GARDENGreener AgRo-fooD logistics in the mEditerraneaN area

5th TRANSNATIONAL ABS STEERING COMMITTE MEETING

6-7 November 2025

Montpellier, France

WP3 – Activity 3.1

Implementation of initiatives for energy transition

Current state and progress of Carcaixent Pilot

Ángel Madrid, Consorci de la Ribera (CRIB)

2 of 11

Pilot Carcaixent��Quick Summary of investments

3 of 11

Charging station for EV

  • Completed work
  • Start-up planned for end November 2025
  • (To coincide with the delivery of the van)
  • Billboard approved by the Head of communication unit

4 of 11

Charging station for EV

5 of 11

100% Electric Van

  • Van delivery scheduled for November 2025.

6 of 11

100% Electric Van

  • Range WLTP combined 25,9 kWh/100
  • We have to buy 2 isothermal boxes with 500 lts capacity

7 of 11

100% Electric Van

  • Rotulation approved by the Head of communication unit

8 of 11

PV PLANT

  • It will be built in Carcaixent football field stands
    • Awarded with 40 kW Power (60 kWp)
    • 100 panels with 600 Wp Power
    • Estimated annual energy production: 82.600 kWh
    • Work will begin on November 10th
    • Conclusion is planned for November 21st
    • Start up is planned for December 2025
    • Billboard approved by the Head of communication unit

9 of 11

LOGISTIC CIRCUIT

  • Carcaixent City Council has created a new, completely free, last-mile sustainable agri-food distribution service, which will begin in January 2026. Staff have been hired to provide this service, funded by the city council's budget.

  • This new service will replace the service provided individually by each of the Municipal Market's stores.

  • It has been necessary to develop operating regulations for the service. Once the service has started, it will be necessary to monitor it and adapt it to any complications that may arise.

  • This regulation specifies the operational flow for a typical day

10 of 11

LOGISTIC CIRCUIT

  • The initial regulation specify:
    • Order placement system via WhatsApp/email
    • Task control sheet using spreadsheet
    • Work order collection schedule (weekdays and Saturday)
    • Daily delivery schedule to the end customer (weekdays and Saturdays)
    • Types of packaging that stores must use
    • Order identification/labeling/cold chain requirements
  • We are currently continuing to work on and improve the definition of the details of these regulations, meeting with the stakeholders involved, with the aim of minimizing any potential problems when the service begins.

11 of 11

Thank you!

Angel Madrid, Consorci de la Ribera