FORM MONITORING POTENSI
FORCE OUTAGE (FO) DAN
FORCE DERATING (FD- DER)��UNIT OM 1�Periode Januari 2026
Sidoarjo, Oktober 2025
Summary Potensi EFOR Unit OM-1 Januari 2026
PLTA ASAHAN
01 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | TURBIN | Urgent | Gangguan signal temperatureTurbine pad Bearing | Sudah dilakukan perbaikan | ● | 1.I&C | | | | | WO74744 |
| | | | | | | | | | | |
Potensi EFOR Generator & Trafo Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Generator | Urgent | Gangguan alarm G60, Isolator pada sambungan antar pole Rotor rusak | Sudah dilakukan perbaikan | | Elektrik | | | | | WO 74358 |
2 | PLC | Urgent | Electrical accident, disebabkan perbedaan input perintah Auto dan Manual pada program yang di inject tim Schneider sehingga MIV auto close. | Sudah dilakukan perbaikan | | | | | | | |
| | | | | | | | | | | |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | Nihil | | | | | | | | | |
2 | Nihil | | | | | | | | | |
PLTU BANGKA
02 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Boiler Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Furnace System | Urgent | Normal | Terdapat beberapa kebocoran pada Walltube | Patrol check rutin | Operasi | Rutin |
| Mekanik |
| |
2 | Dearator | Urgent | Normal | Kebocoran pada check valve | Patrol check rutin | Operasi | Rutin |
| Mekanik |
| |
3 | Safety Valve | Urgent | Valve MOV leaktrough | Valve MOV leaktrough (line up venting) | Patrol check rutin | Operasi | Rutin | Penggantian Valve MOV safety valve | Mekanik & INC | WMTL (ME) | |
4 | IAC | Urgent | Hanya beroperasi 1 unit | Hanya beroperasi 1 unit | Overhaul dan penggantian 1 set | Operasi | Rutin |
| Mekanik | Levering | |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Feed Water 2B | Urgent | Standby Emergency | Standby Emergency | Patrol check dan rutin pengambilan data (saat change over) | Operasi | Rutin Mingguan | Pembongkaran Pompa | Mekanik | OH ME Sept 2025 | |
2 | Governor Turbine | Urgent | Normal (OLS) | Normal (OLS) | Saat ini dilakukan OLS pada flange GV | Mekanik | Rutin | Penggantian packing, Flange | Mekanik | OH ME Sept 2025 | |
3 | Water Ejector B | Urgent | Vibrasi sisi pompa | Vibrasi sisi pompa | Monitoring Vibrasi dan level oli | Operasi dan PdM | Rutin Mingguan | Penggantian Bearing dan Seal oil | Mekanik | OH ME Sept 2025 | |
4 | Generator 2 | Urgent | Vibrasi sisi Exciter | Vibrasi sisi Exciter | Rutin cek aliran oil B5 dan B4 serta monitoring Vibrasi | Operasi dan PdM | Outage | Alignment ulang dan pengecekan kondisi Bearing | Elektrik Outage | OH ME Sept 2025 | |
5 | CWP 3 | Emergency | Trip dan Fuse putus | Normal | Penggantian Fuse dan pengecekan terminal box | Elektrik | FO OMC | Penggantian Fuse | Elektrik | Finish | |
Potensi EFOR Boiler Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Kebocoran dinding Furnace | Emergency | Furnace bocor pasir dari beberapa titik | Normal | Top up pasir dan penambalan dinding (temporari/ online) | Operasi Rendal | M3 Mar 2025 | Pengelasan pin di area tube | Mekanik | ME Sept 2025 | |
| | | | | | | | | | | |
Potensi EFOR CHF
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Alat Berat | Urgent | Beberapa alat berat rusak | Beberapa alat berat rusak |
| 1. Har 2. Ops | Rutin harian dan mingguan |
| Mekanik | 1.Finish 2. Proses perbaikan Transmisi | |
2 | Crusher System | Urgent | Vibrasi | Vibrasi | Monitoring Vibrasi | PdM | Rutin 2 mingguan | Penggantian Hammer Crusher | Mekanik | TW 3 2025 | |
3 | Rotary Screen System | Urgent | Vibrasi | Vibrasi | Monitoring Vibrasi | PdM | Rutin 2 mingguan | Leveling pondasi/ Re alignment | Mekanik | TW 4 2025 | |
4 | EDG System | Urgent | Normal | EDG tidak bisa maksimal supply daya | Pengecekan Filter oli dan Compressor serta aux | Elektrik | Rutin bulanan | Overhaul mesin | Elektrik Mekanik | TW 3 2025 | |
5 | Coalyard | Urgent | Batubara basah | Batubara basah |
| 1. Rendal & Operasi 2. Rendal & Operasi 3. PLN EP, PLN NP& Unit | Rutin | Mixing dan Optimalisasi stock kering | Rendal dan Operasi | Sustain | |
Potensi EFOR Common
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | SWRO #1 | Urgent | Penyangga Keropos | Penyangga Keropos | Weldingarea yang keropos dengan besi hollow baru | Mekanik | Tentative |
| Mekanik | TW 3 2025 | AI2024 (Levering) |
2 | Valve SWRO system | Urgent | Indikasi Valve leaktrough | Indikasi Valve leaktrough | Plug saat akan dilakukan cleaning | Mekanik | Tentative | Upgrade Valve ke material Duflex | Mekanik & Rendal | Juni 2025 | AI2024 (Levering) |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | Nihil | | | | | | | | | |
2 | Nihil | | | | | | | | | |
PLTU BELITUNG
03 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | PRESSURE OUTLET MOP LOW | Emergency | Normal | Normal | Pengecekan saat Outage | Mekanik | Saat Outage | Penggantian shaft MOP, Impeller | Mekanik | OH SE 2025 | |
2 | VAKUM CONDESOR DROP | Emergency | Kondisi debris tidak bisa auto cleaning | Debris tidak bisa auto cleaning | Cleaning debris manual | Mekanik | Rutin | Akan di lakukan inspeksi | Mekanik | OH SE 2025 | |
3 | VALVE OUTLET CONDENSOR A DAN B INDIKASI RUSAK ( valve terkadang close sendiri ) | Emergency | 1. Valve terkadang close sendiri 2. Gear box indikasi aus | 1. Valve terkadang close sendiri 2. Gear box indikasi aus | Dilakukan perbaikan gearbox ( selesai ), tetapi masih tetap tidak bisa full open close | Mekanik | Rutin | Dilakukan penggantian valve | Mekanik | OH SE 2025 | |
4 | SPEED TURBIN DI DCS DAN LOCAL TERBACA 550 RPM | Emergency | 520 rpm | 472 rpm | Pemantauan | Operator | Rutin | Dilakukan perbaikan end shaft gear speed | Mekanik | 1. MO januari 2024 2. Dilakukan perbaikan saat OH SE 2025 | |
Potensi EFOR Boiler Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | REFACTORY FURNACE DAN SICLONE SUDAH BANYAK TAMBALAN | Urgent | Sudah banyak tambalan | Banyak tambalan | Perbaikan temporary saat Outage | Mekanik | Saat Outage ( rencana M4 Januari 2025 ) | 1. Inspeksi refractory 2. Akan dilakukan penggantian refractory | Mekanik | 1. Saat MO rencana M4 januari 2025 2. OH SE 2025 | |
2 | FINDER VORTEK SICLONE A DAN B DEFORMASI | Urgent | Kondisi vortek mengembang pada support dudukan dan ada temuan crack | 1. Vortek mengembang pada support dudukan & ada temuan crack 2. Terjadi hotsport dan bocoran pada area support dudukan vortek | Pengecekan saat Outage | Mekanik | Outage M4 januari 2025 | Dilakukan penggantian | Mekanik | OH SE 2025 | |
Potensi EFOR Boiler Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
3 | SAFETY VALVE SUPERHEATER PASING (Sudah ada history, safety valve tidak bekerja sesuai set pressure dan tidak close sesuai setting ) | Emergency | Bekerja tidak sesuai setting | Bekerja tidak sesuai setting | Perbaikan safety valve | Mekanik | MO Juli 2024 | Penggantian safety valve | Mekanik | OH SE 2025 | |
4 | BED TEMPERATUR TINGGI ( BEDA SEKITAR 50C DENGAN UNIT 1 ) | Emergency | Bed temp mencapai 990C saat beban 16,5 MW dan BB kering | Bed temp mencapai 990C saat beban 16,5 MW dan BB kering | 1. Menjaga pola operasi max temp 980C 2. Dilakukan Mixing BB dengan kalori rendah | Operator | Rutin | Akan dilakukan inspeksi | Mekanik | MO Januari 2025 | |
5 | SAFETY VALVE STEAM DRUM TIDAK BEKERJA SESUAI SETTING PRESSURE | Emergency | Tidak bekerja sesuai setting | Tidak bekerja sesuai setting | 1.Sudah diakukan perbaikan saat MO Juli 2024 2. Monitoring | Mekanik | | Penggantian valve baru | Mekanik | OH SE 2025 | |
Potensi EFOR Generator & Trafo Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | VIBRASI TINGGI BEARING 4 GENERATOR | Emergency | Vibrasi B4H = 10,41mm | Tetap | Monitoring rutin | Operator, CBM | mingguan | Pengecekan dan penggantian | Mekanik | OH SE 2025 | |
2 | TRANSFORMER UAT SHORT CIRCUIT SISI LV | Emergency | off | off | - | - | - | Dilakukan penggantian baru | Listrik | Semeter 2 2025 | |
Potensi EFOR CHF
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | PLUGGING JALUR LOADING | Emergency | Plugging kondisi BB basah | Plugging BB basah | 1. Cleaning Jalur loading continu 2. Terpalisasi BB di Coal yart | Operator, Helper | 1. Sebelum loading dan saat terjadi plugging | Penambahan/ Perluasan coalshet | NPS KP, NP | 2025 | |
2 | AUTO START CONVEYOR JALUR LOADING TIDAK BISA SEJAK PROJECT 2017 | Emergency | Tidak normal | Tidak normal | - | - | - | Penormalan auto start conveyor | I&C | AI | |
Potensi EFOR Common
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | DISPLAY EDG RUSAK | Emergency | Rusak | Rusak | Start manual lokal | Operator | mingguan | Penggantian display | Listrik | Semester 1 2025 | |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | End shaft speed Turbin | End shaft indikasi aus | FO | | Monitoring Rutin | Operator | | | | Perbaikan End shaft gear speed |
PLTU TEMBILAHAN
04 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | 170605TM10MA STEAM TURBINE/TURBIN SYSTEM #1 | Urgent | Temuan kerusakan curtis no.2 Potensi akan mempengaruhi tekanan dan velocity uap di outlet. Aliran steam yang keluar dari leading edge menuju ke trailing edge akan terganggu dan gaya tekan untuk memutar blade rotor curtis no. 2 akan berkurang. Kondisi ini akan membuat kelelahan material (fatigue) pada blade dan mengurangi performa/ kinerja dari blade | Temuan kerusakan curtis no.2 Potensi akan mempengaruhi tekanan dan velocity uap di outlet. Aliran steam yang keluar dari leading edge menuju ke trailing edge akan terganggu dan gaya tekan untuk memutar blade rotor curtis no. 2 akan berkurang. Kondisi ini akan membuat kelelahan material (fatigue) pada blade dan mengurangi performa/ kinerja dari blade | 1. Monitoring parameter operasi di turbin (Temperature dan vibrasi bearing, serta kualitas oli) | 1. Operasi & PDM | 1. Kontinue | 1. Lakukan penggantian pada blade curtis yang mengalami kerusakan atau keseluruhan | OM & Enj | 1. AI 2025 (Proses Pengadaan) | WO26128 |
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
2 | 170605TM10LA FEED WATER SYSTEM #1 | Urgent | BFP1B Vibrasi high, sudah dilakukan minor OH namun vibrasi masih tinggi. | BFP1B Vibrasi high, sudah dilakukan minor OH namun vibrasi masih tinggi. | 1. Melakukan pengukuran vibrasi saat beban rendah untuk memastikan indikasi blade pass frekuensi apakah muncul saat 1 BFP beroperasi 2. Pastikan supply cooling pada pompa sesuai GAD & PID. Untuk menjaga part lifetime/failure dari potensi over heat. 3. Pastikan posisi IN/OUT cooling line pada pompa sesuai dengan posisi yang diinginkan mechanical design as per mech.seal drawing & GAD. Untuk hindari over flow+head pada mechanical seal. 4. Melakukan pengaturan flow total operasi BFP mendekati flow sesuai spek 5. BLO pipe dipasang dengan koneksi masing-masing secara terpisah. Untuk hindari adanya potensi back pressure | 1.PDM 2.HAR Mek 3. HAR Mek 4. Operasi 5.HAR Mek | 1. selesai 2. selesai 3. selesai 4. Kontinu 5. Sudah dilakukan saat SI Mei Juni 2024 untuk BFP #1 | 1. Melakukan minor dan major part checking untuk internal parts secara clearance, visual condition 2. Perlu lakukan kajian/analisa secara engineering untuk dapatkan kesesuaian BEP untuk masing pompa saat beroperasi pararel agar pump operation berada pada duty pointnya (80-110% BEP), terhadap plant demands operation. Perlu dilakukan test bench pompa BFP eksisting untuk mengetahui karakteristik aktual pompa 3. Pengadaan 1 set BFP 4. Penggantian balance disk, oring mechseal, penggantian bearing DE & NDE serta bearing axial | 1.Renhar 2. Enjiniring 3. Enjiniring 4. NPS Project | 1. Finished 2. SM 1 2025 -Site visit tim KSB 20-22 April 2025 -Menunggu hasil kajian (M3 Agustus 2025) 3. Usulan AI 2027 4. OH SE 2025 | |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | 170605TM20LA FEED WATER SYSTEM #2 | Urgent | BFP2A,2B,2C Vibrasi high, sudah dilakukan minor OH namun vibrasi masih tinggi. | BFP2A,2B,2C Vibrasi high, sudah dilakukan minor OH namun vibrasi masih tinggi. | 1. Melakukan pengukuran vibrasi saat beban rendah untuk memastikan indikasi blade pass frekuensi apakah muncul saat 1 BFP beroperasi 2. Pastikan supply cooling pada pompa sesuai GAD & PID. Untuk menjaga part lifetime/failure dari potensi over heat. 3. Pastikan posisi IN/OUT cooling line pada pompa sesuai dengan posisi yang diinginkan mechanical design as per mech.seal drawing & GAD. Untuk hindari over flow+head pada mechanical seal. 4. Melakukan pengaturan flow total operasi BFP mendekati flow sesuai spek '5. BLO pipe dipasang dengan koneksi masing-masing secara terpisah. Untuk hindari adanya potensi back pressure | 1.PDM 2.HAR Mek 3. HAR Mek 4. Operasi 5.HAR Mek | 1. selesai 2. selesai 3. selesai 4. Kontinu 5. Sudah dilakukan saat SE Nov 2024 | 1. Melakukan minor dan major part checking untuk internal parts secara clearance, visual condition 2. Perlu lakukan kajian/analisa secara engineering untuk dapatkan kesesuaian BEP untuk masing pompa saat beroperasi pararel agar pump operation berada pada duty pointnya (80-110% BEP), terhadap plant demands operation. Perlu dilakukan test bench pompa BFP eksisting untuk mengetahui karakteristik aktual pompa 3. Pengadaan 1 set BFP | 1.Renhar 2. Enjiniring 3. Enjiniring | 1. Selesai 2. SM 1 2025 -Site visit tim KSB 20-22 April 2025 -Menunggu hasil kajian (M3 Agustus 2025) 3. Usulan AI 2027 | |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
2 | Circulating Water Pump 2B (170605TM20PAC40AP004) | Urgent | Nilai vibrasi tertinggi pada sisi PIH (Pompa Inboard Horizontal) 11.4 Rms mm/s, menurut standart ISO 10816 - 3. Masuk dalam kategori Vibration Caused Damage | Nilai vibrasi tertinggi pada sisi PIH (Pompa Inboard Horizontal) 11.4 Rms mm/s, menurut standart ISO 10816 - 3. Masuk dalam kategori Vibration Caused Damage | 1. Melakukan pengujian solo run untuk mengetahui kondisi bearing sisi DE dan NDE, 2. Melakukan pengecekan softfoot kaki motor 3. Melakukan leveling bearing sisi DE & NDE pompa 4. Melakukan pengecekan endplay pompa 5. Melakukan inspeksi kondisi rubber coupling | 1.Har Mek 2.Har Mek 3.Har Mek 4.Har Mek 5.Har Mek | 1.Selesai 2.Selesai 3.Selesai 4.Selesai 5.Selesai | 1. Melakukan perbaikan impeller (Rubbing hingga crack dan bending) | 1.Har Mekanik | 1. M1 September 2025 | WO39604 |
Potensi EFOR CHF
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | EXCAVATOR | Breakdown | Kondisi mainpump leak out oil | Kondisi mainpump leak out oil | | | | Dilakukan penggantian mainpump | Tim Alat Berat | M1 September 2025 | |
| | | | | | | | | | | |
Potensi EFOR Common
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | 170605TM00SCB40AN001 INSTRUMENT AIR COMPRESSOR (IAC) 1 | Urgent | Suara kasar pada IAC A | Suara kasar pada IAC A | 1.Monitoring parameter operasi 2.Monitoring vibrasi 3.Regreasing | 1.Har Mek 2.PDM 3,Har Mek | 1.Continue 2.Continue 3.Finished | 1.Penggantian bearing SET 2.Penggantian bearing khusus compressor dan seal tip scroll | 1.Har Mek 2.Har Mek | 1. Finished (M2 April 2025) 2.Dilakukan perbaikan oleh workshop Palembang (Estimasi selesai M1 September 2025) | 1.WO36132 2. |
2 | 170605TM00SCB50AN001 INSTRUMENT AIR COMPRESSOR (IAC) 2 | Urgent | Compressor C1 IAC B overload (10 Mar 2025) | Compressor C1 IAC B overload | 1.Monitoring parameter operasi 2.Monitoring vibrasi | 1.Har Mek 2.PDM | 1.Continue 2.Continue | 1. Perbaikan dari pihak ke 3 claim warranty IAC | 1.Har Mek | Levering material 2 bulan dan rencana eksekusi 15 Juli 2025 | WO36964 |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | Nihil | | | | | | | | | |
2 | Nihil | | | | | | | | | |
PLTU BANJARSARI
05 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | CWP 1B | Urgent | 10-01-2025 Nilai Vibrasi tertinggi terdapat pada Motor Inbord Axial sebesar 1.52 mm/s termaksud Normal | 07-02-2025 Nilai Vibrasi tertinggi terdapat pada Motor Outbord Axial 1.83 sebesar mm/s termaksud Normal | 1.Monitoring vibrasi 2.Monitoring parameter operasi | | | 1.Meningkatkan pelaksanaan Pdm 3kali dalam 1bulan 2.Meningkatkan pelaksanaan PM 3.Lakukan solo run motor (Sudah dilakukan, overall vibrasi Normal) | | 1.Rutin 2.Rutin 3.Finish | |
Potensi EFOR Boiler Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Boiler Feed Water Pump 1A | Urgent | 21-01-2025 Nilai Vibrasi tertinggi terdapat pada Pompa Inbord Vertical sebesar 11.37. mm/s termasuk kategori Fault | 06-02-2025 Nilai Vibrasi tertinggi terdapat pada Pompa Inbord Vertical sebesar 9.84. mm/s termasuk kategori Fault | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Setting bukaan sealing ke BFP 1A pada 0.7mpa. 2.Lakukan perencanaan strategic spare internal part | | 1.Rutin 2.Januari 2025 (Pengajuan BPI) | |
2 | Boiler Feed Water Pump 1B | Urgent | 12-07-2024 Hydrotest pressure 12.65 Mpa, Nilai Vibrasi tertinggi terdapat pada Pompa Inbord Vertical sebesar 8.60 mm/s termasuk dalam kategori Alarm | 12-07-2024 Nilai Vibrasi tertinggi terdapat pada Pompa Inbord Vertical sebesar 8.60 mm/s termasuk dalam kategori Alarm menurut ISO 10816 | 1.Meningkatkan pelaksanaan pdm 4kali dalam 1bulan 2.Meningkatkan Frekuensi pelaksanaan PM 1kali dalam 1minggu 3.Setting bukaan sealing ke BFP 1B pada 0.7mpa | | | 1.Setting bukaan sealing ke BFP 1B pada 0.7mpa. 2.Lakukan perencanaan strategic spare internal part 3.Modifikasi penambahan line tapping spray from BFP | | 1.Rutin 2.Januari 2025 (Pengajuan BPI) 3.Finish | |
Potensi EFOR Generator & Trafo Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Generator | Urgent | 07-01-2025 Nilai vibrasi tertinggi terdapat pada sisi Bearing 5 Axial sebesar 17.06 mm/s, Indikasi adanya permasalahan looseness, misalignment dan oil whirl akibat impact bearing (Trending Vibrasi cenderung Stabil) | 23-01-2025 Nilai vibrasi tertinggi terdapat pada sisi Bearing 5 Axial sebesar 17.68 mm/s, Indikasi adanya permasalahan looseness, misalignment dan oil whirl akibat impact bearing (Trending Vibrasi cenderung Stabil) | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi 4.Rutin pengambilan sample oil turbine | | | 1.Lakukan penggantian bearing 5 (Sudah dilakukan) 2.Lakukan aligment ulang pada bearing 3 dan 4 (sudah dilakukan) 3.Lakukan perbaikan shaft Generator pada Bearing 5 4.Lakukan realignment HIP-LP-Generator | | 1.Finish 2.Finish 3.OH ME 2025 4.OH ME 2025 | |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | CWP 2A | Urgent | 11-10-2024 Nilai overall vibrasi tertinggi sisi pompa DE sebesar 4.01 mm/s | 30-01-2025 Kondisi saat ini progress repair machining shaft dan reboushing housing bearing DE pompa | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Lakukan penggantian bearing DE pompa 2.Lakukan inspeksi inner part pompa, gland packing dan pergantian shaft slevee 3.Lakukan perbaikan shaft pompa insitu 4.Fabrikasi Inner Part 1 set strategic spare | | 1.Finish 2.Finish 3.On progress 4.Menunggu proses pengadaan BPI (pengajuan sudah dikirim) | |
2 | Gland Seal Condensor 2B | Urgent | 05-11-2024 Nilai Vibrasi tertinggi terdapat pada Motor inbord Axial sebesar 4.48 mm/s termaksud Alarm | 23-01-2025 Nilai Vibrasi tertinggi terdapat pada Motor inbord Horizontal sebesar 4.89 mm/s termaksud Alarm (Pergantian bearing selesai, lanjut runtest) | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Lakukan penggantian bearing motor DE dan NDE 2.Lakukan pengecekan clearance bearing to housing 3.Lakukan perbaikan/ penguatan pada baut pengikat pondasi motor | | 1.OH BI 2025 (In Progress) | |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
3 | HSF 2C | Urgent | 26-12-2024 Nilai Vibrasi tertinggi terdapat pada blower Inbord Axial sebesar 5.838 mm/s termaksud Normal, kondisi monitoring Parameter vibrasi dan operasi | 24-01-2025 Kondisi peralatan tidak standby beroperasi karena kerusakan motor cooling fan. (Progress rewinding motor cooling) | 1.Meningkatkan pelaksanaan Pdm 3kali dalam 1bulan 2.Meningkatkan pelaksanaan PM 3.Monitoring Vibrasi | | | 1.Perbaikan Motor cooling fan 2.Pemasangan blower portable | | 1.M2 februari 2025\ 2.Finish | |
4 | Cooling Tower 2B | Urgent | 28-11-2024 Nilai Vibrasi tertinggi terdapat pada Motor Inbord Horizontal sebesar 14.32 mm/s termaksud Fault | 05-12-2024 Individual tes motor normal. Pengujian motor-gearbox, nilai Vibrasi tertinggi terdapat pada Motor Outbord Axial sebesar 3.79 mm/s termaksud Normal. Namun kondisi noise sisi Gearbox | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Lakukan solo run test motor 2.Lakukan penggantian long shaft 3.Lakukan penggantian bearing motor 4.Lakukan perbaikan gearbox yang rusak 5.Runtest gearbox menggunakan spare yang telah di perbaiki | | 1.Selesai (rekomendasi penggantian bearing Motor) - WO243964 2.Progress 3.Finish 4.Proses pengajuan perbaikan gearbox yang rusak (M2 Des) 5.Finish (motor normal dan gerbox terdapat kerusakan gear) | |
Potensi EFOR Boiler Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Boiler Feed Water Pump 2A | Urgent | 09-01-2025 Nilai vibrasi tertinggi sisi Pompa Inbord Horizontal sebesar 5,69 mm/s termaksud Normal | 23-01-2025 Nilai vibrasi tertinggi sisi Gearbox Inbord Horizontal sebesar 6.11 mm/s termaksud Normal | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Lakukan perbaikan sisi pompa DE dan NDE yang bocor 2.Lakukan perbaikan sisi stem coupler yang bocor | | 1.OH ME 2025 (Juli) 2.OH ME 2025 (Juli) | |
2 | Boiler Feed Water Pump 2B | Urgent | 23-12-2024 Nilai vibrasi tertinggi sisi Pompa Inbord vertical sebesar 12.78 mm/s termaksud Fault | 07-01-2025 Nilai vibrasi tertinggi sisi Pompa Inbord Horizontal sebesar 9.76 mm/s termaksud Fault | 1.Monitoring vibrasi 2.Monitoring Temperature 3.Monitoring parameter operasi | | | 1.Setting bukaan sealing ke BFP 1A pada 0.7mpa dan 2.Lakukan perencanaan strategic spare internal part 3.Perbaikan kebocoran pada body sisi DE pompa | | 1.Rutin 2.Januari 2025 3.Progress perbaikan dengan metode menggunakan durraloy | |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | Nihil | | | | | | | | | |
2 | Nihil | | | | | | | | | |
PLTU KETAPANG
06 |
Monitoring FO-DER dan Potensi FO-DER
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | LUBE OIL SYSTEM | Urgent | Water contain tinggi | Water contain tinggi | 1.Drain rutin water contain 2.Pengoperasian purifier 3.Pengambilan sampling | 1.Ops 2.Ops 3.Eng ● | 1.Daily 2.Daily 3.3 Month | Penggantian labyrinth seal (Material proses AI2025 - Pengadaan material bearing dan inner part turbin PLTU Ketapang) | Mech | SE 2025 (9 Septembe-24 oktober) 24 Oktober 2025 (Selesai) (AI2027) | |
2 | OPEN COOLING WATER SYSTEM | Normal | Kondisi body valve dan debris filter korosi | Kondisi body debris filter korosi | Patrol check/Visual Check | Operasi | Daily | 1.Penggantian valve debris (Selesai) 2. Doubling plat body debris filter (selesai) 3.Penggantian debris filter masuk AI 20227 beserta penambahan line bypass debris 4. Inspeksi fiber lining bagian dalam debris 5. Thikness pada line in let dan outlet debris | 1.Mech 2.Eng 3.RHar | Usulan AI 2027 | |
Potensi EFOR Turbin Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
3 | CONDENSATE WATER SYSTEM | Urgent | Kondisi check vavle Condensate water pump 1B stuck | Kondisi saat ini sudah beroperasi normal, saat ini masih dalam pemantauan. | 1.Patrol check/Visual Check 2.Pemantauan pressure CEP 1B | 1. Ops | Daily | 1.Penggantian check valve (proses penggantian spring check valve CEP 1B) (selesai) 2.Melakukan setting wearing 3mm, indikasi wearing overclearance. (Selesai) 3.Akan dilakukan identifikasi lebih lanjut pada saat OH SE. | 1.HarMek | SE 2025 ( 9 September -24 oktober) | WO104625 (Appr) |
4 | WATER EJECTION SYSTEM | Urgent | Telah di lakukan inspeksi dan terdapat kotoran yang menyangkut di impeller | Untuk pressure sudah normal, tetapi dari sisi vibrasi terjadi kenaikan menjadi 5 mm/s (status C) | Monitoring press pada WEP 1B dan monitoring vibrasi pada motor dan pompa WEP 1B | 1.Ops 2.ENJ | | 1.Inspeksi pada pompa dan realignment (pressure sudah normal, vibrasi tinggi di 5 mm/s) 2.Lakukan Setting pondasi pompa DE 3.Setting line outlet yang mengalami penurunan. 4.Kajian penambahan expantion joint pada line inlet dan outlet pompa. | Mech, har Listrik & ENJ | SE 2025 ( 9 September -24 oktober) | |
Potensi EFOR Boiler Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Main steam | Normal | Tidak terdapat kebocoran pada BOV | Terjadi kebocoran pada BOV unit 1 | Patrol check dan memastikan persentase kebocoran | 1.Ops | 1.Daily | 1.Melakukan online sealing (Selesai). 2.Lakukan penggantian valve BOV (sudah dilakukan beberapa kali perbaikan, kerusakan berulang) 3.Melakukan pengukuran dimensi gasket atau menentukan material gasket | 1.mech 2.Rendal Har | OH SE 2025 ( 9 September -24 oktober) | |
2 | BOILER EQUIPMENT | Urgent | Telah dilakukan perbaikan pondasi, leveling baseplate, penggantian motor OECD | Vibrasi pada PA Fan 1A masih kategori C baik di sisi motor DE dan NDE indikasi Soft foot | Pengecekan vibrasi & Thermography | 1.Ops 2.PDM | 1.Daily 2. M1 & M3 | 1.Perlu dilakukan perataan sisi baseplate Kembali 2.Perlu dilakukan leveling baseplate motor. | 1.mech,listrik 2.Rendal Har | OH SE 2025 ( 9 September -24 oktober) | |
3 | Boiler | urgent | Di temukan titik hot spot pada J valve refeeder sisi timur #1 | Masih di lakukan pemantauan. | Thermography | 1.Ops 2.PDM | 1.Daily | 1.Perlu pengecheckan refractory pada sisi dalam J valve. 2.Perbaikan refractory menunggu outage 3.Penanganan sementara dilakukan penambahan blower. | 1.Mech 2.ENJ 3.Rendal har | OH SE 2025 ( 9 September -24 oktober) | WO108708 (WAPPR) |
Potensi EFOR Generator & Trafo Unit 1
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Main Transformator | Urgent | Level 4.5 (level maks 10) | Kebocoran oil trafo pada radiator | Patrol check | Ops | Daily | Penggantian radiator trafo (levering material, est M-4 April ) | Listrik | SE 2025 19 Agustus s/d 2 Oktober | |
| | | | | | | | | | | |
Rekomendasi ICORE Unit 1
Case ID | Case Status | Description | Equipment | Follow Up | Follow Up No | Severity | Unit Name | WO Number | SR Number | Activity History |
583977 | INPRG | PAF 1A Vibration increase | Primary Air Fan 1A | | | 1 | PLTU Ketapang 1 | | | Kondisi PA Fan 1A mengalami kenaikan vibrasi sisi motor DE dan NDE indikasi Soft foot (akan di lakukan perbaikan pada saat OH SE 2025 19 agustus-02 oktober) |
583978 | INPRG | SAF 1A Vibration | Secondary Air Fan 1A | | | 1 | PLTU Ketapang 1 | | | Kondisi actual di local vibrasi tertinggi di 2 hunting 3 dan masuk kategori B (kuning) |
Potensi EFOR Turbin Unit 2
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | WATER EJECTION SYSTEM | Urgent | Terjadi kenaikan vibrasi pasca perbaikan. | Kondisi saat ini, vibrasi WEP 2B sudah normal beroperasi dan vibrasi tertinggi di 3,51 mm/s sisi horizontal pompa dengan kategori B (kuning) | Monitoring vibrasi (status emergency standby) | 1.Op, Enj | | 1.Setting support pompa sisi DE. | 1.Har Mekanik 2.Rendal har 3.Eng | M4 Agustus | WO104277 (Proses perbaikan) SELESAI |
2 | HYDRAULIC OIL SYSTEM | Normal | Proteksi ETS #2 lepas tidak bisa di on kan Kembali. Penyebab permasalahan pada DEH Bank | Sudah Kembali normal | Monitoring | Op, I&C | Daily | Retrofit ETS Sudah dilakukan assessment dari manufactur sciyon. Masuk usulan program AI 2026 | 1. Har INC | Usulan AI 2026 | |
3 | OPEN COOLING WATER SYSTEM | Normal | Kondisi body debris filter korosi | Kondisi body debris filter korosi | Patrol check/Visual Check | Operasi | Daily | 1.Penggantian valve debris filter (selesai) 2.Penggantian debris filter | 1.harmek 2.Eng 3.Rendal Har | Usulan AI 2027 | |
Perencanaan MO/MD Tindak Lanjut FO-DER
Unit | Equipment | Kondisi | Resiko | Risk Control | Mitigasi | Activity | ||||
FO | FD | Operation Control | PM/ PdM | PO | MO | MD | ||||
1 | Nihil | | | | | | | | | |
2 | Nihil | | | | | | | | | |
Potensi EFOR CHF
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | CRUSHER | Urgent | Kondisi crusher B mengalami kenaikan vibrasi | Kondisi crusher B mengalami kenaikan vibrasi Sudah dilakukan penggantian ring hammer, vibrasi masih tinggi. Monitoring berkala bidang operasi dan enjiniring | Pengecekan vibrasi & Termograf | PdM | M2 & M4 | 1. Penggantian/repair shaft yang aus (inspeksi / pengukuran) (selesai) 2. Penggantian/repair spindle crusher yang oblak (inspeksi / pengukuran) (selesai) 3. Penggantian total hummer (selesai) 4. Penggantian spring support crusher B | 1. Har Mekanik 2. Rendal Har 3. Eng | 2025 online Proses usulan spring support crusher B (pemasangan menunggu spring crusher ready on site) | |
| | | | | | | | | | | |
Potensi EFOR Common
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
1 | Panel 20kv | Urgent | Support panel 20 kV dan MCC ensensial | Support panel 20 kV dan MCC ensensial | Patrol check | Ops | Daily | 1.Penguatan support pondasi bangunan 20 kV 2.Leveling panel 3.Pastikan kekencangan pada baut terminasi Ketika dilakukan perbaikan pada panel 20 kV | 1.Pemeliharaan 2.Rendal Har | Usulan AI2026 | |
2 | COOLING TOWER | Urgent | Filler CT 1 dan 2 rontok | Filler CT 1 dan 2 rontok | Patrol check | Operasi shift | | 1.Pembersihan rutin lumpur pada kolam CT (continuous) 2.Kontrol kualitas air pengisi/make up water – penambahan clarifier (AI 2025) 3.Revitalisasi CT (AI 2025) 4.Menghitung kapasitas pompa SWP M3/Hari | 1.Ops 2.Eng 3.Har | 2025 (online) | |
3 | CWP | Urgent | Kondisi line CWP (Header dan backwater) korosi | Kondisi line CWP (Header dan backwater) korosi | Patrol check/Visual Check | ops | Daily | 1. Penggantian pipa back water 1,2,3 & 4 (selesai) 2. Penggantian pipa header CWP (proses usulan AI2026) 3. Penggantian valve back water (AI2025) | 1.Mek 2.Eng 3.R.har | 1. 2024 (selesai) 2. 2026 3. 2025 | |
Potensi EFOR Common
NO | SYSTEM | PRIORITAS | KONDISI | ACTION PLAN MONITORING RUTIN | ACTION PLAN PENORMALAN | ||||||
MINGGU LALU | SAAT INI | SCOPE | PIC | SCHEDULE | SCOPE | PIC | SCHEDULE | No WO | |||
4 | INTAKE WATER | Urgent | Floating pump mengalami kenaikan vibrasi | Floating pump sudah di lakukkan perbaikan dan untuk saat ini akan di lakukan pengamatan | Pengecekan vibrasi & Thermography | PdM | M2 & M4 | 1. Perbaikan pondasi motor dan pompa (Selesai) 2. Penggantian rubber coupling (Selesai) 3. Setting dan penambahan support sisi line inlet (indikasi pipe string) 4. Inspeksi innerpart pompa dan pengecekan centering housing pompa DE dan NDE | 1.Pemeliharaan 2.Rendal Har | M4 Agustus 2025 | |
5 | CLOSE COOLING SYSTEM | Urgent | Kebocoran pada line outlet HE to cooling tower | Sudah dilakukan penanganan sementara (clamp pipa), kondisi kebocoran sudah minor | Patrol check/Visual Check | Operasi shift | Daily | 1.Perbaikan titik kebocoran menggunakan clamp. (Selesai) 2.Lakukan penggantian line dari outlet HE to cooling tower. | 1.Har Mekanik 2.Rendal Har | | |
Terima Kasih