FACILITIES BOND PROGRAM UPDATE 2026
Investing in safe, Modern, and Inspiring Learning Environments
AUGUST 2026
2
SUMMER PROJECTS
Districtwide Campus Improvements & Infrastructure Updates
CURRENT WORK INCLUDES
β
Restroom & utility infrastructure upgrades
β
Health & Safety campus improvements
β
Shade structures & accessibility upgrades
β
Playground, hardscape, & outdoor learning
β
Safety & Infrastructure Focus
Summer projects focused on improving campus safety, functionality, and infrastructure needs
3
Alexander Hamilton Elementary
Completed campus-wide modernization of all student, staff, and kindergarten restrooms, including new fixtures, partitions, sinks, lighting, flooring, wall finishes, plumbing, and accessibility improvements.
Mary W. Jackson STEAM Magnet
Completed modernization of all student and staff restrooms throughout the main campus, Building B, and kindergarten areas. Providing cleaner, brighter, safer, and more welcoming facilities.
Norma Coombs Elementary
Completed campus-wide upgrades to all student and staff restrooms across the main campus, kindergarten, and lower campus, including new fixtures, finishes, lighting, plumbing, and accessibility improvements.
Completed Restroom Photos
Restrooms and Utility Infrastructure Upgrade Projects
Multi-Site Summer Projects
4
Health and Safety
Campus Safety, Accessibility & Outdoor Learning Improvements
KEY HIGHLIGHTS
PROJECT BENEFITS
Improvements will provide safer, more durable, and more comfortable outdoor spaces while extending the lifespan of campus surfaces and reducing heat exposure for students and staff.
IMPROVEMENTS
North Playground
Crack fill repairs on surface, reflective coating, court striping and interactive games
South Playground
Crack fill repairs on surface, updated striping, adding interactive games, surface patching and painting on retaining wall
Howard St. & Staff Parking Lot
Overlay with new asphalt, installing new curb and gutter, re-striping parking stalls, enhanced crosswalk visibility
Project Visualization
Washington Elementary School
5
Project Visualization
KEY HIGHLIGHTS
Playground Health & Safety Project
Existing playground photos
New playground renderings with shade structures
Health and Safety
Campus Safety, Accessibility & Outdoor Learning Improvements
Willard Elementary
School
6
Altadena Arts Magnet
Outdoor Learning, Parking, and Campus Improvements
KEY HIGHLIGHTS
The Altadena Parking and Site Improvements Project includes major campus upgrades designed to improve safety, accessibility, and student learning environments.
Project improvements include:
The upper playground, lower playground, and parking lot will open in phases.
Playground Design Diagram
7
Site Plan: Fencing Diagram
KEY HIGHLIGHTS
Summer 2026 project focused on improving student safety, campus security, and outdoor learning environments at the Allendale Swing Space Campus.
Allendale Elementary
Swing Space
8
Multi-Site Phase 2 Project
Shade Structure
New Installations
Project Benefits
Timeline & Funding
Project is part of the Districtβs Measure O campus improvement program.
Construction Status:
Anticipated Summer/Fall 2026
Project Visualization
9
MAJOR PROJECTS
Investing in Safe, Modern, and Inspiring Learning Environments
CURRENT PROGRAM FOCUS
β
Major Campus Modernization
Executing deep modernization across major district campuses.
β
Swing Space & Transition
Detailed planning and preparation for seamless campus transitions.
β
Athletic Improvements
Upgrading high-β physical education and athletic facilities.
β
Infrastructure & Sustainability
Securing our long-term structural integrity and introducing sustainable green practices across the district infrastructure.
β
Future-Ready Classrooms
Investing in next-generation learning environments designed to foster inspiration, high collaboration, and academic growth.
10
Longfellow Elementary School
Campus Modernization Project
KEY HIGHLIGHTS
Campus Renderings: Grounds, Kitchen & Classrooms
11
John Muir High School
Gym and Pool Modernization Project and Improvements to Athletic Facilities
KEY HIGHLIGHTS
Project Visualization
12
KEY HIGHLIGHTS
Project Visualization
Pasadena High School
Campus Modernization Project
13
Roosevelt Campus
Workforce Housing Project
KEY HIGHLIGHTS
Project Visualization
14
Thurgood Marshall Secondary School.
Athletic Field & Track, Restroom & Utility Upgrade Project
KEY HIGHLIGHTS
Athletic Field and Track Project
Planning Reference
15
Franklin Elementary
Swing Space & Campus Recovery Project
KEY HIGHLIGHTS
Restoring and modernizing campus facilities following the Eaton Fire.
Campus Site Renderings
16
Visual Reference
San Rafael Elementary School
Full Campus Rebuild Project
KEY HIGHLIGHTS
KEY HIGHLIGHTS
17
Eliot Arts Magnet
Options Review and Next Steps
Eliot Arts Magnet Campus Renewal Project
Following the Eaton Fire and emergency response activities, PUSD continues working through the next phase of the Eliot Arts Magnet Campus Renewal Project. This work includes ongoing structural evaluations, environmental coordination, and early master planning efforts to help guide the future of the campus in partnership with the Eliot community.
Where We Are Today
Community and Historic Considerations
Moving Forward
VISUAL PROGRESS
After
Before
18
Madison Elementary School
Campus Modernization Project Overview
Project Visualization
KEY HIGHLIGHTS
19
BOND PROGRAM UPDATE
Facilities 5-Year Roadmap Overview
β
Districtwide Investment
All campuses within the Five-Year Plan are receiving facility improvements and infrastructure investments.
β
Modernization
10 campuses receiving major modernization projects
β
Infrastructure & Health & Safety
9 campuses receiving restroom, utility, and Health & Safety improvements
β
Safety & Infrastructure
Districtwide safety, β, and critical infrastructure improvements
β
Future-Ready Campuses
Continued investment in safe, modern, and sustainable learning environments.
20
PROGRAM SNAPSHOT
Facilities 5-Year Roadmap | Overview
34
Campuses Included
119
Completed Projects
10
Major Modernizations
9
Restroom/Utility - Health & Safety
β Willard (Complete)
β Sierra Madre (Complete)
β Hamilton (Complete)
β Jackson (Complete)
β Norma Coombs (Complete)
β Thurgood Marshall
β Altadena Arts
β Washington STEM
β McKinley K-8
Facilities 5-Year Roadmap | High-Level Snapshot Overview
β Security Locksets (Complete)
β Secure Front Entry (Complete)
β Security Camera Replacement (Complete)
β Critical Roofing Replacements (Complete)
β Completed
β Upcoming / Planned
β Major Projects
MAJOR MODERNIZATION CAMPUSES
RESTROOM / UTILITY - HEALTH & SAFETY
DISTRICTWIDE CAPITAL PROGRAMS
β John Muir High School
β Longfellow Elementary
β Madison Elementary
β Pasadena High School
β San Rafael Elementary
β Don Benito Elementary
β Field Elementary School
β Webster Elementary
β Octavia E. Butler Magnet
β Blair High School
21
1 of 3 | High-Level Site Summary
β Completed
β Upcoming / Planned
β Major Projects
Allendale Elementary
β Swing Space Updates
β Door Lockset Replacement
Altadena Arts Magnet
β Chiller Replacement
β Installation of Portables / Solar Moved
β Critical Roofing Replacements 1 Bldg
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Outdoor Learning and Campus Improvements
Cleveland
β Critical Roofing Replacements 1 Bldg
β Security Lockset Replacement
Don Benito Fundamental K-5
β Critical Roofing Replacements 3 Bldgs
β Critical HVAC Replacement 1 Unit
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β MPR and Kitchen Renovation
β School Modernization
Field Elementary
β Shade Structure Phase 1
β Fencing and Curb Appeal
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Emergency Chiller Replacement
β School Modernization
β Impacted Soils Remediation
Hamilton Elementary
β Shade Structure Phase 1
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Health & Safety: Hardscape / Field / Gate Repairs
β Restroom and Utility Updates
Facilities 5-Year Roadmap | High-Level Site Summary
ELEMENTARY CAMPUSES
22
ELEMENTARY CAMPUSES
2 of 3 | High-Level Site Summary
β Upcoming / Planned
β Major Projects
Jackson Elementary
β Security Lockset Replacement
β Health & Safety Upgrades
β Secure Front Entry System
β Security Camera Replacement
β Restroom and Utility Updates
β Shade Structures & ADA Upgrades
Jefferson Child Care Center
β Critical Roofing Replacements
β Play Structure
β Internet & Paging system
β Secure Front Entry System
Linda Vista Campus
β Removal of Portables
Longfellow Elementary
β Child Care Play Structure
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β School Modernization
Madison Elementary
β Critical Roofing Replacements 2 Bldgs
β Shade Structure Phase 1
β Security Lockset Replacement
β Secure Front Entry System
β Emergency Chiller Replacement
β School Modernization
Norma Coombs Elementary
β Critical Roofing Replacements 8 Bldgs
β Shade Structure Phase 1
β Critical HVAC Replacement 3 units
β Security Lockset Replacement
β Secure Front Entry System
β Health & Safety: Hardscape Updates
β Restroom and Utility Updates
Facilities 5-Year Roadmap | High-Level Site Summary
β Completed
β Upcoming / Planned
β Major Projects
23
ELEMENTARY CAMPUSES
3 of 3 | High-Level Site Summary
β Upcoming / Planned
β Major Projects
Roosevelt
β Workforce Housing Contractor Selected
San Rafael Elementary
β Critical Roofing Replacements 6 Bldgs
β Critical HVAC Replacement (6 units)
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β School Campus Rebuild
Sierra Madre Elementary
β Critical Roofing Replacements 3 Bldgs
β C- PA System Upgrade
β Security Lockset Replacement
β Health & Safety: Hardscape Updates
β Secure Front Entry System
β Central Plant Upgrades
β Restroom and Utility Updates
β Shade Structures & ADA Upgrades
Washington Ele. STEM Magnet
β Shade Structure Phase 1
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Health & Safety: Updates
β Restroom and Utility Updates
Webster Elementary
β Critical Roofing Replacements 4 Bldgs
β Critical HVAC Replacement (Bldg A) 27 units
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Shade Structures & ADA Upgrades
β School Modernization
Willard Elementary
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Health & Safety: Hardscape and field Updates
β Restroom and Utility Updates
β Shade Structures & ADA Upgrades
Facilities 5-Year Roadmap | High-Level Site Summary
β Completed
β Upcoming / Planned
β Major Projects
24
High-Level Site Summary
Facilities 5-Year Roadmap | High-Level Site Summary
MIDDLE CAMPUSES
Blair (MS Campus)
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
Eliot Middle
β Critical Roofing Replacements 4 Bldgs
β Critical HVAC Replacement (Bldg C)
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
McKinley K-8
β Critical Roofing Replacements 3 Bldgs
β Critical HVAC Replacement (Library)
β Shade Structure Phase 1
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Health & Safety: Bldg. B Exterior Doors
β Restroom and Utility Updates
Octavia E. Butler Magnet
β C- PA System (Gym)
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β School Modernization
Sierra Madre Middle
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
Wilson - CIS, PALS
β Security Lockset Replacement
β Secure Front Entry System
β Completed
β Upcoming / Planned
β Major Projects
25
HIGH SCHOOL CAMPUSES
High-Level Site Summary
Blair (HS Campus)
β Secure Front Entry System
β Security Camera Replacement
β Security Upgrades - Fencing
β Restrooms, Pool and Track/Field Modernization
John Muir High
β Critical Roofing Replacements 6 Bldgs
β Security Camera Replacement
β Security Lockset Replacement
β Secure Front Entry System
β Restroom Refresh
β Gym/Pool, Athletic Fields and Parking Lots Modernization
Thurgood Marshall Secondary School 6-12
β Critical Roofing Replacements 6 Bldgs
β Emergency Ceiling Replacement - Band Room
β Security Lockset Replacement
β Secure Front Entry System
β Security Camera Replacement
β Softball Field Renovation
β Restrooms, Utility and Track/Field Updates
Pasadena High
β Critical Roofing Replacements 10 Bldgs
β Security Camera Replacement
β Critical HVAC Replacement (Exhaust hoods)
β Security Lockset Replacement
β Secure Front Entry System
β Identity & Curb Appeal Project
β Kitchen Upgrades-Food Services Project
β Pool and Restroom Modernization
Rose City High 10-12
β Security Lockset Replacement
β Secure Front Entry System
Facilities 5-Year Roadmap | High-Level Site Summary
β Completed
β Upcoming / Planned
β Major Projects
26
OTHER CAMPUSES
1 of 1 | High-Level Site Summary
β Upcoming / Planned
Hodges
β Security Lockset Replacement
β Secure Front Entry System (Closed loop)
Audubon (Odyssey Charter)
β Walkway and Gate
β Restroom Portable Relocation
β Security Lockset Replacement
β Secure Front Entry System (Closed loop)
β Door Lockset Replacement
β Health & Safety: Asphalt Replacement
Loma Alta
β Critical Roofing Replacements 5 Bldgs
β Critical HVAC Replacements 4 Units
Facilities 5-Year Roadmap | High-Level Site Summary
Burbank (Stratford School)
β Security Lockset Replacement
β Secure Front Entry System (Closed loop)
Edison
β Portable Restoration 4 rooms
β Completed
β Upcoming / Planned
β Major Projects
27
FINANCIAL PLANNING UPDATE
Funding, Planning & Program Adjustments
Current Program Adjustments
August Board Consideration
28
CAPITAL FINANCIAL SNAPSHOT
Additional Resources
as of June 2026
29
STATE MATCH FUNDING RESET
Original five-year-plan assumption removed β’ 2026 eligibility is not an award
$124.1M ASSUMPTION REMOVED
$117.7M ELIGIBILITY IN 2026
Eligibility was created in 2026, and applications may now be submitted.
$117.7M is eligibilityβnot an award. No State funding is guaranteed.
Additional eligibility is projected in 2029. Any future award depends on a State bond and statewide availability.
The original five-year plan assumed $124.1M in State matching funds.
That funding never became available on the planned timeline, so the assumption is removed from the current plan.
Affected projects move to later Measure R planning for possible funding.
30
BOARD SUMMARY
31
BUDGET MOVEMENTS β APPROVED
32
BUDGET MOVEMENTS β PROPOSED
33
RESTROOM / UTILITY 97129 β 1 OF 2
34
RESTROOM / UTILITY 97129 β 2 OF 2
35
SWING SPACE AND SHADE DETAIL
36
PROJECT SCHEDULES REFLECTING PRIOR BOARD APPROVALS
37
βGreat places donβt happen by chance; they are created through public involvement, creative thinking, good planning and hard workβ
β Unknown
38
Q&A