Our Pursuit For Excellence customer’s satisfaction every time without quality variance…surpass
LME OFFICE
LME TEAM
LME WORKSHOP
About Us
Policies
Vision : Providing the enhanced customer service solutions at all times.
Mission : Delivering the best solutions to our customers ,employees, suppliers by working together and high transparency at all levels of technical and commercial aspects.
Quality : Delivering the customer expectations on right time
Price : Assuring the customer money is delivered with right services
People : Treating them as our assets and assuring the careness
Success Policy
TRUST
Truthful
Relationship
Unique
Smart solutions
Time
Industries� Covered
Marine
Industrial
Oil & Gas
LME Services
Rewinding Services
Electrical Services
Fabrication Services
Mechanical Services
Diesel (Marine & IND) engines overhauling
Complete solutions for Diesel Engines/Overhauling of Diesel Engine ( All major Brands )
(in-situ)
Rewinding of Motors & Alternators :��Rewinding of Motors and Alternators�( 0 .5 – 3000 kW )�
( AC / DC )
Mechanical Repairs �( Maintenance / Repair / Refurbishment )
(Service & Manufacturing)
Mechanical Repairs �( Maintenance / Repair / Refurbishment )
( Hydraulic & Mechanical )
Mechanical Repairs �( Maintenance / Repair / Refurbishment )
Fabrication Services
Electrical Services
LME Major Client’s
Some of Timebound Project’s Achievement’s
Project Details
|
Project Deliverables |
Client : Al Mansoori Pdn Services LLC.
Description : Major Overhauling of Oil Well Pump RIP-008
|
Deliverables : Overhauling of Oil Well Pump X 1 No
Achievements : Complete Overhauling owas done by our Team with target delivery time by overhauling of Engine Detroit 8V92, Allison Transmission & Oil Well Pump SA640 with Skid Fabrication
|
Client : Al Mansoori Pdn Services LLC.
Description : Complete Refurbishment of Tripex SPM Pump APU0003
|
Deliverables : Complete Refurbishment of SPM Pump
Achievements : Complete Refurbishment was been carried out with minimum targeted cost by Overhauling of Detroit Series 60, Allison Transmission 4000 Series, SPM Pump TWS600S 4.5”. |
Project Details
|
Project Deliverables |
Client : Zakher Marine Intl Inc
Description : Top Overhauling of Nigata 6L25HX ( 2 Nos )
|
Deliverables : Top Overhauling of Nigata 6L25HX X 2 NOS
Achievements : Job was being carried out at Dubai Port at Vessel Zakher Provider. Completed in 7 Days within limited Time Frame. |
Client : Hyundai Engineering
Description : Rewinding of 1500 Kva Alternator
|
Deliverables : Rewinding of 1500 Kva Alternator
Achievements : Job was completeted with full satisfaction as per customer requirement and even though winding wires was being imported from Overseas. |
Project Details
|
Project Deliverables |
Client : GISCO – Gulf Industrial Services Company
Description : Major Overhauling of CAT 3208
|
Deliverables : Major Overhauling of CAT 3208
Achievements : Actually the end user of the engine was UAE Military and being used on very critical operations, Delivery was done in 7 Days including Dyno Testing. |
Client : Allianz Middle East Ship Mgmt LLC.
Description : Overhauling of KTA 19 x 2 Nos
|
Deliverables : Overhauling of KTA 19 X 2 Nos
Achievements : Parts was also sourced by Us and at very competitive price for Genuine parts and we have completed 2 Engines where our Competitor has completed only one engine within the given Time Frame. |
Project Details
|
Project Deliverables |
Client : Mermaid Marine Services LLC.
Description : Top Overhauling of KTA 50
|
Deliverables : Top Overhauling of KTA 150
Achievements : As this Job was done middle of the Sea as Engine was brokedown. |
Client : Pioneer Engineering
Description : Major Overhauling of BF4M2012
|
Deliverables : Major Overhauling of BF4M2012
Achievements : As customer was very much happy with the Quality as this Unit was being repaired and Delivered to South Africa. |
Project Details
|
Project Deliverables |
Client : Speedy International Inc
Description : Electrical Refurbishment of MTU 2000 Kva
| Deliverables : Electrical Refurbishment of MTU 2000 Kva Genset
Achievements : Job was done with the Lowest cost to the customer by using alternative solutions on the complete Genset control System. |
Client : AM Marine
Description : Overhauling of CAT 3412 X 2 NOS
|
Deliverables : Overhauling of CAT 3412 X 2 Nos
Achievements : Cylinder Block was damaged since Marine block was not available we have converted industrial block and completed the Job. |
Stability
Why to choose LME ?
Contact Details
Latest Mechanical Equipment Llc.,
PO Box #: 91976, Workshop No. 2,
Plot No. 76, M-37, Musaffah inds
Area, Abu Dhabi – UAE.
Tel: +971 2 554 7422
Fax: +971 2 554 7633
Website: www.latestme.com
Ram Prasad TC
Business Operations Manager
Mobiile # +971 55 501 6078
Email: ram@latestme.com
Ramesh Gupta
Finance Manager
Mobile # +971 52 6113820
Email : ramesh@latestme.com