Frame up, then fill inside
Lay 4” waste pipe to 4’ outside of foundation. Slope down 1” over 8’ per plumbing detail.
Option 1 In Full Detail
Soil Moving
Add soil to raise pad. Tamp it with tractor
Soil moving requires 3 steps: digging, depositing, and leveling at end. Final grading step requires a lot of soil
Forms, Anchors, Stubs
14”
Pour, Insulation, Poly Flashing
18” form
Vapor Barrier + 4” Gravel.
Terminate gravel 2’ out from pad
Backfill
Level backfill
Option 2 In Full Detail
Dig down with Lifetrac. Pad is already tamped.
Soil moving requires 1.5 steps: digging and depositing pile at end of side.
Dig and bury the stubs and water line
Pour, Insulation, Poly, Flashing above poly
4” Gravel, vapor barrier, forms, anchors.
Level backfill
14”
18” form
18”
Need to backfill 2” to get bottom of footer 12” below grade
Option 3
Dig down 12”. Pad is already tamped.
Insulate.
Bury.
Edge may be troublesome
So dig down and make 18” forms -
Next Steps
Soil Moving
Add soil to raise pad. Tamp it.
Lay 4” waste pipe to 4’ outside of foundation. Slope down 1” over 8’ per plumbing detail.
Option 1
Option 2
Dig down with Lifetrac. Pad is already tamped.
Soil Moving
This still leaves final sloping step to be done at end.
Can we get away from final sloping step? Option 2 minimizes the final bury step.
Soil moving requires 3 steps: digging, depositing, and leveling at end. Final grading step requires a lot of soil
Soil moving requires 1.5 steps: digging and depositing pile at end of side.
Pad
32x64
Pad, 16x32
48’
16’
1
2
3
4
Foundation Actual Build - Gravity Pond
Soil Moving
1
2
3
5
71.6’
4
6
64’
32’
2
Foundation Actual Build
Add soil + removal area becomes pond
Grade to flat. Runoff not considered here yet.
Slopes down unless area is flat.
Stake area of house + 8’ and determine level
To stake area:
1
2
3
5
71.6’
4
6
64’
32’
Foundation Detail
14”
Add soil to raise pad. Tamp it.
Lay 4” waste pipe to 4’ outside of foundation. Slope down 1” over 8’ per plumbing detail.
Vapor Barrier + 4” Gravel.
Terminate gravel 4’ out from pad
Add soil + removal area becomes pond
Grade to flat. Runoff not considered here yet.
Slopes down unless area is flat.
Stake area of house + 10’ and determine level
Final Stub locations
1” tolerance to wall
13.5” + 5.5/2 = 13.5+2.75 = 16.25”
22.5”
27.8”
27.8”
27.8” OC
Waste Pipe
House Base
32x16 Including insulation
Red is stake for foundation corner
31’8”x15’8”
Tub starts 3.5” down from stake
Tub is 60” long so it ends 63.5” down from stake and midline of tub is 18” in from left (14.5” from edge of tub).
Waste pipe (4”) has 4.5” OD and is 0.5” from end of tub, so pipe begins at 64” on edge from Corner Stake
48.5” from according to this
(Framing is 2x6 for water utility wall)
One Stick of 4”
Tub
Plumbing Rough-in
Shower Drain
Foundation
Form, EPS, Stubs, and Pour
14”
Lateral EPS, Poly, Flashing
Lateral EPS, Poly, Flashing
18” form
Add soil + removal area becomes pond
Grade to flat. Runoff not considered here yet.
Add soil to raise pad. Tamp it.
Slopes down unless area is flat.
Lay 4” waste pipe to 4’ outside of foundation. Slope down 1” over 8’ per plumbing detail.
Vapor Barrier + 4” Gravel.
Terminate gravel 4’ out from pad
Shallow Frost Protected Footer, 500 SF
Gravel Calculation
36x20
Shallow Frost Protected Footer, 500 SF
32x16
16x20
16x16
52’ long by 2’ wide
52*2+16*2=136 feet long
?
Seed: Drains & Vents
W/D
up
DW
Ref
20”
5.5”
15.5”
15”
15”
24”
24”
113.5”
60”
24”
18”
240”
vent stack
105”
2” rigid insulation
Factor e Farm : Rosebud
Water Shutoff
Can we stand tub on top of the floor, so we nee no foundation complication?
No, because somewhere the drain must go below floor.
Not 60 but 60 + wall
Plumbing Test - This is what the building inspector looks at:
Use 90 degree elbows for water to prevent water line kinks
Check out this auto ladder lift:
Vinyl flooring - tongue and groove - $1.40/sf
Ergonomic Analysis
Compact It + Vapor Barrier + 4” Gravel
Form, EPS, Stubs, and Pour
14”
Lateral EPS, Poly, Flashing
Lateral EPS, Poly, Flashing
Case of 1000 sf foundation: Grade and pile dirt in middle. Dirt is 1160 cu ft - 200 cu ft for edge so about 1000 cu ft, or 37 cu yd. Soil comes from future Gravity Pond.
Grade
Backhoe
18” form
Uninsulated - Below Frost Line
Shallow Frost Protected Footer
Advantage - does not need to rip up area around footer for earthworks of the insulation burial. But, if we are building up from flat for SFPF, then there is no additional earthworks for the insulation - the insulation is laid on grade.
Mudsill Anchors - 26 Total
Updated for very final layout?
8 - corners
4 - ends of boards
6 - around doors
8- 6’ runs
TOC
Slab on Grade - Frost Protected Shallow Footer
Slab on Grade - Frost Protected
Compact It + Vapor Barrier + Gravel
Form and Pour
12”
Polishing Concrete
Raft Slabs
Slab Foundation
Leveling
With Footer
Other details