VBCPS 2023 Update

Second Annual Climate Round Table for Southside Hampton Roads

2 of 6

Solar Update

  • Electricity purchased via PPA is currently 30% cheaper than Dominion's rate
    • 5% increase from 2019 update
      • 9.4¢/kWh (PPA with 1% Escalation Rate) vs 13.5¢/kWh
    • On track to save $3,125,000 over the course of 25 years
      • Projection does not include future Dominion rate hikes

           

Size    

2022 Production

2023 Production (Aug 23)

% Offset

Notes

Ocean Lakes ES

333 kW

 567,013 kWh

443,786 kWh

100%

Original design was 100% offset

Princess Anne MS

660 kW

2,165,067 kWh

1,270,042 kWh

60%

Original design was 51% offset

Renaissance Academy

833.3 kW

4,089,752 kWh

2,895,874 kWh

28%

Original design was 30% offset

Thoroughgood ES

166.4 kW

209,960 kWh

162,358.48 kWh

33%

Original design was 20% offset

Landstown ES/MS*

1.2 MW*

1,769,231* kWh

75%*

*Designed Specifications

Construction held up by State Corporation Commission case PUR-2023-00097

Old Donation School*

571 kW*

838,493* kWh

33%*

Red Mill ES*

462 kW*

647,529* kWh

83%*

3 of 6

Utility Dashboard for Students

  • Worked with Department of Teaching & Learning to incorporate VBCPS utility usage into elementary curriculum
  • Built two custom PowerBI dashboards which are dynamic and interactive
    • All utility usage from 2009
    • Dominion 30-minute usage data since 2020
  • Learning goal is to read and interpret various graphs and tables

4 of 6

NORESCO Rate Analysis

  • Commissioned NORESCO to analyze the 30-minute usage data from 5 different schools
  • VEPGA rates 100, 110, 130, and 132 were all modeled
  • All schools selected will produce guaranteed savings by switching rates
  • Total savings guaranteed at $192,600 over the course of 1 year

5 of 6

Electric Vehicle & Bus Charging Plan

  • Commissioned a study for the potential cost and location of white fleet (cars and maintenance vehicles) and yellow fleet (Buses)
  • Studied the transformer sizes, existing Dominion infrastructure, and parking lot Space availability at 20 locations
  • Goal – 6 DC fast chargers at each site for white fleet
    • 6-8 DC fast chargers for yellow fleet
  • Currently at 95% completion

6 of 6

Questions??� �Thank You

J. Ryan Hersey, PE, LEED BD+C, Sustainability Officer