DEVELOPMENT
OF
20 RAILWAY STATIONS
UNDER
AMRIT BHARAT STATION SCHEME
IN
PUNE DIVISION
BY
GATI-SHAKTI UNIT
Section | SN | Station | Estimated cost (in Cr.) | New Proposed Cost (in Cr.) |
PA-LNL | 1 | Chinchwad | 20.44 | 10.5287 |
2 | Akurdi | 33.83 | 2.4728 | |
3 | Dehu road | 8.05 | 11.2817 | |
4 | Talegaon | 40.34 | 10.7618 | |
PA-BRMT | 5 | Hadapsar | 47.88 | - |
6 | Uruli | 19.79 | - | |
7 | Kedgaon | 12.55 | - | |
8 | Baramati | 11.40 | - |
Section | SN | Station | Estimated cost (in Cr.) | New Proposed Cost (in Cr.) |
PA-KRD | 9 | Lonand | 10.48 | - |
10 | Wathar | 7.97 | 7.01 | |
11 | Satara | 34.31 | 19.6103 | |
12 | Karad | 12.51 | - | |
13 | Phaltan | 0.92 | - | |
KRD-KOP | 14 | Sangli | 24.20 | 19.8713 |
15 | Hathkanangle | 6.00 | 11.8647 | |
16 | Kolhapur | 43.03 | 19.8256 |
STATIONS
Section | SN | Station | Estimated cost (in Cr.) | New Proposed Cost (in Cr.) |
�����DD-MMR | 1 | Daund | 14.24 | 6.8564 |
2 | Ahmednagar | 30.92 | 10.4492 | |
3 | Belapur | 31.96 | 9.9713 | |
4 | Kopargaon | 29.94 | 7.7662 |
STATIONS
S N | Name of station | TDC | Sanction Cost | New proposed cost | Physical Progress | Financial progress | S N | Name of station | TDC | Sanction Cost | New proposed cost | Physical Progress | Financial progress |
1 | Kedgaon | Completed on 28.02.25 FOB: NA | 12.55 | - | 100% | 99.3% | 11 | Talegaon | Soft: 30.09.2026 06 m FOB :31.12.2026, Lift & ESC: 31.03.2027 | 40.34 | 10.7618 | 61% | 52.8% |
2 | Lonand | Completed on 28.02.25 FOB: NA | 10.48 | - | 100% | 99.73% | 12 | Kolhapur | Soft : 31.10.2026 12m FOB: 31.12.2026 LIFT & Escalator – 30.06.2027 | 43.03 | 19.8256 | 57% | 52% |
3 | Phaltan | Completed on 08.03.25 FOB: NA | 0.92 | - | 100% | 99% | 13 | Satara | Soft: 31.12.2026 12m FOB: 31.01.2027 LIFT & ESC -30.09.2027 | 34.31 | 19.6103 | 43% | 39.6% |
4 | Baramati | Completed on 30.09.25 FOB: NA | 11.40 | - | 100% | 99% | 14 | Sangli | Soft: 31.12.26 12m FOB: 31.01.2027 LIFT & ESC -30.09.2027 | 24.20 | 19.8713 | 51% | 50% |
5 | Karad | Soft upgradation & COP:Completed on 30.09.2025 12m FOB: -NA | 12.51 | - | 100% | 99% | 15 | Belapur | Soft: 31.08.2026 6 m FOB: - 31.03.2027 Lift & Escalator - 15.12.2027 | 31.96 | 9.9713 | 47% | 44% |
6 | Wathar | Soft & COP: 30.09.2027 3m FOB: - Being Executed by construction dept. 31.03.2028 | 7.97 | 7.01 | 50% | 46.5% | 16 | Ahmednagar | Soft: 30.08.2026 6 m FOB: - 31.12.2026 Lift & Escalator - 15.12.2027 | 30.92 | 10.4492 | 55% | 52% |
7 | Hadapsar | Soft works, FOB & Skywalk Completed on :10.11.2025 Lift & ESC in circulating area for Divyangjan compliance: 30.04.2026, Lift on PF 1 - 30.09.2026, Escalator on PF 2&3 - 30.09.2026 | 47.88 | - | 96% | 95% | 17 | Hatkanangle | Soft: 31.03.2028 FOB: NA | 6.00 | 11.8647 | 35% | 32.6% |
8 | Uruli | Soft: 30.09.2026 12m FOB: - NA LIFT & ESC: NA | 19.79 | - | 69% | 64% | 18 | Dehu Road | Soft & COP : 31.03.2028 FOB: NA | 8.05 | 11.2817 | 16% | 13% |
9 | Chinchwad | Soft: 31.08.2026 Old FOB Extension :31.12.2026, Lift & ESC: 20.02.2027 | 20.44 | 10.5287 | 79% | 72% | 19 | Daund | Soft: 31.03.2028 FOB: NA | 14.24 | 6.8564 | 47% | 40.69% |
10 | Akurdi | Soft: 31.05.2026 12m FOB: 31.12.2026 Escalator-15.03.2027 | 33.83 | 2.4728 | 64% | 59% | 20 | Kopergaon | Soft : 31.03.2027 6 m FOB: - 31.12.2027, Lift & escalators - 31.03.2028 | 29.94 | 7.7662 | 50% | 46% |
GSU/PA ABSS Stations (Status of Ongoing works)
Talegaon (Estimated cost: 40.39 Cr)
Phase-I Works Soft: 30.09.2026
06 m FOB :31.12.2026, Lift & ESC: 31.03.2027
Current status
Physical Progress- 61%
TALEGAON (SG-3) –Scope of work (overall progress)
Sr No. | Scope | Progress% | Remarks |
| Civil | | |
1 | Construction of Entrance Gate(Main & 2nd Entry) | 100% | |
2 | Development of Circulating Area (UP) | 100% | |
3 | Parking Area Construction (DN) | 80% | |
4 | Façade Work | 100% | |
5 | New Portico Construction (DN) | 100% | |
6 | Renovation of Existing Booking Office | 100% | |
7 | Platform Surface Improvement | 100% | |
8 | Construction of COP | 100% | |
9 | Construction of New Toilet Block | 100% | |
10 | Renovation of Waiting Room | 100% | |
11 | Renovation of Existing Station Superintendent Office and Other Offices | 100% | |
12 | Construction of New Water Booths. | 85% | |
13 | Foot Over Bridge (FOB) Work | 35% | |
14 | Lift 1 on PF1 (DN Side) Main Entry | 60% | |
15 | Lift 2 on PF2 | Not Yet Started | |
16 | Lift 3 at (Up Side) Second entry side | 60% | Required FOB Extension |
17 | Escalator 1 on PF1 (DN Side) Main Entry | 55% | Required FOB Extension |
18 | Escalator 2 on PF2 | Not Yet Started | |
19 | Escalator 3 at second entry side (UP Side) | 62% | |
20 | Landscaping work | 25% | |
TALEGAON (SG-3) –Scope of work (overall progress)
Sr. No. | Scope | Progress% | Remarks |
| Electrical | | |
20 | Lift 1 on PF1 | 20% | |
21 | Lift 2 on PF2 | Not Yet Started | Location not final |
22 | Lift 3 at second entry side (UP Side) | 20% | Beam shifting work in progress |
23 | Escalator 1 on PF1 (DN Side)(Single Direction) | 50% | Hoisting Work Completed |
24 | Escalator 2 on PF2(Single Direction) | Not Yet Started | Location not final |
25 | Escalator 3 at second entry side (UP Side)(Single Direction) | 50% | Hoisting Work Completed |
26 | Electrical works of TRD | 100% | |
| General electrical work |
| |
27 | A. DG Room and DG erection, testing and commissioning | 90% | |
28 | B. Substation erection , Testing and charging | 60% | |
29 | C. Illumination of station building, and circulating area (including high mast) | 60% | |
30 | D. HVAC work | 10% | |
31 | E.Cable dressing and clamping (via cable tray) | 20% | |
32 | Signages | 0% | |
| S & T |
| |
33 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 85 % | |
34 | Telecom, Expansion of information system to facilitate Divyangjan and other PA items | 85% | |
Important new additions and Improvement works planned (Talegaon)
Dehu Road (Estimated cost: 8.05 Cr, New proposed cost: 15.32)
Phase-I Works TDC :
Soft & COP : 31.03.2028
Lift & FOB: 31.03.2028
Current status
Physical Progress-16%
Dehu Road (NSG-3)–Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Civil |
| |
1 | Construction of Entrance Gate | 45% | |
2 | Development of Circulating Area/ Approach road with parking 2nd Entry | 90% | |
3 | Parking Area Construction Main Entrance | 75% | |
4 | Façade Work | 0% | |
5 | New Portico Construction DN side | 15% | |
6 | Renovation of Existing Booking Office | 0% | |
7 | Platform Surface Improvement | 0% | |
8 | Construction of COP | 90% | |
9 | Construction of New Toilet Block | 100% | |
10 | Renovation of Waiting Room | 0% | |
11 | Renovation of Existing Station Superintendent Office and Other Offices | 0% | |
12 | Construction of New Water Booths. | 0% | |
13 | Foot Over Bridge (FOB) Work | NA | |
14 | Provision of Escalators and Lifts (Civil Works) | NA | |
15 | Landscaping Work | 0% | |
16 | 6 M wide FOB | - | Work yet to be taken up |
17 | PF Surfacing | - | Work yet to be taken up |
18 | Water Booth | - | Work yet to be taken up |
19 | Booking office | - | Work yet to be taken up |
| Electrical |
| |
20 | Lift and Escalator | NA | |
21 | Electrical works of TRD | NA | |
| General electrical work |
| |
22 | A. DG Room and DG erection, testing and commissioning | 90 % | Theft incident reported |
23 | B. Substation erection , Testing and charging | 50 % | Theft incident reported |
24 | C. Illumination of station building, and circulating area (including high mast) | 0% | |
25 | D. HVAC work (Fan) | 0% | |
26 | E. Cable dressing and clamping (via cable tray) | 15% | |
27 | Signages | 0% | |
| S & T |
| |
28 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 35% | |
29 | Telecom, Expansion of information system to facilitate Divyangjan and other PA items | 35% | |
| Commercial |
| |
30 | Provision of Furniture ( Commercial Department will provide furniture at the time of inauguration) | - | |
Important new additions and Improvement works planned (Dehu road)
AKURDI (SG-3) Estimated Cost: 33.83 Cr.
�
�
Current status
Physical Progress- 64%
Phase-I Works TDC :
Soft - 31.06.2026
FOB - 31.12.2026
Escalator - 15.03.2027
AKURDI (SG-3) Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Civil |
|
|
1 | Construction of Entrance & Exit Gate | 35% |
|
2 | Development of Circulating Area | 85% |
|
3 | Parking Area Construction | 75% |
|
4 | Façade Work | 75% |
|
5 | New Portico Construction | 80% |
|
6 | Renovation of Existing Booking Office | 0% |
|
7 | Platform Surface Improvement | 90% |
|
8 | Construction of COP | 80% |
|
9 | Construction of New Toilet Block in both side waiting area | 50% |
|
10 | Renovation of Waiting Room both side | 55% |
|
11 | Renovation of Existing Station Offices | 0% |
|
12 | Construction of New Water Booths. | 95% |
|
13 | Foot Over Bridge (FOB) Work | 65% |
|
14 | Lifts | NA |
|
15 | Escalator at PF-1 | Yet To Start | |
16 | Escalator at PF-2 | Yet To Start | |
17 | Landscaping Work | Yet To Start | |
AKURDI (SG-3) Scope of work (Overall Progress)
| Electrical |
|
|
18 | Lifts | NA |
|
19 | Escalator at PF-1(Both Direction) | Yet To Start |
|
20 | Escalator at PF-2(Both Direction) | Yet To Start | |
21 | Electrical works of TRD | NA | |
| General electrical work |
|
|
22 | A. DG Room and DG erection, testing and commissioning | 95% |
|
23 | B. Substation erection , Testing and charging | 95% |
|
24 | C. Illumination of station building, and circulating area (including high mast) | 100% |
|
25 | D. HVAC work (Fan) | 100% |
|
26 | E. Cable dressing and clamping (via cable tray) | 90% |
|
27 | Signages | 0% |
|
| S & T |
|
|
28 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 85% |
|
29 | Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 85% |
|
| Commercial |
|
|
30 | Provision of Furniture ( Commercial Department will provide furniture at the time of inauguration) | - |
|
Important new additions and Improvement works planned (Akurdi)
CHINCHWAD (SG-3) (Estimated cost: 20.44 Cr-)
Current status
Physical Progress- 79%
Phase-I Works TDC :
Soft – 31.08.2025
Old FOB Extension – 31.12.2026
Lift TDC – 20.02.2027
Escalator TDC – 20.02.2027
CHINCHWAD(SG-3) –Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Civil |
| |
1 | Construction of Entrance Gate | NA | Initially planned but cancel due to connection of Metro FOB to Railway Existing FOB |
2 | Development of Circulating Area | 90% | |
3 | Parking Area Construction | 90% | |
4 | Construction of New RPF THANA | 100% | |
5 | New OHE room | 100% | |
6 | Façade Work | 85% | |
7 | New Portico Construction | 90% | |
8 | New Entrance lobby (DN) | 90% | |
9 | Extension of booking office with provision of OFC room, Electrical panel room, CBS room with toilet | 100% | |
10 | Renovation of Existing Booking Office | 95% | |
11 | Platform Surface Improvement | 35% | |
12 | Construction of COP | 83% | |
13 | Construction of New Toilet Block | 90% | |
14 | Renovation of Waiting Room(2nd class) | 90% | |
15 | Renovation of Existing Station Superintendent Office and Other Offices | 85% | |
16 | Construction of New Water Booths. | 0% | |
17 | Foot Over Bridge (FOB) Work(extension) | 25% | |
18 | TOILET UNDER FOB | 90% | |
19 | Lift-1 Main Entry | 100 % | |
20 | Lift-2 on PF-1 &2 | 55 % | |
21 | Lift-3 on PF-3&4 | 55% | |
22 | Lift-4 at Second Entry | 20% | |
23 | Escalator-1 at Main Entry | 100% | |
24 | Escalator-2 at Second Entry | 30% | |
25 | Landscaping work | 30% | |
CHINCHWAD(SG-3) –Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Electrical |
| |
26 | Lift-1 at Main Entry | 100 % | Handover Done |
27 | Lift-2 on PF-1&2 | 80 % | |
28 | Lift-3 on PF-3&4 | 70 % | |
29 | Lift-4 at second Entry | 30 % | |
30 | Escalator -1 at Main Entry(Single Direction) | 100% | Handover Done |
31 | Escalator-2 at Second Entry(Single Direction) | 10% | |
32 | Electrical works of TRD | NA | |
| General electrical work :- | | |
33 | A. DG Room and DG erection, testing and commissioning | 100 % | |
34 | B. Substation erection , Testing and charging | 100 % | |
35 | C. Illumination of station building, and circulating area (including 2 no. high mast) | 70 % | |
36 | D. HVAC work (Fan) | 45 % | |
37 | E. Cable dressing and clamping (via cable tray) | 80% | |
38 | Signages | 0% | |
| S & T |
| |
39 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 85% | |
40 | Telecom, Expansion of information system to facilitate Divyangjan and other PA items. | 75% | |
| Commercial |
| |
41 | Provision of Furniture ( Commercial Department will provide furniture at the time of inauguration) | 0 % | |
Important new additions and Improvement works planned (Chinchwad)
HADAPSAR
(Estimated cost: 47.88 Cr)
Current status
Overall Physical Progress- 96%
Phase-I Works TDC :
Soft, FOB & Skywalk – 10.11.25�1LIFT & 02 Escalator (Circulating area) – 30.04.2026
LIFT ON PF 1 – 30.09.26
ESC ON PF 2/3 – 30.09.2026
�
SN | Scope | Progress % | Remarks |
PHASE-I | | | |
1 | Construction of Entrance Gate | NA | |
2 | Development of Circulating Area | 100% | |
3 | Parking Area Construction | 100% | |
4 | Façade Work | 100% | |
5 | New Portico 1 Construction | 100% | |
6 | New Portico 2 Construction | 100% | |
7 | Building A (reservation office, waiting room, dormitory) | 100% | |
8 | building B (Existing building extension, RPF Post, child care room) | 100% | |
9 | Building C (VIP waiting room, upper class waiting, toilet block, RPF office) | 100% | |
10 | Building D parcel office | 100% | |
11 | Platform Surface Improvement | 100% | |
12 | Construction of COP | 100% | |
13 | Renovation of Waiting Room | 100% | |
14 | Construction of New Water Booths. | 100% | |
15 | Foot Over Bridge (FOB) Work | 100% | |
16 | Skywalk | 100% | |
17 | Lift at Circulating Area | 70% | |
18 | Lift at PF-1 to New FOB | Not Yet Started | GAD Submitted in e-DAS for divisional approval |
19 | Lift at PF-1 to Old FOB | Not Yet Started | GAD Submitted in e-DAS for divisional approval |
20 | Lift at PF-2&3 to Old FOB | Not Yet Started | GAD Submitted in e-DAS for divisional approval |
21 | 02 Escalators at Circulating Area | 85% | |
22 | 01 Escalators at PF-2&3 to New FOB | Not yet Started | GAD Submitted in e-DAS for divisional approval |
23 | Landscaping work | 100% | |
HADAPSAR (NSG-6)–Scope of work (Overall Progress)
SN | Scope | Progress % | Remarks |
PHASE-I | | | |
| Electrical | | |
24 | Lift at Circulating Area | 75 % | |
25 | Lift at PF-1 to New FOB | 0 % | Waiting for electrical lift GAD |
26 | Lift at PF-1 to Old FOB | 0 % | Material received at site |
27 | Lift at PF-2&3 to Old FOB | 0 % | Material received at site |
28 | Escalators at Circulating Area(Both Direction) | 55 % | |
29 | Escalators at PF-2&3 to New FOB(Single Direction) | 0 % | Material received at site |
30 | Electrical works of TRD | 90 % | |
| General electrical work :- | | |
31 | A. DG Room and DG erection, testing and commissioning | 95 % | |
32 | B. Substation erection , Testing and charging | 100 % | |
33 | C. Illumination of station building, and circulating area (including high mast) | 93 % | |
34 | D. HVAC work (Fan) | 90 % | |
35 | E. Cable dressing and clamping (via cable tray) | 90 % | |
36 | Signages | 96 % | |
| S & T |
| |
37 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 85% | |
38 | Telecom, Expansion of information system to facilitate Divyangjan and other PA items. | 75% | |
| Commercial |
| |
39 | Provision of Furniture ( Commercial Department will provide furniture at the time of inauguration) | 100 % | |
HADAPSAR (NSG-6)–Scope of work (Overall Progress)
HADAPSAR
(Estimated cost: 47.88 Cr in PH-53 under ABSS & 135.81 Cr. under PH-16)
Highlights of Planned works
URULI (NSG-5) (Estimated cost: 12.86 Cr)-
Current status
Overall Physical Progress- 69%
Phase-I Works TDC :
Soft – 30.09.2026�12m FOB – NA
Lift & Escalator – NA�
URULI (NSG-5) –Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Civil |
| |
1 | Construction of Entrance Gate | NA | |
2 | Development of Circulating Area | 65 | |
3 | Parking Area Construction | 75 | |
4 | Façade Work | 90 | |
5 | New Portico Construction | 70 | |
6 | Entrance lobby | NA | |
7 | Renovation of Existing Booking Office | NA | |
8 | Platform Surface Improvement | 70 | |
9 | Construction of COP on PF-1 | 100 | |
10 | Construction of COP on PF-2 | 100 | |
11 | Construction of New Toilet Block | 70 | |
12 | Renovation of Waiting Area attached Toilet | 100 | |
13 | Renovation of Existing Station Superintendent Office and Other Offices | 95 | |
14 | Construction of New Water Booths. | 75 | |
15 | Foot Over Bridge (FOB) Work | 80 | |
16 | FOB ramp to Old FOB | NA | |
17 | Provision of Escalators and Lifts | 85 | |
18 | Landscaping work | 10 | |
| Electrical |
| |
19 | Lift and Escalator | NA | |
20 | Electrical works of TRD | 95 % | |
| General electrical work :- | | |
21 | A. DG Room and DG erection, testing and commissioning | 25 % | DG Room work in progress |
22 | B. Substation erection , Testing and charging | NA | |
23 | C. Illumination of station building, and circulating area (including high mast) | 55 % | |
24 | D. HVAC work (Fan) | 0% | |
25 | E. Cable dressing and clamping (via cable tray) | 0% | |
26 | Signages | 0% | |
| S & T |
| |
27 | Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 70% | |
28 | Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 70% | |
| Commercial |
| |
29 | Provision of Furniture. | 0% | |
Important new additions and Improvement works planned (Uruli)
KEDGAON (NSG-5)(Estimated cost: 12.54 Cr)
Current status
Physical Progress- 100%
Phase-I
Soft and COP completed on – 28.02.2025
Station Inaugurated on – 22.05.2025
KEDGAON (NSG-5)–Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
| Civil |
| |
1 | Main Entry Gate | 100% | |
2 | PF1- Construction of Compound Wall | 100% | |
3 | PF1- Construction of Parking Area | 100% | |
4 | PF1- Construction of Portico | 100% | |
5 | Construction of front elevation | 100% | |
6 | Renovation of Existing booking area, Entrance lobby & waiting room | 100% | |
7 | Renovation of Waiting Hall | 100% | |
8 | Construction of PF Toilet Block | 100% | |
9 | Construction of Water Booth | 100% | |
10 | PF SURFACE | 100% | |
11 | PF-1 | 100% | |
12 | PF-2 | 100% | |
13 | Cover Over Platform ( COP ) | 100% | |
14 | PF-1 | 100% | |
15 | PF-2 | 100% | |
16 | FOB ramp PF-1 to Old FOB | 100% | |
17 | FOB ramp PF-2 to Old FOB | 100% | |
18 | Landscaping work | 100% | |
| Electrical |
| |
19 | Lift and Escalator | NA | |
20 | Electrical works of TRD | 100 % | |
| General electrical work :- | | |
21 | A. DG Room and DG erection, testing and commissioning | 100% | |
22 | B. Substation erection , Testing and charging | 100% | |
23 | C. Illumination of station building, and circulating area (including high mast) | 100% | |
24 | D. HVAC work | 100% | |
25 | E. Cable dressing and clamping (via cable tray) | 100% | |
26 | Signages | 100% | |
| S & T |
| |
27 | Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 100% | |
28 | Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 100% | |
29 | Commercial |
| |
30 | Provision of Furniture. | 100% | |
Important new additions and Improvement works planned (Kedgaon)
BARAMATI (NSG-5) (Estimated cost: 11.40 Cr)
Current status
Physical Progress- 100%
Phase-I
Soft & COP Completed on – 30.09.2025
12m FOB – NA
BARAMATI (NSG-5)–Scope of work (Overall Progress)
Sr. No. | Scope | Progress% | Remarks |
PH-1 | Civil |
| |
1 | Construction of Entrance Gate | 100% | |
2 | Development of Circulating Area | 100% | |
3 | Parking Area Construction | 100% | |
4 | Façade Work | 100% | |
5 | New Portico Construction | 100% | |
6 | Construction of Compound Wall | 100% | |
7 | New Entrance lobby (Veranda) | 100% | |
8 | Renovation of Existing Booking Office | 100% | |
9 | New electrical office | 100% | |
10 | Platform Surface Improvement | 100% | |
11 | Construction of COP | 100% | |
12 | Construction of New Toilet Block | 100% | |
13 | Renovation of Waiting Room | 100% | |
14 | Renovation of Existing Station Superintendent Office and Other Offices | 100% | |
15 | Construction of New Water Booths. | 100% | |
16 | Foot Over Bridge (FOB) Work | NA | |
17 | Provision of Escalators and Lifts | NA | |
18 | Landscaping work | 100% | |
| Electrical |
| |
19 | Lift and Escalator | NA | |
20 | Electrical works of TRD | 100 % | |
21 | General electrical work :- | | |
22 | A. DG Room and DG erection, testing and commissioning | 100% | |
23 | B. Substation erection , Testing and charging | 100% | |
24 | C. Illumination of station building, and circulating area (including high mast) | 100% | |
25 | D. HVAC work | 100% | |
26 | E. Cable dressing and clamping (via cable tray) | 100% | |
27 | Signages | 100% | |
| S & T |
| |
28 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 100% | |
29 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 100% | |
| Commercial |
| |
30 | Provision of Furniture | 100% | |
Important new additions and Improvement works planned (Baramati)
PUNE - KARAD
MADHA CONSTITUENCY
(02- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-KRD MADHA | 1 | Wathar, | 7.97 |
2 | Phaltan | 0.76 | |
Total | 8.73 | ||
WATHAR (NSG-6) (Estimated cost: 7.97 Cr, New proposed work Cost: 7.34)
Current status
Physical Progress- 50%
Phase-I
Soft upgradation & COP – 30.09.2027
6m FOB (being constructed by construction dept.) – 31.05.2028
WATHAR (NSG-6) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress % | Remarks |
| Civil | | |
1 | Construction of Entrance Gate | 100% | |
2 | Development of Circulating Area | 100% | |
3 | Parking Area Construction | 100% | |
4 | Façade Work | 100% | |
5 | New Portico Construction | 100% | |
6 | Construction of Compound Wall parking | 100% | |
7 | New Entrance lobby (Verandah) | 100% | |
11 | Renovation of Existing Booking Office | 100% | |
12 | Platform Surface Improvement | 100% | |
13 | Construction of Compound Wall on PF | 100% | |
14 | Improvement of Roof | 100% | |
15 | Construction of COP | 100% | |
16 | Renovation of Toilet Block | 100% | |
17 | Dismantling of Union Office | 100% | |
18 | Renovation of Waiting Room | 100% | |
19 | Renovation of Existing Station Superintendent Office and Other Offices | 100% | |
20 | Construction of New Water Booths. | 100% | |
21 | Foot Over Bridge (FOB) Work | NA | |
22 | Provision of Escalators and Lifts at main entrance (Civil Works) | NA | |
23 | Landscaping work | 100% | |
WATHAR (NSG-6) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress % | Remarks |
| Electrical | | |
24 | Lift and Escalator | NA | |
25 | Electrical works of TRD | NA | |
| General electrical work :- | | |
26 | A. DG Room and DG erection, testing and commissioning | 100% | |
27 | B. Substation erection , Testing and charging | 100% | |
28 | C. Illumination of station building, and circulating area (including high mast) | 100% | |
29 | D. HVAC work | 100% | |
30 | E. Cable dressing and clamping (via cable tray) | 100% | |
31 | Signages | 100% | |
| S & T | | |
32 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 100% | |
33 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 100% | |
| Commercial | | |
34 | Provision of Furniture | 0% | |
Important new additions and Improvement works planned (Wathar)
Current status
Physical Progress- 100%
PHALTAN (Estimated cost: 0.92 Cr)
Phase-I
Soft and COP completed on – 28.02.2025
FOB – NA
PHALTAN Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
1 | COP | 100% | |
2 | Repairing of Existing PF Surface | 100% | |
3 | Seating Facilities | 100% | |
4 | Entrance Ramp | 100% | |
5 | Painting Work of Existing Station Building | 100% | |
5.Renovation of Existing Building
Important new additions and Improvement works planned (Phaltan)
LONAND (Estimated cost: 10.47 Cr)
Current status
Physical Progress- 100%
Phase-I
Soft and COP completed on – 28.02.2025
12m FOB – NA
Station Inaugurated on – 22.05.2025
LONAND (NSG-6) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
| Civil | | |
1 | Construction of Entry Gate | 100% | |
2 | Construction of Compound Wall | 100% | |
3 | Construction of New portico | 100% | |
4 | Construction of Circulation Area | 100% | |
5 | Construction of Parking | 100% | |
6 | Renovation of Booking Office and Entrance Lobby | 100% | |
7 | PF-1 Construction of New Toilet block | 100 % | |
8 | PF-1 Construction of Waiting Room | 100 % | |
9 | PF-1 Improvement of new water booths | 100 % | |
10 | PF-2 Construction of New Toilet block | 100 % | |
11 | COP PF 1 | 100 % | |
12 | COP PF 2 | 100 % | |
13 | Improvement of Platform Surface PF1 | 100 % | |
14 | Improvement of Platform Surface PF2 | 100 % | |
15 | Landscaping work | 100% | |
| Electrical | | |
16 | Lift and Escalator | NA | |
17 | Electrical works of TRD | NA | |
| General electrical work :- | | |
18 | A. DG Room and DG erection, testing and commissioning | 100% | |
19 | B. Substation erection , Testing and charging | 100% | |
20 | C. Illumination of station building, and circulating area (including high mast) | 100% | |
21 | D. HVAC work | 100% | |
22 | E. Cable dressing and clamping (via cable tray) | 100% | |
23 | Signages | 100% | |
| S & T | | |
24 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 100% | |
25 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 100% | |
| Commercial | | |
26 | Provision of Furniture | 100% | |
Important new additions and Improvement works planned (Lonand)
SATARA (Estimated cost: 34.31 Cr, New proposed work cost: 19.21)
Current status
Physical Progress- 43%
Phase-I Works TDC:
Soft – 31.12.2026
FOB – 31.01.2027
Lift TDC – 30.09.2027
Escalator TDC – 30.09.2027
Sr. No. | Scope | Progress% | Remarks |
| Civil | | |
1 | Construction of Entrance Gate | 90% | |
2 | Construction of Exit Gate | 90% | |
3 | Development of Circulating Area | 55% | |
4 | Parking Area Construction | 60% | |
5 | Façade Work | 0% | |
7 | New Portico Construction | 90% | |
8 | New Entrance lobby (Verandah) | 10% | |
9 | Renovation of Existing Booking Office | 5% | |
10 | Platform Surface Improvement PF-1 | 45% | |
11 | Platform Surface Improvement PF -2/3 | 5% | |
12 | Construction of COP at PF - 1 | 85% | |
13 | Construction of COP at PF 2-3 | 25% | |
14 | PF-1 Construction of New Toilet block | 85% | |
15 | PF-2&3 - Construction of New Toilet block | 0% | |
16 | PF-4&5 -Construction of Toilet Block | 0% | |
17 | Renovation of SM Rest Room | 80% | |
18 | PF-1 Renovation of Ladies waiting room with Toilet Block | 80% | |
19 | Renovation of Upper-Class waiting room with Toilet Block | 100% | |
20 | PF-1 Renovation of Parcel Office | 0% | |
21 | Construction of new TI Room | 80% | |
22 | Renovation of Existing Station Superintendent Office and Other Offices | NA | |
23 | Construction of New Water Booths. | 0% | |
24 | Foot Over Bridge (FOB) Work 12 M | 55% | |
25 | Lift at PF-1 | 0% | |
26 | Lift at PF-2&3 | 0% | |
27 | Lift at PF 3&4 | 0% | |
28 | Escalator at PF-1 | 0% | |
29 | Escalator at PF-2&3 | 0% | |
30 | Escalator at PF – 4&5 | 0% | |
31 | Landscaping work | 0% | |
SATARA (NSG-5) Scope of work (Overall Progress)
SATARA (NSG-5) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
32 | Improvement of COP | | |
33 | Developing circulating area + road + Parking | | |
34 | Retaining wall | | |
35 | Compound wall | | |
36 | Main station building renovation | | |
37 | Landscaping | | |
38 | Water booth | | |
39 | Painting old structure | | |
40 | Divyagjan friendly toilet at PF No. 04 | | |
41 | Seating facility | | |
| Electrical | | |
42 | Lift at PF-1 | 0% | |
43 | Lift at PF-2&3 | 0% | |
44 | Lift at PF 3&4 | 0% | |
45 | Escalator at PF-1(Both Direction) | 0% | |
46 | Escalator at PF-2&3(Both Direction) | 0% | |
47 | Escalator at PF – 4&5(Both Direction) | 0% | |
48 | Electrical works of TRD | 100% | |
| General electrical work :- | | |
49 | A. DG erection, testing and commissioning | 100% | |
50 | B. Substation erection , Testing and charging | 25% | |
51 | C. Illumination of station building, and circulating area (including high mast) | 45% | |
52 | D. HVAC work | 45% | |
53 | E. Cable dressing and clamping (via cable tray) | 55% | |
54 | Signages | 0% | |
| S & T | | |
55 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 50% | |
56 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 50% | |
| Commercial | | |
57 | Provision of Furniture | | |
Important new additions and Improvement works planned (Satara)
KARAD (NSG-5) (Estimated cost: 12.50 Cr, New proposed work cost: 8.33)
Current status
Physical Progress- 100%
Phase-I Works TDC:
Soft upgradation & COP – Completed on 30.09.2026
12m FOB – NA
Sr. No. | Scope | Progress% | Remarks |
1 | Construction of Entrance Gate | 100% | |
2 | Development of Circulating Area | 100% | |
3 | Parking Area Construction | 100% | |
4 | Façade Work | 100% | |
5 | New Portico Construction | 100% | |
6 | Construction of Compound Wall parking | 100% | |
7 | New Entrance lobby (Verandah) | 100% | |
8 | Renovation of Existing Booking Office | 100% | |
9 | Platform Surface Improvement on PF-1 | 100% | |
10 | Renovation of Compound Wall on PF | 100% | |
11 | Construction of COP | 100% | |
12 | construction of divyanjan Toilet Block | 100% | |
13 | Renovation of Toilet Block | 100% | |
14 | Renovation of Waiting Room | 100% | |
15 | Renovation of Existing Station Superintendent Office and Other Offices | 100% | |
16 | Renovation of New Water Booths. | 100% | |
17 | Foot Over Bridge (FOB) Work | NA | |
18 | Provision of Escalators and Lifts | NA | |
19 | Landscaping work | 100% | |
20 | PF Surfacing | - | Work yet to be taken up |
21 | Balance COP | - | Work yet to be taken up |
22 | Divyangjan friendly toilet | - | Work yet to be taken up |
23 | Repairs of existing structure | - | Work yet to be taken up |
24 | Provision of 2 Nos of lift | - | Work yet to be taken up |
25 | Water booth | - | Work yet to be taken up |
KARAD (NSG-5) Scope of work (Overall Progress)
KARAD (NSG-5) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
| Electrical | | |
26 | Lift and Escalator | NA | |
27 | Electrical works of TRD | NA | |
| General electrical work :- | | |
28 | A. DG Room and DG erection, testing and commissioning | 100% | |
29 | B. Substation erection , Testing and charging | 100% | |
30 | C. Illumination of station building, and circulating area (including high mast) | 100% | |
31 | D. HVAC work | 100% | |
32 | E. Cable dressing and clamping (via cable tray) | 100% | |
33 | Signages | 100% | |
| S & T | | |
34 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 100 | |
35 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 100 | |
| Commercial | | |
36 | Provision of Furniture | 0% | |
Important new additions and Improvement works planned (Karad)
SANGLI CONSTITUENCY
(01- STATION)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
KRD-KOP / SANGLI | 1 | Sangli | 24.20 |
Total | 24.20 | ||
SANGLI (Estimated cost: 24.19 Cr, New proposed work cost: 14.92)
Current status
Physical Progress- 51%
Phase-I Works TDC :
Soft TDC – 31.12.2026
FOB TDC – 31.01.2027
Lift TDC – 30.09.2027
Escalator TDC – 30.09.2027
Sr. No. | Scope | Progress% | Remarks |
1 | Construction of Entrance Gate | 97% | |
2 | Development of Circulating Area | 92% | |
3 | Construction of Parking Area | 90% | |
4 | Construction of Compound Wall | 98% | |
5 | Construction of New Portico | 97% | |
6 | Construction of new Booking Office | 100% | |
7 | Improvement of Façade | 0% | |
8 | Renovation of Second-class waiting room | 75% | |
9 | General Toilet with Divyangjan toilet | 100% | |
10 | Upper class waiting room with toilet block | 75% | |
11 | COP PF1 | 95% | |
12 | COP PF 2-3 | 60% | |
13 | COP PF 4-5 | 25% | |
14 | Improvement of Platform Surface PF 1 | 96% | |
15 | Construction of FOB | 70% | |
16 | Lift at PF-1 | 0% | |
17 | Lift at PF 2&3 | 0% | |
18 | Lift at PF 4&5 | 0% | |
19 | Escalator at PF1 | 0% | |
20 | Escalator at PF 2&3 | 0% | |
21 | Escalator at 4&5 | 0% | |
22 | Landscaping work | 0% | |
23 | PF Surfacing | - | Work yet to be taken up |
24 | Improvement of COP | - | Work yet to be taken up |
25 | Landscaping | - | Work yet to be taken up |
26 | Water booth | - | Work yet to be taken up |
27 | Seating facilities | - | Work yet to be taken up |
28 | Renovation of existing parking area | - | Work yet to be taken up |
29 | Renovation of existing booking office | - | Work yet to be taken up |
30 | Improvement of station building | - | Work yet to be taken up |
SANGLI (NSG-5) Scope of work (Overall Progress)
SANGLI (NSG-5) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
| Electrical | | |
31 | Construction of Civil Works For Escalator | Nil | |
32 | Lift at PF-1 | Nil | |
33 | Lift at PF 2&3 | Nil | |
34 | Lift at PF 4&5 | Nil | |
35 | Escalator at PF1(Both Direction) | Nil | |
36 | Escalator at PF 2&3(Single Direction) | Nil | |
37 | Escalator at 4&5(Single Direction) | Nil | |
38 | Electrical works of TRD | 100% | |
| General electrical work :- | | |
39 | A. DG Room and DG erection, testing and commissioning | 80% | |
40 | B. Substation erection , Testing and charging | 40% | |
41 | C. Illumination of station building, and circulating area (including high mast) | 60% | |
42 | D. HVAC work | 10% | |
43 | E. Cable dressing and clamping (via cable tray) | 35% | |
44 | Signages | 0% | |
| S & T | | |
45 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 70% | |
46 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 70% | |
| Commercial | | |
47 | Provision of Furniture | | |
Important new additions and Improvement works planned (Sangli)
KARAD-KOLHAPUR
HATKANANGLE CONSTITUENCY
(01- STATION)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
MRJ-KOP / HATKANANGLE | 1 | Hathkanangle | 6.0 |
Total | 6.0 | ||
HATKANANGALE (NSG-5) (Estimated cost: 6.00 Cr (New proposed work cost: 8.45)
Current status
Physical Progress- 35%
Phase-I :
Soft TDC – 31.03.2028 FOB TDC – NA
Sr. No. | Scope | Progress | Remarks |
1 | Construction of Entrance Gate | 90% | |
2 | Development of Circulating Area | 90% | |
3 | Parking Area Construction | 85% | |
4 | Façade Work | 75% | |
5 | New Portico Construction | 100% | |
6 | New Entrance lobby (Verandah) | 95% | |
7 | Renovation of Existing Booking Office | 0% | |
8 | Platform Surface Improvement on PF-1 | 65% | |
9 | Platform Surface Improvement on PF-2 | 70% | |
10 | Construction of COP | 95% | |
11 | construction of Toilet Block | 95% | |
12 | construction of Waiting Room | 95% | |
13 | Renovation of Existing Station Superintendent Office and Other Offices | 0% | |
14 | Renovation of New Water Booths. | 0% | |
15 | Foot Over Bridge (FOB) Work | NA | |
16 | Provision of Escalators and Lifts | NA | |
17 | Landscaping work | 0% | |
18 | Balance COP | - | Work yet to be taken up |
19 | Water booth | - | Work yet to be taken up |
20 | Compound wall | - | Work yet to be taken up |
21 | Station building | - | Work yet to be taken up |
22 | Rain wall harvesting | - | Work yet to be taken up |
23 | Ramp | - | Work yet to be taken up |
24 | Divyangjan friendly toilet | - | Work yet to be taken up |
25 | Retaining wall | - | Work yet to be taken up |
HATHAKANANGLE (NSG-5) Scope of work (Overall Progress)
HATHAKANANGLE (NSG-5) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress | Remarks |
| Electrical | | |
26 | Lift and Escalator | NA | |
27 | Electrical works of TRD | 100% | |
| General electrical work | | |
28 | A. DG Room and DG erection, testing and commissioning | 75% | |
29 | B. Substation erection , Testing and charging | 75% | |
30 | C. Illumination of station building, and circulating area (including high mast) | 70% | |
31 | D. HVAC work | 50% | |
32 | E. Cable dressing and clamping (via cable tray) | 60% | |
33 | Signages | 0% | |
| S & T | | |
34 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 50% | |
35 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 50% | |
| Commercial | | |
36 | Provision of Furniture | 0% | |
Important new additions and Improvement works planned (Hatkanangle)
KOLHAPUR (NSG-3) (Estimated cost: 43.03 Cr)
Current status
Physical Progress- 57%
Phase-I :
Soft TDC – 31.10.2026
FOB TDC – 31.12.2026
Lift TDC – 30.06.2027
Escalator TDC – 30.06.2027
KOLHAPUR (NSG-3) Scope of work (Overall Progress)
SN | Scope | Progress% | Remarks |
1 | Construction of Entry Gate | 95% | |
2 | Construction of Exit Gate | 95% | |
3 | Construction o Circulation area | 30% | |
4 | Construction of Parking Area | 0% | |
5 | Cover over existing pathway in front of existing building | 95% | |
6 | Improvement of Facade | 95% | |
7 | Construction of new portico | 99% | |
8 | Extension of Existing portico | 95% | |
9 | PF-1 Renovation of Existing Entrance lobby | 2% | |
10 | PF-1 Renovation of VIP Entrance lobby | 98% | |
11 | Construction of New Booking office | 100% | |
12 | Construction of Public Toilet Block | 100% | |
13 | Main Station Building Roofing Work | 100% | |
14 | Removal of Union office | 100% | |
15 | PF-1 Renovation of existing General class waiting room | 0% | |
16 | PF-1 Renovation of existing AC waiting room With Male & Female Toilet Blocks | 100% | |
17 | PF-1 Renovation of existing PRS | 99% | |
18 | PF-1 Renovation of existing Ladies waiting room | 100% | |
19 | PF-1 Construction of New Toilet block | 100% | |
20 | PF-1 Construction of new water booths | 0% | |
21 | PF-2&3 Construction of New Toilet block | 100% | |
22 | COP - PF1-2 | 98% | |
23 | COP – PF-3 | 0% | |
24 | Improvement of Platform Surface PF1 (Work done as per Instruction) | 10% | |
25 | Improvement of Platform Surface PF2-3 | 100% | |
26 | Construction of 12m wide FOB | 47% | |
27 | Development of Second entry (UP side) with circulating area improvement and parking. | NA | |
28 | Lift at PF-1 | Nil | |
29 | Lift at PF-2 | Nil | |
30 | Escalator at PF-1 | Nil | |
31 | Escalator at PF2 | Nil | |
32 | Landscaping work | 0% | |
KOLHAPUR (NSG-3) Scope of work (Overall Progress) | | ||
Sr. No. | Scope | Progress% | Remarks |
| Electrical | | |
33 | Lift at PF-1 | 0% | GAD in under process |
34 | Lift at PF-2 | 0% | GAD in under process |
35 | Escalator at PF-1(Both Direction) | 0% | GAD in under process |
36 | Escalator at PF2(Both Direction) | 0% | GAD in under process |
37 | Electrical works of TRD | 100% | |
| General electrical work :- | | |
38 | A. DG Room and DG erection, testing and commissioning | 100% | |
39 | B. Substation erection , Testing and charging | 100% | |
40 | C. Illumination of station building, and circulating area (including high mast) | 90% | |
41 | D. HVAC work | 90% | |
42 | E. Cable dressing and clamping (via cable tray) | 80% | |
43 | Signage | 0% | |
| S & T | | |
44 | Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 50% | |
45 | Telecom, Expansion of information system to facilitate divyangjan and other PA items | 50% | |
| Commercial | | |
45 | Provision of Furniture | 0% | |
Important new additions and Improvement works planned (Kolhapur)
Daund Estimated cost: 44.17 Cr, (New proposed work cost: 17.01)
Current status
Physical Progress- 47%
Phase-I : Soft TDC – 31.03.2028
Daund Scope of work (Overall Progress)
SN | Scope | Progress% | Remarks |
1 | 1.Station Approach road (PA Side) | 100% | |
2 | Repairs to existing buildings | 100% | |
3 | PF Surfacing | 100% | |
4 | Model Toilet | 100% | |
5 | power house area road work in progress | 95% | |
6 | PF Shelter (COP) | 75% | |
7 | Relocation of Units | 80% | |
8 | Improvements to water stands | 50% | |
9 | Quarters type-3 | 90% | |
10 | � Illumination & Signages | 0% | |
11 | FOB | 0% | |
12 | Lift | 0% | |
13 | Escalator | 0% | |
14 | New station building | - | Work yet to be taken up |
15 | Parking | - | Work yet to be taken up |
16 | Toilets | - | Work yet to be taken up |
17 | PF Surfacing | - | Work yet to be taken up |
18 | Balance COP | - | Work yet to be taken up |
Renovation works: Renovation to existing quarters.
Important new additions and Improvement works planned (Daund)
AHMEDNAGAR (Estimated cost: 30.92 Cr)
Current status
Overall Physical Progress- 55%
Phase-I Works TDC :
Soft TDC – 30.08.2026
FOB TDC – 31.12.2026
Lift & Escalator TDC – 15.12.2027
Ahmednagar Scope of work (Overall Progress)
SN | Scope | Progress% | Remarks |
1 | Station Approach road completed (PA Side) | 100% | |
2 | Renovation to existing buildings | 100% | |
3 | Parcel Office | 100% | |
4 | Building "B" ( CCI Office, CHI Office, TI/N, TI/S, Telecom office, Electric 2.Office, RPF Thana, Retiring Room, VIP Room.) | 100% | |
5 | Circulating area Infront of booking office | 100% | |
6 | Two-wheeler parking | 100% | |
7 | Fountain Renovation. | 100% | |
8 | power house area road | 100% | |
9 | Improvement of Drainage | 100% | |
10 | Building "A" (ADEN Office, General Waiting Hall, Toilets including Ladies, Gents & Divyangjan, Food Plaza, Electric Charging Room, RMS ) | 92% | |
11 | PF Shelter (COP) | 100% | |
12 | Improvements to water stands | 10% | |
13 | Toilet | 95% | |
14 | Booking Office Renovation | 85% | |
15 | PF Surfacing | - | |
16 | Illumination & Signages | - | Works yet to be takenup |
17 | Landscaping work | 0% | |
18 | FOB | 0% | |
19 | Lift | 0% | |
20 | Escalator | 0% | |
Important new additions and Improvement works planned (Ahmednagar)
KOPARGAON (Estimated cost: 29.94 Cr)
Current status
Overall Physical Progress- 50%
Phase-I Works TDC :
Soft – 31.03.2027
FOB – 31.12.2027
LIFT & ESC – 31.03.2028
Kopargaon Scope of work (Overall Progress)
SN | Scope | Progress% | Remarks |
1 | 1.Front Façade of Station PF Circulating Area | 100% | |
2 | PF Shelter | 100% | |
3 | PF Surfacing | 100% | |
4 | Waiting Hall (Sleeper, General & Ladies ) | 100% | |
5 | Parking for 2 & 4-Wheeler | 100% | |
6 | Station Wall | 100% | |
7 | Electric sub station | 100% | |
8 | Gang hut Relocation | 100% | |
9 | Drainage improvement | 100% | |
10 | Entry Gate | 100% | |
11 | Renovation to existing Booking office | 100% | |
12 | Bay COP | 100% | |
13 | Toilet (New/ Renovation) | 100% | |
14 | Service Building | 100% | |
15 | Pathway | 96% | |
16 | Illumination & Signages | 0% |
|
17 | Landscaping | 0% | |
18 | FOB | 0% | |
19 | Lift | 0% | |
20 | Escalator | 0% | |
Provision of 2 nos. retiring rooms for passengers, widening of platform 1 towards DD end for 45 m., improvement to drainage was also done.
Important new additions and Improvement works planned (KOPARGAON)
BELAPUR (Estimated cost: 31.96 Cr)
Current status
Overall Physical Progress- 47%
Phase-I Works TDC:
Soft – 31.08.2026
FOB – 31.03.2027
Lift & Esc – 15.12.2027
Belapur Scope of work (Overall Progress)
SN | Scope | Progress% | Remarks |
1 | Waiting Hall ( General & Upper Class ) | 100% | |
2 | PF1 Shelter & PF 2 Shelter | 100% | |
3 | Entry Gate & Exit Gate | 100% | |
4 | Relocation of 10 Qtrs. | 100% | |
5 | Relocation of Sump | 100% | |
6 | Augmentation of Drainage line | 100% | |
7 | Improvement to Bldg. | 83% | |
8 | Service Building | 96% | |
9 | Circulating Area | 75% | |
10 | PF Surfacing | 42% | |
11 | Toilet (New) | 75% | |
12 | New Booking Office | 90% | |
13 | Electric sub station | 95% | |
14 | Front Facade & Portico | 35% | |
15 | 2 & 4-wheeler parking | 78% | |
16 | Improvement of Water Stand | 10% | |
17 | Illumination & Signages | 0% |
|
18 | Landscaping | 0% | |
19 | FOB | 0% | |
20 | Lift | 0% | |
21 | Escalator | 0% | |
Provision of 2 nos. retiring rooms for passengers, extension of platform 1 towards DD end for 150 m., improvement to drainage was also done.
Important new additions and Improvement works planned (BELAPUR)
THANKS