Milestone Guidelines�
Capstone Project
��
Actual costs and Earned Value
Project Documentation
Earned Value Calculations
Project estimated cost = $2 million
Actual spending was $3 million comprising of $2 million which is sourceble and $1 million spent on technology.
the model was estimated to save $200 million and 2001 revenue was estimated to be $800
EVM Calculations
Earned Value
Will be calculated by taking the months where completion has been done over the total time schedule multiplied by budget cost
1859/ 1896 = 98.04%
. 98.04%*2 million = 1.96097 million dollars
Planned value
= 948*5/6 = 0.790 million dollars
Ratios for software customization
SV = BCWP – BCWS where
BCWP = 1.96097million
BCWS =1.896
Sv = 1.96097-1.896 = 0.06497 million
SPI= BCWP / BCWS
1.9607/1.896 = 1.0343
Cost Impact
Control Ratio Calculations
SPI Implication
CPI Implication
Recommendations
Recommendations
References