1 of 15

Cryogenics Overview

Wei Guo

Drive System • CDR 2024

2 of 15

Table of contents

01

Cryogenics system overview

02

System requirements

03

Cost estimation

04

Acquisition schedule

2

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

3 of 15

Table of contents

01

Cryogenics system overview

02

System requirements

03

Cost estimation

04

Acquisition schedule

3

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

4 of 15

Cryogenics system overview

The cryogenics system is comprised of the following components:

4

  • Dilution refrigerator: (to be purchased)
  • Cryocooler
  • Compressor for cryocooler operation
  • Thermal shields and heat exchangers
  • Gas pumping/handling system for driving 3He circulation
  • Support Structure

Mixing chamber plate

Cold plate

Still plate

4K shield

flange

50K shield

flange

50 K

4 K

0.7 K

100 mK

10 mK

  • Upper canisters: (to be fabricated)
  • 50 K upper canister
  • 4 K upper canister
  • Still-plate upper canister
  • Cold-plate upper canister
  • MXC upper canister

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

5 of 15

Cryogenics system overview

The cryogenics system is comprised of the following components:

5

  • Payload canisters and payload box plates: (to be fabricated)
  • 50 K payload canister and box plate
  • 4 K payload canister and box plate
  • Still payload canister and box plate
  • Cold payload canister and box plate
  • MXC box plate

Upper canister

Payload box plate

Payload canister

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

6 of 15

Table of contents

01

Cryogenics system overview

02

System requirements

03

Cost estimation

04

Acquisition schedule

6

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

7 of 15

System requirements

7

ID

Requirement Name

Requirement Text

TE-CRY-1

Material Requirements for internal canisters

The internal radiation shielding canisters shall be XX to meet background requirements. Thermal performance?

TE-CRY-2

Cryostat Dimensions to fit Warm Shielding

The internal cryogenic shielding canisters shall be defined by drawing DWG#X. This will ensure that they fit within the warm shielding and vacuum canister without interference.

TE-CRY-3

Accomodation of Detector Auxiliary Equipment.

- Squid cards (stage 1 and stage 2) as defined in DOC#X�- HEMTs�- He supply and return lines�- etc.

TE-CRY-4

Payload/Detector Weight Capacity

The dilution refrigerator has a limited weight capacity, and needs to accommodate cryogenic shielding, backgrounds shielding. This leads to an allowable detector payload weight of XX kgs.

TE-CRY-5

Heat Dissipation Load of Detectors

The dilution refrigerator shall be sized to dissipate the thermal loads imposed by the detectors, as defined in DOC#X

TE-CRY-6

Heat Conduction Load of Detector Cabling

Heat loads induced by electronics, including detectors, HEMTs, SQUIDs, and cabling, should be carefully analyzed.

TE-CRY-7

Temperature Difference Between Detectors and Mixing Chamber Plate

The design should ensure that the temperature difference between the MXC fridge and the MXC box remains below 1 mK.

TE-CRY-8

Internal background shielding

Lead block dimensions to be XXmm by XXmm�Copper Still Chamber dimensions to be Xmm by Xmm by X mm

TE-CRY-9

Payload Access

The payload canisters shall be designed to be opened and closed to swap detector elements.

TE-CRY-10

Payload Access Frequency

The Payload canisters will be designed to allow for an open/close cycle on a monthly basis.

TE-CRY-11

Upper Dilution Refrigerator Access

The canister design shall allow for complete disassembly and access to the dilution refrigerator internals.

TE-CRY-12

Vibration Isolation of the Dilution Refrigerator

External and internal vibration isolation

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

8 of 15

System requirements

  • Radiation shields requirements: (Yinghe Qi)

8

  • There should be enough gap between shielding canisters and payload boxes.
  • Thermal contraction should be considered in the design.
  • Space for detectors and readout cables.
  • Space for installing readout electronics (Squid cards, stage 1 and stage 2).
  • Arrangement of cables through the narrow gaps between canisters.
  • Enough experimental space in the payload box.
  • All the radiation shields fit the vacuum vessel and do not interfere with each other.
  • The design of the canisters must allow: 1) easy access to the detector elements; 2) easy access to all dilution refrigerator internal components

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

9 of 15

System requirements

  • Thermal requirements: (Yinghe Qi)

9

Mixing chamber plate

Cold plate

Still plate

4K shield

flange

50K shield

flange

50 K

4 K

0.7 K

100 mK

10 mK

  • Temperatures of radiation shielding canisters and boxes must meet refrigerator and detector operation requirements.
  • Heat load from detectors and cables (TES and SQUID readout cables) can be managed by the dilution refrigerator.
  • Need to determine suitable locations for heat sinking detectors and cables.

T (K)

  • Suitable materials and geometry (thickness) to ensure sufficiently small thermal resistance.
  • Interface resistance should be sufficiently small

R. L., Schmitt, et al, Cryogenics, 70, 41 (2015)

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

10 of 15

System requirements

  • Fridge selection: (Scott A. Hertel)

10

  • The dilution refrigerator must be able to sustain the weight of the following items:
  • Radiation shielding canisters and boxes
  • Internal background shielding (lead shielding disc)
  • Payload copper box
  • Gamma Ray shielding: (Bjoern Penning)
  • Internal lead disc shielding and copper box shielding should suppress background events to below targeted threshold
  • Vibration isolation and support structure (Matt Pyle):
  • Fridge vibration suppression: vibration isolation frame, placing compressor in separate room at sufficient distance, etc.
  • Internal vibration isolation system.
  • Cooling power at 4K, 1K, cold plate, and MXC
  • Other factors: quality, service, costs

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

11 of 15

Table of contents

01

Cryogenics system overview

02

System requirements

03

Cost estimation

04

Acquisition schedule

11

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

12 of 15

Cost estimation

  • Dilution refrigerator system:

12

  • Dilution refrigerator
  • Gen-2 Gas handling system
  • Compressor for cryocooler
  • Compressor for driving 3He/4He flow
  • Reinforced internal support structure (rated: up to 350 kg to 4K plate; up to 300 kg to Still plate.)

Estimated subtotal: $600k USD

  • Dilution refrigerator support:
  • Fridge support frame ($10,000)
  • Compressor cabinets ($4,000)
  • Closed cooling water loop ($5,000)
  • Internal OFE copper ($10,000)
  • N2 cold trap ($1,000)
  • 20L 3He ($20,000)

Estimated subtotal: $50k USD

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

13 of 15

Cost estimation

13

  • Shields and miscellaneous:
  • Shields: upper canisters, payload canisters, and payload box plates ($150k USD)

Estimated subtotal: $160k USD

  • Ricochet has an OVC, 50K, 4K, 1K thermal shields in three parts (total length ~1.5 meter) 🡪 80k Euros
  • Our design has complex neck parts that need to be welded
  • Our design has an additional shielding at 100 mK (cold plate)
  • Thermal straps ($4k)
  • Thermometers ($1k/each x 6 = $6k)

Estimated total cost:

$600k + $50k + $160k = $810k

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

14 of 15

Table of contents

01

Cryogenics system overview

02

System requirements

03

Cost estimation

04

Acquisition schedule

14

Presentation Title | BERKELEY LAB

Drive System • CDR 2024

15 of 15

Acquisition schedule

15

2025

(2nd half)

2026

(1st half)

2026

(2nd half)

2027

(1st half)

2027

(2nd half)

Complete Cryo Design

Cryo FDR

Dil Fridge PRR

Order Dil Fridge

Order fridge peripheries: 3He, thermal straps, thermometers, etc.

Fridge Testing and Commissioning

Fabricate canister shields

Commission the full TE cryogenic and fridge assembly

Presentation Title | BERKELEY LAB

Drive System • CDR 2024