1 of 86

RPI Force 1 Final Presentation

MPS Student Team: Fall 2021-Spring 2022

2 of 86

Content

  • Project Summary
  • Overall Challenges
  • Manufacturing
  • Assembly
  • Budget

3 of 86

Our Team

Aksen, Michael

Assembly Engineer

Barbee, Ammar

Information Manager, TDP Co-Manager

Bhimani, Kevin

Co-Assembly Manager, Plastics Engineer

Deiros, Eric D.

Co-Assembly Manager

Gallagher, Ava S.

TDP Co-Manager, Robot Programmer, Plastics Engineer

Grinberg, Benjamin

Plastics Engineer

Interian, Gabriela

Assembly Engineer

Pirovano, Alex

Financial Manager, Packaging Manager

Raheb, Joseph S.

Manufacturing Manager

Sarmiento, Aaron

Manufacturing Engineer, TDP Co-Manager

Stotz, John

Project Manager

4 of 86

Project Overview

5 of 86

6 of 86

Semester Overview

January

February

March

April

May

  • New team formed
  • Improvements to CAD with better tolerancing
  • Manufacturing plan thoroughly developed
  • SOPs developed
  • Prototyped/simulated production
  • TDP Updated
  • Mid-term presentation
  • Manufacturing began
  • Assembly fixtures started to be produced
  • Manufacturing ends
  • Assembly fixtures finalized
  • Assembly SOPs developed
  • Began assembly of subsystems
  • Final Assembly
  • Final TDP submitted
  • Final presentation
  • 300 planes assembled

7 of 86

Overall Challenges

  • COVID
    • Multiple team members caught COVID and had to isolate
    • Transferred responsibility to in-person students
  • Delays
    • Many parts had oversights that the team corrected
    • As a result project fell behind schedule
    • Team members worked extra time to get on schedule
  • Scheduling
    • Team members had other commitments, making scheduling difficult
    • Created weekly schedules with input from team members

8 of 86

Manufacturing

9 of 86

Top Fuselage

10 of 86

Bottom Face Machining

  • Run Time: 4:09
  • Material: 1 Inch Square 6061 Aluminum Bar Stock
  • Machine: Haas VF2 CNC Mill
  • Fixturing: Standard Vice
  • Tooling:
  • 3” Face Mill
  • ⅛” Carbide Drill Bit
  • #10-24 Threadform
  • #18 Drill
  • ½” Flat End Mill
  • ¼” Flat End Mill
  • ⅛” Ball End Mill
  • ⅛” Flat End Mill
  • ¼” Ball End Mill

11 of 86

Bottom Face Machining

  • Notable features: Two ¼”-20 �threaded holes for interfacing �with the 4th axis fixture
  • Post Process: Break and deburr all�sharp edges
  • 100% inspection of locator holes
    • .125” and .130” pin gages
    • Go/No-Go style
  • 100% inspection of PCB cutout
    • Digital calipers to check width
  • 1 part per operation

12 of 86

4th Axis Design

Subplate

Mitee-Bite

Problems:

  • Chatter
  • Clamping Force

13 of 86

4th Axis Design - Modifications

  • Locator pins installed on main body
    • Greater locational constraint to reduce chatter
  • Countersunk screws (shown) replaced with cap head bolts
    • Allowed for more thread engagement with the subplates

14 of 86

4th Axis Design - Modifications

  • Mitee-Bite clamps found to not apply adequate force to hold part
    • Replaced with ¼-20 cap head screws for more clamping force

15 of 86

4th Axis - Top Fuselage Machining

  • Run Time: 34:00
  • Machine: Haas VF2 CNC Mill
  • Fixturing: 4th Axis
  • Tooling:
  • 1” Face Mill
  • ¼” Ball End Mill
  • ⅛” Ball End Mill
  • ¾” Ball End Mill

16 of 86

4th Axis - Top Fuselage Machining

  • Notable features: Window and �windshield for aesthetic purposes
  • Post Process: Break and deburr all�sharp edges
  • Qualitative visual inspection of all �parts
  • 4 parts per operation
  • Lead to inconsistent surface finish
    • Rock tumbled for 3 hours to provide�even finish and darker coloration

17 of 86

Lessons Learned

  • Design for manufacturing
    • Bottom face surfacing operation was long and could have been eliminated by modifying wing subassembly
  • Value of time
    • A difference of 6 seconds per part means a half hour of labor, this scales up quickly
    • Optimized MasterCAM to minimize machining time

18 of 86

Plastic Injection Molded Parts

19 of 86

Mold

  • Runners were placed close together
  • Easier to mold in one shot
  • Injection pressure > clamping force
  • Decreased shot size

20 of 86

Flashing from Injection Pressure → Clamping Force & Oversized Inserts

21 of 86

Effect of Undershot Parts

22 of 86

2 Wings Assembled Together

23 of 86

Bottom Fuselage Challenges

  • Design changes were not incorporated into the mold
  • Screw hole height interfered with wing placement
  • Required an extra facing operation on the mill

Decreased height

24 of 86

Turning

25 of 86

Spinner & Wheels

  • Machine: ST-10Y Lathe
  • Tools:
    • T2: 35° Facing Tool
    • T4: Grooving tool
    • T8: #7 Drill (spinner)
    • T10: #29 Drill (wheels)
    • T12: .118” Angled Parting Tool
    • T13: Bar Puller
    • 0.5” Collet
  • Material: 6061 Aluminum, OD 0.5”

Turning: Drilling:

26 of 86

Mastercam

Spinner

Wheel

Cycle Time: 3 minutes

Output: 3 spinners

Cycle Time: 1 minute, 33 seconds

Output: 3 wheels

27 of 86

Quality Control

Spinners

  • 100% inspection of drilled hole
    • .200” and .202” pin gages
    • Go no-go style
  • Every cycle hole depth
    • 1 spinner per cycle
    • Digital Caliper
  • Every 1st, 10th, 25th, 50th, 75th, 100th… cycle spinner height
    • 1 spinner per request
    • Digital Calipers

Wheels

  • 100% inspection of drilled hole
    • .1295” pin gage

28 of 86

Design Changes

Spinner

  • Machining to a point is difficult, forces cause the part to break-off
  • Spinner is flat on both ends
  • Requires a sanding operation

Wheels

  • Inner fillets are difficult to cut
    • Changed to flat inner groove
  • Initial parting speed forces causes premature breaking
    • Reduced parting speed to compensate

29 of 86

Lessons Learned

  • Small Part Collection is Not Easy
    • Parts were often lost in the lathe area among the shavings
    • Basket and holed sheet metal helped mitigate issue, but parts still fell into chip conveyor

30 of 86

Lessons Learned

  • Faster Turnaround Time = Less Time for Quality Check
    • Quality control was done while another cycle was running
    • The short run times made the more intensive quality checks pile up parts
  • Small Errors on Small Parts = Big Changes
    • For the wheels, the through hole drill bit was incorrectly set for the first runs resulting in wheels with off-centered holes
    • An incorrect insert for the spinners vibrated the tool causing every 2 parts to be smaller in every dimension

31 of 86

Wheel Wire Forming

32 of 86

Wheel Wire Forming: Altair Inspire Simulation

  • Support planes fuselage
  • Steel vs Aluminum
  • Simulation demonstrates no failure points for Steel

33 of 86

Wheel Wire Manufacturing

  1. Cut ⅛” dia SS 304 wires from spool using Foot Shear

2. Grind wire ends to smoothen the ends

34 of 86

Wheel Wire Manufacturing Continued

3. Place wire in die and bend the wire using Arbor Press station

4. Quality check: place through two quality control gauges to inspect quality of the wire

35 of 86

Tooling: Wheel Wire Die

Components:

  • Top Die Components
  • Base Die Components
  • Alignment Brackets
  • Alignment Wall
  • Arbor Press End Rod
  • Base Plate
  • Fasteners

36 of 86

Wheel Wire Calculations

Die Clearance Equation [1]

S0=Surface Thickness (⅛”)

Springback Equation [1]

  1. “Metal Working Lab - Deep Drawing.” RPI MANE, Troy, NY.

Sample Die Clearance Calculation: UD=(1.1-1.2)So=1.12*0.125=0.14"

Ri = 0.396”, αi=89.04o

Sample Springback Calculation:

37 of 86

Assembly

38 of 86

39 of 86

Spinner Propeller Subassembly

40 of 86

Overview

  • Staubli Robot Arm
  • Feeder Tooling
    • Spinner Pallet
    • Propeller Pallet
  • Press Fit Tooling
    • Pallet
    • Plate
    • Piston
    • Bracket

Force to Press:

41 of 86

Feeder Tooling

42 of 86

Press Fit Tooling

Press-fit Pallet

Locator Pins

Piston

Bracket

Piston Connector

Press-fit Plate

Press-fit Bars

43 of 86

44 of 86

Process Overview

  1. Press fit pallet will arrive at location 1
  2. Robot will begin to load spinners onto press fit pallet
  3. Robot will load propellers on top of spinners
  4. Press fit pallet is released from location 1

45 of 86

Process Overview

5. Operator ensures that propeller pegs are aligned with the spinner hole

Before & after alignment

46 of 86

Process Overview

6. Press fit pallet arrives at location 2

7. Piston presses propellers into spinners

8. Press fit pallet is released from location 2

47 of 86

Process Overview

9. Operator checks gap

48 of 86

Quality Control

  • 100% inspection of spinner propeller interface gap
    • Feeler gage to 0.050”
    • Go no-go style

49 of 86

Challenges

  • Weighing gap versus quantity per cycle
  • Finding location for best press
  • Losing air pressure due to tubing available at the MILL

.013” gap

.035” gap

50 of 86

Lessons Learned

  • Importance of aligning components
  • Importance of testing set-ups
  • Break up goal into smaller tasks
    • Makes testing and debugging easier

51 of 86

Wheel Wire Subassembly

52 of 86

Assembly: Parts and Fixture

Alignment Block

Assembly Die

53 of 86

Assembly of Wheel wire

Wire fixed to assembly fixture

Inner push nut alignment

Push nut slid into the wire

Push nut touches fixture surface

54 of 86

Assembly of Wheel wire: Continue

Wheel and slid into the wire

Outer push but alignment

Push nut slid into the wire

Push nut touches wheel surface

55 of 86

Assembly of Wheel wire : Quality Check

56 of 86

Octopuz Simulations

  • Simulation demonstrates the process can be fully automated at industrial scale

57 of 86

Wheel Wire: Lessons Learned & Future Improvements

Manufacturing

  • Designing a forming die
  • Continuous improvement design process

Assembly:

  • Designing the alignment block to accommodate the wheel

Future Improvements:

  • Use pistons for forming, design a progressive die, use tool steel
  • Add longer lever arm for easier forming, Add thinner shims to reduce misalignment
  • Instead of 3D printing fixture can be made using steel to avoid wear

58 of 86

Wings & Horizontal Stabilizer Subassemblies

59 of 86

Overview

  • Adept cobra robot arm
  • Feeder tooling
    • Wing pallet
    • Horizontal stabilizer pallet
  • Welding Tooling
    • Wing welding fixture
    • Stabilizer welding fixture
    • End effector
    • Welding horn

60 of 86

Feeder Tooling

61 of 86

Welding Tooling

62 of 86

63 of 86

64 of 86

65 of 86

Process Overview

  • Pallets will be loaded with wing halves
  • Pallets will be checked for quantity and secured on the workspace using 3-2-1 fixturing
  • Robot will load a concave up wing in the welding fixture
  • Robot will load a concave down wing on top of the previous wing

66 of 86

Process Overview

  • Welding horn will lower to weld the wing halves
  • Robot will wait for prompt to remove welded part
  • Robot will place part in a box for QC and final assembly
  • Robot will iterate through pallets yielding 30 welded wings

67 of 86

Process Overview

  • Operator check hole diameter with gauge pin
  • Operator performs cosmetic QC

68 of 86

Quality Control

  • 100% inspection of welded parts
    • Gaps in wing interface
      • Visual
    • Excessive flashing
      • Visual
    • Hole diameter
      • Gauge pin
      • Go no-go style

Proper

Gap

Misaligned

69 of 86

Challenges

  • End effector design
    • Must reach under the welder to place the part
    • Rigidity
  • Quantity of pins in the feeder for greatest repeatability
  • Losing air pressure due to tubing available at the MILL

70 of 86

Lessons Learned

  • Importance of aligning components
    • Quality control
    • Repeatability
  • Greater tolerance for locator pins
  • Height of alignment components
    • Limit robot’s movements
    • Ensure welding horn doesn’t touch the fixture

Pre-weld

Post-weld

71 of 86

Electronic Subassembly

72 of 86

Electronic Subassembly Overview

Safety Concerns Prevented Soldering from Being Automated

Circuit Diagram

Physical Subassembly

  • Assembly Machines
    • Soldering Iron
    • Third Hand Fixture
    • Wire Length Gauge Block
  • Parts:
    • DC Motor
    • USB-B Breakout Board
    • 10 Ohm Resistor
    • Wires (Red and Black)

73 of 86

Assembly Steps and Quality Control

  • Cut Wires and Resistors to Length and Strip Wires
    • Red = 4.25 Inches; Black = 3.25 Inches; Leads = 0.25 Inches
  • Solder the Resistor to the Black Wire
  • Solder the Red and Black Wire to the Breakout Board
    • Leads Must solder through the BOTTOM of the Breakout Board
  • Solder the Red Wire and Resistor to the DC Motor
  • Fit the Subassembly into the 3D Printed Bottom Fuselage
    • If the Subassembly does not fit, Scrap
  • Plug the USB-B Cable into the Breakout Board
    • If the Motor does not turn, Scrap

74 of 86

Challenges Faced

  • Solder on the top of the PCB could cause a short with the top fuselage
    • Had to solder only from bottom or trim down lead
    • Implemented rework procedure during final assembly in case the short was detected
  • Subassembly Sometimes Break in Full Assembly
    • Overstretching sometimes break soldered areas
    • Implemented rework procedure during final assembly also covers broken subassemblies

75 of 86

Lessons Learned

  • Assemblies Interact with Each Other
    • Remember this for other Projects where Electronics and Metal are Close Together
  • Slack Between Wires is Important for Final Assembly
    • Do Not Trim Wires to their Shortest Length Possible
  • Pre-Cut and Pre-Soldered Wires Speed Up Assembly
    • Adapt the SOP for Future Work

76 of 86

Main Assembly

77 of 86

78 of 86

Challenges

  • Significant force was required to install the top fuselage
    • Discovered that tumbling left a dry powder coat that reduced the size of the hole, significant force required to assembly
    • Deburring the holes reduced the force required to assemble

79 of 86

Packaging

80 of 86

81 of 86

Budget

82 of 86

Part Description

Quantity per Unit

Supplier

Budget ($USD)

Actual Cost ($USD)

Main Body

Top Fuselage Aluminum 6061 Stock (6" per part)

12

Albany Steel

$750.00

$632.50

Bottom Fuselage($125.00 for the cost of the mold manufacturing)

1

MILL

$125.00

$125.00

Propeller ($125.00 for the cost of the mold manufacturing)

1

MILL

$125.00

$125.00

Wing ($125.00 for the cost of the mold manufacturing)

4

MILL

$125.00

$125.00

Spinner ($50.00 for 3 pieces of 6’ stock)

1

Albany Steel

$50.00

$100.00

Stabilizer

Horizontal Stabilizer ($125.00 for the cost of the mold manufacturing)

2

MILL

$125.00

$125.00

Vertical stabilizer (300 for the price of $0.25 each)

1

Piedmont Plastics

$74.82

$185.00

Wheels

Wheels (300 for the price of $0.07 each)

2

Albany Steel or MILL

$42.00

$73.69

Wheel Wire (300 for the price of $0.60 each)

1

McMaster Carr

$180.00

$102.38

Electronics

DC Motor (300 for the price of $0.89 each)

330

MiniScience Inc.

$269.00

$311.00

Pololu USB PCB 2586 (300 for the price of $1.49 each)

300

Digi-Key Electronics

$447.00

$499.15

Resistor (300 for the price of $0.10 each)

330

Digi-Key Electronics

$30.00

$8.00

Insulated Copper Wire (100' of wire in 2 different colors at 25.95/ea)

2

Digi-Key Electronics

$49.30

$51.90

83 of 86

Assembly

Tape (5 yd roll or 15' or 180'' or 3/5" per plane per roll - $12.50/roll)

1

Grainger

$12.50

$12.50

Countersunk Machine Screw

13

McMaster Carr (91771A537)

$62.22

$73.97

O-Ring

7

McMaster Carr (9452K339)

$39.48

$50.61

Push Nut

12

McMaster Carr (94807A024)

$28.53

$114.12

Packaging

Corrugated pads (300 for the price of $0.88 each)

300

Grainger

$264.00

$264.00

Twist tie ($11.99 for 2000)

2000

Staples

$11.99

$11.99

Adhesive Dots ($65.60 for a package of 400)

4000

Grainger

$65.60

$65.60

TOTAL

$2,876.44

$3,056.41

84 of 86

Budget Summary

Total Budget

$3,200.00

Current Spending

$3,056.41

Allocated Budget

$2,876.44

Total Amount Leftover

$143.59

85 of 86

Thank you!

86 of 86

Q&A