Cryogenics Overview
Wei Guo
Drive System • CDR 2024
Table of contents
01
Cryogenics system overview
02
System requirements
03
Cost estimation
04
Acquisition schedule
2
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Table of contents
01
Cryogenics system overview
02
System requirements
03
Cost estimation
04
Acquisition schedule
3
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Cryogenics system overview
The cryogenics system is comprised of the following components:
4
Mixing chamber plate
Cold plate
Still plate
4K shield
flange
50K shield
flange
50 K
4 K
0.7 K
100 mK
10 mK
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Cryogenics system overview
The cryogenics system is comprised of the following components:
5
Upper canister
Payload box plate
Payload canister
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Table of contents
01
Cryogenics system overview
02
System requirements
03
Cost estimation
04
Acquisition schedule
6
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
System requirements
7
ID | Requirement Name | Requirement Text |
TE-CRY-1 | Material Requirements for internal canisters | The internal radiation shielding canisters shall be XX to meet background requirements. Thermal performance? |
TE-CRY-2 | Cryostat Dimensions to fit Warm Shielding | The internal cryogenic shielding canisters shall be defined by drawing DWG#X. This will ensure that they fit within the warm shielding and vacuum canister without interference. |
TE-CRY-3 | Accomodation of Detector Auxiliary Equipment. | - Squid cards (stage 1 and stage 2) as defined in DOC#X�- HEMTs�- He supply and return lines�- etc. |
TE-CRY-4 | Payload/Detector Weight Capacity | The dilution refrigerator has a limited weight capacity, and needs to accommodate cryogenic shielding, backgrounds shielding. This leads to an allowable detector payload weight of XX kgs. |
TE-CRY-5 | Heat Dissipation Load of Detectors | The dilution refrigerator shall be sized to dissipate the thermal loads imposed by the detectors, as defined in DOC#X |
TE-CRY-6 | Heat Conduction Load of Detector Cabling | Heat loads induced by electronics, including detectors, HEMTs, SQUIDs, and cabling, should be carefully analyzed. |
TE-CRY-7 | Temperature Difference Between Detectors and Mixing Chamber Plate | The design should ensure that the temperature difference between the MXC fridge and the MXC box remains below 1 mK. |
TE-CRY-8 | Internal background shielding | Lead block dimensions to be XXmm by XXmm�Copper Still Chamber dimensions to be Xmm by Xmm by X mm |
TE-CRY-9 | Payload Access | The payload canisters shall be designed to be opened and closed to swap detector elements. |
TE-CRY-10 | Payload Access Frequency | The Payload canisters will be designed to allow for an open/close cycle on a monthly basis. |
TE-CRY-11 | Upper Dilution Refrigerator Access | The canister design shall allow for complete disassembly and access to the dilution refrigerator internals. |
TE-CRY-12 | Vibration Isolation of the Dilution Refrigerator | External and internal vibration isolation |
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
System requirements
8
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
System requirements
9
Mixing chamber plate
Cold plate
Still plate
4K shield
flange
50K shield
flange
50 K
4 K
0.7 K
100 mK
10 mK
T (K)
R. L., Schmitt, et al, Cryogenics, 70, 41 (2015)
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
System requirements
10
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Table of contents
01
Cryogenics system overview
02
System requirements
03
Cost estimation
04
Acquisition schedule
11
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Cost estimation
12
Estimated subtotal: $600k USD
Estimated subtotal: $50k USD
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Cost estimation
13
Estimated subtotal: $160k USD
Estimated total cost:
$600k + $50k + $160k = $810k
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Table of contents
01
Cryogenics system overview
02
System requirements
03
Cost estimation
04
Acquisition schedule
14
Presentation Title | BERKELEY LAB
Drive System • CDR 2024
Acquisition schedule
15
| 2025 (2nd half) | 2026 (1st half) | 2026 (2nd half) | 2027 (1st half) | 2027 (2nd half) |
Complete Cryo Design | | | | | |
Cryo FDR | | | | | |
Dil Fridge PRR | | | | | |
Order Dil Fridge | | | | | |
Order fridge peripheries: 3He, thermal straps, thermometers, etc. | | | | | |
Fridge Testing and Commissioning | | | | | |
Fabricate canister shields | | | | | |
Commission the full TE cryogenic and fridge assembly | | | | | |
Presentation Title | BERKELEY LAB
Drive System • CDR 2024