EGYPT � ISLAMIC � CULTURAL � CENTER
PROJECT SCOPE
PROJECT LOCATION
PROJECT LOCATION
Project Overview
3B(LE)
440700 m²
32 Months
PROJECT COMPONENTS
EGYPT MOSQUE
TWO MINARETS
The West Service Building
The East Service Building
THE WEST HALL
THE EAST HALL
The Cultural Center
Graduation Project Scope
19,100 m²
12,000 Prayer
656,400,000 LE
PROJECT PARTICIPANTS
Armed Forces Engineering Authority (owner)
Arab Contractors
(Main Contractor)
ENGINEERING CONSULTANTS GROUP (Consultant)
PROJECT CHARTER
Project Name | Egypt Islamic Cultural Center |
Project Start Date | 23/10/2019 |
Project Expected Finish Date | 8/10/2021 |
Owner | Armed Forces Engineering Authority |
Project Main Contractor | Arab Contractors |
Project Consultant | ECG |
Contract Type | Cost Plus |
Project Description: |
The Egypt Islamic Cultural Center is in the middle of the New Administrative Capital on a plateau 24 meters high in the middle of the government district, where the project overlooks from the south side the Green River and from the north side the presidential axle and Sahet El-Shaab, where the mosque accommodates a total of 12,000 prayers. -Site Location: Egypt Islamic Cultural Center is in New Capital of EYGPT, it exists in the middle of the governmental district, it is bounded by Sahet El-Shaab and road 11 from one side and Mohamed ben Zayed from the other side |
PROJECT CHARTER
Project Goals and Purpose |
|
Deliverables | |
-Praying Square | -Hall of doctrines teaching |
-Hall of Qur’an memorization | -Hall of sunnah teaching |
-Occasions Hall | -Retail stories |
-Restaurant | -The Cultural commercial center |
-Parking spaces | -Building Services |
PROJECT CHARTER
Scope Definition |
Construction of a mosque with an area of 19100 square meters to accommodate 12,000 prayers, two western and eastern halls with an area of 3055 square meters and 2800 square meters and two minarets with a height of 140 meters and an area of 1600 square meters each, In scope: Egypt Mosque Out of scope: |
The Cultural Center | Minarets | Landscaping |
The East Hall | The West Hall | Parking |
The West Service Building | The East Service Building | |
PROJECT CHARTER
Assumptions and Constrains |
Assumptions:
Constrains:
Success Criteria:
|
Project High Level Risk |
|
SITE MANAGEMENT
IMPORTANCE OF SITE ORGANISATION IN CONSTRUCTION
PROJECT LAYOUT
ENTRANCES, EXITS AND MOVEMENT PATH
CARAVANS
MATERIALS STORAGE
CONSTRUCTION SITE STRATEGY
The West & East Hall
Egypt Mosque
The Minarets
The West & East Service Buildings
Parking
The Culture Centre
Landscape
CONSTRUCTION ALTERNATIVES STUDY
Benefits of Construction Alternative study
The main stages of alternative study using VE:
Information
Phase
Creativity
Phase
Analysis
Phase
Development
Phase
Presentation
Phase
Value engineering potential saving during the project period:
Alternatives Case Study:
Comparison between Cup-Lock Formwork & Bailey Bridge Formwork:
No. | Characteristics | Cup-Lock Formwork | Bailey Bridge Formwork |
1 | Re-usage value of formwork | 100-250 times | 100-350 times |
2 | Rate of production | 4 Towers/Day | 5 Towers/Day |
3 | Tools needed for demolition of formwork | A hammer is the only tool required for dismantle the system | Hammer, wrench |
4 | Specialty in construction | Scaffold system and horizontal buildings | Vertical buildings, bridges, chimneys and tanks |
5 | Labor & Equipment resource | 2-4 workers | 2workers & crane |
6 | Wastage of formwork material | Low | Very low |
7 | Spacing between elements | 500 mm | 100-300 mm |
Alternative study for formwork:
Methods of evaluating alternatives will be according to: Scale: (1 → 5)
1. Economic Factors.
2. Engineering Factors.
The evaluation method steps:
1. The weighted of desired criteria.
2. The analysis of desired criteria.
The weighted evaluation method :
Criteria of evaluation :
A. Special Need.
B. Safety during construction.
C. Cost.
D. Rate of Production.
E. Easy of Construction.
F. Availability.
Criteria of evaluation | Row weight | Normalized weight |
Special Need | 12 | 31% |
Safety during construction | 10 | 25% |
Cost | 9 | 23% |
Rate of Production | 5 | 13% |
Easy of Construction | 3 | 8% |
Availability | 0 | 0% |
Total | 39 | 100% |
Alternative study for formwork:
Construction Material | Special Needs | Safety during construction | Cost | Rate of Production | Easy of Construction |
Cup-Lock Formwork | 5 | 4 | 5 | 3 | 2 |
Bailey-bridge Formwork | 7 | 6 | 4 | 2 | 1 |
Evaluation Criteria | Normalized Weight | Alternatives | |||
Cup-Lock Formwork | Bailey-bridge Formwork | ||||
Rank | Score | Rank | Score | ||
Special Need | 31% | 5 | 155 | 7 | 217 |
Safety during construction | 25% | 4 | 100 | 6 | 150 |
Cost | 23% | 5 | 115 | 4 | 92 |
Rate of Production | 13% | 3 | 39 | 2 | 26 |
Easy of Construction | 8% | 2 | 16 | 1 | 8 |
Total | 100% | 425 | 493 | ||
Second: Alternatives for construction of the main dome:
Comparison between 3 methods that can be used for the main dome:
(Fixing then Exterior GRC & Interior Finishes GRP)
(Exterior Finishing GRC then Fixing and Interior Finishes GRP)
(Exterior GRC & Interior GRP Finishes then Fixing)
Finishing & Fixing process for 3rd Method
Alternative study for Main Dome:
Methods of evaluating alternatives will be according to:
The evaluation method steps:
The weighted evaluation method :
Criteria of evaluation :
Scale: (1 → 5)
Criteria of evaluation | Row weight | Normalized weight |
Cost | 10 | 37% |
Time consumed | 8 | 30% |
Safety during construction | 5 | 18% |
Easy of Construction | 4 | 15% |
Availability | 0 | 0% |
Total | 26 | 100% |
Alternative study for Main Dome:
Then for our project we choose the 3rd method as it's the more safe, cost reduced, time consumption and suitable for our site working strategy to compensate the project's cost and time and to more likely to limit the risks which is our first priority.
Construction Material | Cost | Time consumed | Safety during construction | Easy of Construction |
Method No. 1 | 3 | 2 | 2 | 1 |
Method No. 2 | 3 | 3 | 1 | 1 |
Method No. 3 | 4 | 3 | 2 | 2 |
Evaluation Criteria | Normalized Weight | Alternatives | |||||
Method No. 1 | Method No. 2 | Method No. 3 | |||||
Rank | Score | Rank | Score | Rank | Score | ||
Cost | 37% | 3 | 111 | 3 | 111 | 4 | 148 |
Time consumed | 30% | 2 | 60 | 3 | 90 | 3 | 90 |
Safety during construction | 18% | 2 | 36 | 1 | 18 | 2 | 36 |
Easy of Construction | 15% | 1 | 15 | 1 | 15 | 2 | 30 |
Total | 100% | 222 | 234 | 304 | |||
RESOURCE MANAGEMENT
RESOURCE ELEMENT
Resources classifications:
LABOR
EGYPT MOSQUE RESOURCE
EGYPT MOSQUE RESOURCE
EQUIPMENT
EGYPT MOSQUE RESOURCE
MATERIAL
EGYPT MOSQUE RESOURCE
Resource calculations for Pouring for foundation plan concrete :
1 m3 of plan concrete = 350 kg cement + 0.4 m3 sand + 0.8 m3 coarse aggregate + 200 L water
Cost of 1 m3 of plan concrete (ready mix) = 725 L.E
The price included 5% wastage of concrete.
Amount of concrete = 2118.87 m3
Pouring crew = 2 skilled labor + 2 formers + 2 helper
Production rate for 1 crew = 140 m3 / Day
Cost for crew per day = 6 * 150 = 900 L.E
Number of crews needed = 4 crews / Day
EGYPT MOSQUE RESOURCE
Resource calculations for Pouring for foundation plan concrete :
Item | Activities | Laborer | Non-labor |
| Material |
| |||||
Crew | PR/Day | No. Of Crews | Equipment | Num | Duration | Item | Amount | Unit |
| ||
Earthwork | Excavation | 1 Surveyor | 400 | 155 | loader | 155 | 5 |
| 310000 | m³ |
|
1 Laborer | 2 Truck | 310 |
| ||||||||
Soil replacement | 3 Laborer | 200 | 24 | Loader | 24 | 5 | Clear Sand | 24000 | m³ |
| |
Escort Roller | 24 |
| |||||||||
Backfilling | 1 Surveyor | 200 | 69 | Loader | 69 | 21 | Clear Sand | 286000 | m³ |
| |
1 Laborer | Escort Roller | 69 |
| ||||||||
Plain Concrete Works For Footing | Formwork Works | 1 Carpenter | 20 | 0 |
|
| 15 |
|
|
|
|
2 Helper |
|
|
|
|
|
| |||||
1 Laborer |
|
|
|
|
|
| |||||
Pouring | 6 Laborer | 140 | 4 | Concrete pump | 1 | 5 | Ready Mix Concrete | 2118.87 | m³ |
| |
| |||||||||||
Deshuttering Formwork | 1 Carpenter | 30 | 1 |
|
| 5 |
|
|
| | |
2 Helper |
|
|
|
|
| | |||||
1 Laborer |
|
|
|
|
| | |||||
Reinforced Concrete Works For Footings | Formwork Works | 1 Carpenter | 20 | 0 |
|
| 19 |
|
|
| |
2 Helper |
|
|
|
|
| | |||||
1 Laborer |
|
|
|
|
| | |||||
Fixing Steel | 4 Steel Fixer | 1 | 16 |
|
| 21 | Reinforcement Steel | 334.0284 | ton | | |
6 Helper |
|
| | ||||||||
Strengthening | 1 Carpenter | 20 | 1 |
|
| 7 |
|
|
| | |
2 Helper |
|
|
|
|
| | |||||
1 Laborer |
|
|
|
|
| | |||||
Pouring | 6 Laborer | 140 | 4 | Concrete pump | 1 | 5 | Ready Mix Concrete | 2783.57 | m³ | | |
| |||||||||||
Curing | 2 Skilled Laborer |
| 1 |
|
| 10 |
|
|
| | |
Deshuttering Formwork | 1 Carpenter | 30 | 1 |
|
| 5 |
|
|
| | |
2 Helper |
|
|
|
|
| | |||||
1 Laborer |
|
|
|
|
| | |||||
RESOURCE PLANNING
Structure Example:
Q= 2118.87
P.R=140 m/ day
D= 5 days
N.C= (Q / P.R*D) = 4 crews
RESOURCE PLANNING
Item | Activities | Laborer | Material | |||||
Crew | PR/Day | No. Of Crews | Duration | Item | Amount | Unit | ||
Moisture Insulation | Walls | 2 Laborer | 100 | 3 | 64 | APP Rolls | 17155 | m² |
Floors | 2 Laborer | 100 | 2 | 34 | 4330 | m² | ||
Thermal Insulation | Floors | 1 Technical | 100 | 2 | 34 | Polystyrene Rolls | 4330 | m² |
2 Laborer | ||||||||
Screed Works For Roof | Roof Floor | 2 Skilled Laborer | 100 | 1 | 55 | Concrete Foam | 4330 | m² |
1 Helper | ||||||||
Masonry Works | Thickness = 100/200 mm | 1 Skilled Laborer | 25 | 3 | 562 | Thickness = 100 mm | 1074 | m² |
1 Semiskilled Laborer | Thickness = 200 mm | 25300 | ||||||
1 Helper | Thickness = 200 mm | 2950 | ||||||
Thickness = 200 mm | 285 | |||||||
Handrails Works | Installations | 1 Skilled Laborer | 50 | 1 | 5 | Handrails for Mihrab | 68 | m |
1 Helper | Handrails for Entrances | 115 | ||||||
Plastering Works | Plastering Works For Walls | 1 Skilled Laborer | 37 | 3 | 66 | Mortar | 7166 | m² |
1 Semiskilled Laborer | ||||||||
1 Helper | ||||||||
Plastering Works For Ceiling | 1 Skilled Laborer | 30 | 4 | 44 | Mortar | 5222 | m² | |
1 Semiskilled Laborer | ||||||||
1 Helper | ||||||||
Painting Works | Painting | 1 Skilled Laborer | 100 | 2 | 120 | Acrylic Painting | 12388 | m² |
1 Helper | ||||||||
Architecture example:
LABOR RESOURCE HISTOGRAM
Arches (Formwork crew – steel fixing crew concrete pouring crew - concrete curing crew) – Fire fighting crew – mechanical equipment fixation crew – BMS crew – Lighting crew
Slabs (Formwork crew – steel fixing crew concrete pouring crew - concrete curing crew)
EQUIPMENT RESOURCE HISTOGRAM
Man lift – Mobile crane – Concrete pump
Concrete Pump – Loader - Truck
CONSTRUCTION METHOD STATEMENT
CONSTRUCTION STRATEGY
CONSTRUCTION STRATEGY
CONSTRUCTION STRATEGY
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
The main steel beam
The Secondary steel beam
Braces
Steel Plate
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
Procurement & bailey bridge fixing
Assembling of 12 supplied segment (guide)
Assembling the twelve other segments in the site
Water leaking test
Trial lifting test
Install GRC as external finishing beginning from fourth ring to tenth ring
Install GRP as internal finishing for the dome
Lifting, fixing the dome
Continue GRC installation for first, second & third ring
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
METHOD OF CONSTRUCTION
WBS & ACTIVITY LIST
PROJECT WBS
STRUCTURAL WORKS WBS
MEP WORKS WBS
ARCHITECTURAL WORKS WBS
Project Name | Project Phase | Disciplines | Project Zone | Level | Work package |
MSQ | CST | STR | Z00 | L00 | XXX |
WBS ID SYSTEM
Structural WBS
Project Name | Project Phase | Disciplines | Project Zone | Finishing description | Level | Work package |
MSQ | CST | ARC | Z00 | XXX | L00 | XXX |
Architectural WBS
Project Name | Project Phase | Disciplines | Project Zone | Level | MEP category | Work package |
MSQ | CST | MEP | Z00 | L00 | XXX | XXX |
MEP WBS
EGYPT MOSQUE
Construction
MEP Works
Mihrab zone
Level 4.85
Mechanical
HVAC
First Fix
WBS ID SYSTEM
ACTIVITY LIST
Columns work |
Shuttering counter for columns |
Fixing steel for columns |
Second shuttering and Strengthening counter formwork for columns |
Pouring concrete for columns |
Curing for columns |
Deshuttering counter formwork for columns |
Disciplines | Project Zone | Level | Work package | Numbering |
ST | Z0 | L00 | XX | 00000 |
Structural activity
Disciplines | Project Zone | Level | Finishing description | Work package | Numbering |
AR | Z0 | L00 | XX | XX | 00000 |
Architectural activity
Disciplines | Project Zone | Level | MEP category | Work package | Numbering |
MP | Z0 | L00 | XX | XX | 00000 |
MEP activity
ACTIVITY ID SYSTEM
MEP
THE EAST ENTRANCE
Level 17.85
Mechanical
HVAC
Numbering
ACTIVITY ID SYSTEM
QUANTITY SURVEYING
QUANTITY SURVEYING TYPES AND TOOLS
Quantity surveying
Initial survey
Preparation stage
Construction stage
Actual / Engineering surveying
Implementation stage
Delevering stage
UNITS USED IN EGYPT MOSQUE PROJECT
Meter
Square meter
Cubic meter
Number
Ton
METHODS OF QS
Footing:
Quantity = (length * width * depth) * no. of model
Tie Beam:
Quantity = clear length * width * depth
Columns for each level:
Quantity = (length * width * clear height) * no. of model
Slabs:
Quantity = (area* thickness) + total drop panel vol. - opening vol.
Beams:
Quantity = length * width * depth*no. of beams
FOUNDATION QS
Quantity = (length * width * depth) * no. of model
PC & RC FOOTING CALCULATIONS EXAMPLE
RC TIE BEAM FOUNDATION
Quantity = clear length * width * depth
RC Tie Beam Calculations Example
COLUMNS QS
Quantity = (length * width * clear height) * no. of model
COLUMNS CALCULATION EXAMPLE
This example represents columns (from the foundation level to level 4.85) :
SLABS QS
Quantity = (area* thickness) + total drop panel vol. - opening vol.
BEAMS QS
Quantity = length * width * depth*no. of beams
FRAMES QS
Quantity = length * width * depth*no. of beams
SLAB REINFORCEMENT QS
RFT weight / ton for slab (top or bottom) =
(total area * weight of bar /m * number of bar /m) /1000
Additional RFT weight / ton for slab (top or bottom) =
(Length of bar*number of bar /m * distribution distance * weight of bar /m *replication number) / 1000
RFT bar chair weight / ton for slab =
(Number of bar * length of bar * weight of bar /m) / 1000
SLAB REINFORCEMENT QS
Reinforcement for slab level (+9.35)
SLAB REINFORCEMENT QS EXAMPLE
SLAB REINFORCEMENT QS EXAMPLE
TOTAL QS ERROR PERCENTAG TABLE
Item | Q.S | BOQ | Error % |
PC Foundation (m³) | 2118.87 | 2000 | 5.49 |
RC Foundation (m³) | 7228.18 | 7550 | -4.26 |
RC Columns (m³) | 5369.5 | 5150 | -4.26 |
SOG (m²) | 15563.12 | 16500 | -5.68 |
RC Slabs (m³) | 8569.43 | 9400 | -8.83 |
Pre-cast Ribs (m³) | 991.45 | 1000 | -0.86 |
Topping Slab for pre-cast rips (m²) | 4845.75 | 4500 | 7.68 |
Arches (m³) | 760.13 | 800 | -4.98 |
Frames (m³) | 2140.87 | 2050 | 4.43 |
TOTAL QS ERROR PERCENTAG DIAGRAM
TIME SCHEDULE
PROJECT CALENDAR
MAIN PROCESSES FOR TIME SCHEDULE
Develop schedule
Estimate activity duration
Sequence activities
Define activities
ACTIVITY SEQUENCE
Develop schedule
Estimate activity duration
Sequence activities
Define activities
ACTIVITY SEQUENCE
Develop schedule
Estimate activity duration
Sequence activities
Define activities
ESTIMATE DURATION
Activity name: Installing Plaster coats for walls ground story
Quantity: 2913 m2
No. of crews: 4/Day
Production rate: 37 m2/d
Duration = 2913/ (4*37) = 19.682 d = 20 Day.
Duration = Quantity (Q) / Production Rate (PR) * No. Of Crews
Equation: -
Develop schedule
Estimate activity duration
Sequence activities
Define activities
DEVELOP SCHEDULE
Develop schedule
Estimate activity duration
Sequence activities
Define activities
PROJECT TOTAL DURATION
PROJECT GANNT CHART
TIME SCHEDULE EVALUATION
TIME SCHEDULE EVALUATION
�
FS (90.8%)
FF (6%)
SS (3.2%)
SF (0%)
COST ESTIMATION
INTRODUCTION
Bid Price = Direct Costs + Indirect Costs + Markup
BID PRICE
COST
DIRECT COST
LABOR
EQUIPMENT
MATERIAL
INDIRECT COST
Project overhead
General overhead
MARKUP
PROFIT
RISK CONTINGENCY
COST ESTIMATE
1- Material
1 m2 of plastering = 0.03 m3 sand + 6 kg cement
Total cost of plastering materials =
12264+ 75050 + 5596 +37164= 130,074 (LE.)
2- labor
Crew consists of:
COST ESTIMATE
= 3* 620*66=122,760 (LE.)
= (7166*10.5) + 122,760 = 198,003(LE.)
Total direct Cost of 1m2 = 198003/7166 = 26.51 (LE.)
COST ESTIMATE
= 4* 620*44=109,120 (LE.)
= (5222*10.5) + 109,120 = 163,951 (LE.)
Total direct Cost of 1m2 = 163,951/5222 = 31.39 (LE.)
COST ESTIMATE
INDIRECT COST
PROJECT OVERHEAD
Project Overhead | |||
Job Title | No. | Salary/month (L.E) | Total/month (L.E) |
Project Manager | 1 | 40,000.00 | 40,000.00 |
Construction Manager | 3 | 20,000.00 | 60,000.00 |
Site Engineer | 8 | 9,000.00 | 72,000.00 |
Technical office Engineer | 4 | 8,000.00 | 32,000.00 |
Supervisor | 8 | 6,500.00 | 52,000.00 |
Utilities | - | - | 350,000.00 |
Caravans | 9 | 10,000.00 | 90,000.00 |
Mobile crane | 6 | 3,000.00 | 18,000.00 |
lift machine | 5 | 2,000.00 | 10,000.00 |
First Aid Equipment | - | 25,000.00 | 25,000.00 |
Tower Crane | 4 | 500,000.00 | 2,000,000.00 |
GENERATOR | 4 | 70,000.00 | 280,000.00 |
Consultant Requirements | - | 50,000.00 | 50,000.00 |
Site Clearing | - | 600,000.00 | 600,000.00 |
Site Fence | - | 913,604.63 | 913,604.63 |
Total / Month (L.E) | 3,079,000.00 | ||
Total Project Duration (month) | 24 | ||
Total Project Overhead Cost (L.E) | 75,409,604.63 | ||
INDIRECT COST
GENERAL OVERHEAD
General Overhead | |||
Job Title | No. | Salary/month (L.E) | Total/month (L.E) |
Board Member | 1 | 95,000.00 | 95,000.00 |
Sector Manager | 1 | 50,000.00 | 50,000.00 |
Deputy branch manager | 1 | 45,000.00 | 45,000.00 |
Total / Month (L.E) | 190,000.00 | ||
Total Project Duration (month) | 24 | ||
Project Overhead Cost (L.E) | 4,560,000.00 | ||
Relative weight for the MOSQUE | 40% | ||
Total Project Overhead Cost (L.E) | 1,824,000.00 | ||
BID PRICE
Item | Matrial | Labor | Equipment | Quantity | Lumpsum | Item Direct Cost | Item Price | |
Total Price | Unit Price | |||||||
STRUCTURAL WORKS | ||||||||
Earthwork | 9,300,000.00 | 943,600.00 | 8,931,200.00 | 620,000.00 |
| 19,174,800.00 | 28,344,961.72 | 45.72 |
Plain Concrete Works For Footing | 6,882,089.76 | 123,000.00 | 1,500.00 | 2,000.00 |
| 7,006,589.76 | 10,357,423.21 | 5,178.71 |
Reinforced Concrete Works For Footings | 14,219,867.35 | 764,960.00 | 3,000.00 | 4,000.00 |
| 14,987,827.35 | 22,155,610.10 | 5,538.90 |
Mass Reinforced Concrete Works For Footings | 23,314,201.76 | 1,295,900.00 | 3,000.00 | 4,500.00 |
| 24,613,101.76 | 36,384,078.44 | 8,085.35 |
Jacketing Reinforced Concrete Works For Footings | 692,900.00 | 18,240.00 | 600.00 | 200.00 |
| 711,740.00 | 1,052,122.74 | 5,260.61 |
Reinforced Concrete Works For Columns | 37,980,521.64 | 3,400,240.00 | 32,400.00 | 5,150.00 |
| 41,413,161.64 | 61,218,603.66 | 11,887.11 |
Reinforced Concrete Works For SOG | 16,541,124.78 | 675,000.00 | 20,500.00 | 16,500.00 |
| 17,236,624.78 | 25,479,873.04 | 1,544.23 |
Reinforced Concrete Works For Slabs, Beams and Stairs | 54,738,943.81 | 2,709,700.00 | 108,600.00 | 10,400.00 |
| 57,557,243.81 | 85,083,436.21 | 8,181.10 |
Reinforced Concrete Works For Pre-cast Ribs | 5,507,504.75 | 420,000.00 | 21,600.00 | 1,200.00 |
| 5,949,104.75 | 8,794,206.27 | 7,328.51 |
Reinforced Concrete Works For Topping Slab For Pre-cast Ribs | 1,923,515.81 | 122,400.00 | 2,400.00 | 3,500.00 |
| 2,048,315.81 | 3,027,902.93 | 865.12 |
Reinforced Concrete Works For Archs | 3,501,561.88 | 194,740.00 | 3,900.00 | 800.00 |
| 3,700,201.88 | 5,469,787.46 | 6,837.23 |
Reinforced Concrete Works For Frames | 20,215,164.98 | 1,691,200.00 | 9,600.00 | 2,000.00 |
| 21,915,964.98 | 32,397,062.21 | 16,198.53 |
Metal Frame Works For Small and Middle Domes | 2,438,646.00 | 211,800.00 | 72,000.00 | 66.00 |
| 2,722,446.00 | 4,024,429.34 | 60,976.20 |
Metal Frame Works For Main Dome | 3,503,000.00 | 378,000.00 | 108,013.00 | 172.00 |
| 3,989,013.00 | 5,896,719.69 | 34,283.25 |
Insulation For Foundation | 1,400,000.00 | 30,000.00 | - | 10,000.00 |
| 1,430,000.00 | 2,113,883.60 | 211.39 |
BID PRICE
Item | Material | Labor | Equipment | Quantity | Lumpsum | Item Direct Cost | Item Price | |
Total Price | Unit Price | |||||||
FINISHES WORKS | ||||||||
Moisture Insulation | 966,825.00 | 78,000.00 | - | 21,485.00 |
| 1,044,825.00 | 1,544,502.40 | 71.89 |
Thermal Insulation | 259,800.00 | 37,400.00 | - | 4,330.00 |
| 297,200.00 | 439,333.01 | 101.46 |
Screed Works For Roof | 947,454.00 | 143,000.00 | - | 16,622.00 |
| 1,090,454.00 | 1,611,953.03 | 96.98 |
Masonry Works | 2,159,373.50 | 1,045,320.00 | - | 29,609.00 |
| 3,204,693.50 | 4,737,307.02 | 160.00 |
Handrails Works | 315,800.00 | 2,100.00 | - | 183.00 |
| 317,900.00 | 469,932.59 | 2,567.94 |
Plastering Works (for walls) | 75,243.00 | 122,760.00 | - | 7,166.00 |
| 198,003.00 | 292,696.01 | 40.85 |
Plastering Works (for ceiling) | 54,831.00 | 109,120.00 |
| 5,222.00 |
| 163,951.00 | 242,358.97 | 46.41 |
Floor Works (marble) | 2,711,000.00 | 161,700.00 | - | 3,511.00 |
| 2,872,700.00 | 4,246,540.85 | 1,209.50 |
Floor Works (granite) | 5,751,250.00 | 244,750.00 |
| 6,515.00 |
| 5,996,000.00 | 8,863,528.72 | 1,360.48 |
Floor Works (vynle) | 12,500.00 | 550.00 |
| 50.00 |
| 13,050.00 | 19,291.04 | 385.82 |
Floor Works (epoxy) | 1,584,980.00 | 61,050.00 |
| 3,686.00 |
| 1,646,030.00 | 2,433,227.85 | 660.13 |
Floor Works (carpet) | 19,052,600.00 | 93,750.00 |
| 12,292.00 |
| 19,146,350.00 | 28,302,905.78 | 2,302.55 |
Floor Works (morter) | 158,263.00 |
|
| 13,762.00 |
| 158,263.00 | 233,950.74 | 17.00 |
Painting Works | 309,700.00 | 103,200.00 | - | 12,388.00 |
| 412,900.00 | 610,365.41 | 49.27 |
Marble Cladding Works | 47,505,609.00 | 5,911,500.00 | - | 37,838.00 |
| 53,417,109.00 | 78,963,322.16 | 2,086.88 |
Doors Installation Works (Metal model 3) | 100,000.00 | 3,000.00 | - | 5.00 |
| 103,000.00 | 152,258.75 | 30,451.75 |
Doors Installation Works (Metal model 3) | 73,600.00 | 2,000.00 |
| 4.00 |
| 75,600.00 | 111,754.97 | 27,938.74 |
Doors Installation Works (Metal model 6) | 48,000.00 | 1,000.00 |
| 3.00 |
| 49,000.00 | 72,433.77 | 24,144.59 |
BID PRICE
Item | Material | Labor | Equipment | Quantity | Lumpsum | Item Direct Cost | Item Price | |
Total Price | Unit Price | |||||||
Doors Installation Works (wooden) | 828,238.00 | 9,450.00 |
| 460.16 |
| 837,688.00 | 1,238,304.14 | 2,691.03 |
Doors Installation Works (aluminume) | 12,757.50 | 400.00 |
| 7.29 |
| 13,157.50 | 19,449.95 | 2,668.03 |
Windows Installation Works | 3,070,830.48 | 12,400.00 | - | 1,962.19 |
| 3,083,230.48 | 4,557,755.49 | 2,322.79 |
Signs Installation Works | 25,600.00 | 3,000.00 | - | 8.00 |
| 28,600.00 | 42,277.67 | 5,284.71 |
Bayonet Installation Works (H 1.2 m) | 115,200.00 | 6,750.00 | - | 12.00 |
| 121,950.00 | 180,271.40 | 15,022.62 |
Bayonet Installation Works(H 2.4 m) | 153,600.00 | 6,000.00 |
| 8.00 |
| 159,600.00 | 235,927.15 | 29,490.89 |
Bayonet Installation Works(H 8 m) | 64,000.00 | 3,000.00 |
| 1.00 |
| 67,000.00 | 99,042.10 | 99,042.10 |
Steel Mesh Installation Works (grill) | 6,000.00 | 750.00 |
| 1.00 |
| 6,750.00 | 9,978.12 | 9,978.12 |
GRC Works (for domes) | 8,898,000.00 |
|
| 3,559.20 |
| 8,898,000.00 | 13,153,382.01 | 3,695.60 |
GRC Works (cornice, H 2 m) | 534,000.00 |
|
| 356.00 |
| 534,000.00 | 789,380.31 | 2,217.36 |
GRC Works (cornice, H 2.5 m) | 810,000.00 |
|
| 432.00 |
| 810,000.00 | 1,197,374.63 | 2,771.70 |
GRC Works (cornice, H 2.75 m) | 837,375.00 |
|
| 406.00 |
| 837,375.00 | 1,237,841.45 | 3,048.87 |
GRC Works (cornice, H 2.9 m) | 691,650.00 |
|
| 318.00 |
| 691,650.00 | 1,022,424.89 | 3,215.17 |
GRC Screens Works | 4,833,400.00 |
|
| 1,859.00 |
| 4,833,400.00 | 7,144,926.57 | 3,843.42 |
GRP Work (for domes) | 9,552,000.00 |
|
| 3,184.00 |
| 9,552,000.00 | 14,120,151.15 | 4,434.72 |
GRP Work (for ceiling) | 21,884,800.00 |
|
| 10,942.40 |
| 21,884,800.00 | 32,350,992.88 | 2,956.48 |
MEP Work | ||||||||
MEP Work |
|
|
|
| 76,563,544.61 | 76,563,544.61 | 113,179,315.62 | |
BID PRICE
BID PRICE
BID PRICE
Foundation works – columns works
Backfilling – Foundation– SOG – columns
Foundation-SOG - insulation for foundation– Slabs– columns works
foundation - SOG – columns – Slabs - circular beam – deep beam – inverted beam – Electrical works - Block works - Plastering
34,339,887 M
53,545,864 M
42,397,366 M
37,887,645 M
Backfilling - foundation - insulation - SOG – columns –Slabs - circular beam – Domes – inverted beam- deep beam – Electrical works – Plastering – GRC - GRB
28,355,023 M
columns –Slabs - circular beam – Pre-cast ribs - Pre-cast slab – HVAC works – Fire fighting works - Electrical works – Cladding works – Bayonet works
28,355,023 M
BID PRICE
CASH FLOW
CASH FLOW
CASH FLOW
Months | Cash out | Cum cash out | Cash in | Cum cash in |
0 | 0.00 | 0.00 | 0.00 | 0.00 |
2 | 33,376,507.51 | 33,376,507.51 | 65,639,127.27 | 65,639,127.27 |
4 | 64,837,951.55 | 98,214,459.06 | 37,041,384.38 | 102,680,511.65 |
6 | 37,562,154.34 | 135,776,613.40 | 71,957,423.49 | 174,637,935.14 |
8 | 31,706,778.60 | 167,483,391.99 | 41,686,632.32 | 216,324,567.46 |
10 | 25,643,251.16 | 193,126,643.16 | 35,188,312.41 | 251,512,879.87 |
12 | 30,371,003.23 | 223,497,646.39 | 28,458,984.89 | 279,971,864.77 |
14 | 33,051,958.44 | 256,549,604.83 | 33,705,863.45 | 313,677,728.22 |
16 | 37,333,789.67 | 293,883,394.50 | 36,681,198.50 | 350,358,926.71 |
18 | 52,553,270.79 | 346,436,665.29 | 41,433,192.29 | 391,792,119.00 |
20 | 47,084,646.86 | 393,521,312.15 | 58,323,834.61 | 450,115,953.61 |
22 | 34,429,631.07 | 427,950,943.23 | 52,254,733.43 | 502,370,687.03 |
24 | 13,982,112.56 | 441,933,055.79 | 38,210,145.21 | 540,580,832.24 |
26 | 1,652,853.81 | 443,585,909.60 | 15,517,405.64 | 556,098,237.88 |
27 |
| 443,585,909.60 | 100,293,034.81 | 656,391,272.69 |
TOTAL | 656,391,272.69 | |||
CASH FLOW
CASH FLOW
UPDATED SCHEDUALE
INTRODUCTION
INTRODUCTION
UPDATE SCHEDULE
UPDATE SCHEDULE
UPDATE SCHEDULE
UPDATE SCHEDULE
UPDATE SCHEDULE
UPDATE COST
UPDATE COST
UPDATE COST
UPDATE COST
EARNED VALUE ANALYSIS
EARNED VALUE ANALYSIS
Earned value management is a project management technique for measuring project performance and progress. It has the ability to combine measurements of the project
EARNED VALUE ANALYSIS
EARNED VALUE ANALYSIS
BCWS (PV) = 487,670,765.89
BCWP (EV) = 478,172,457.61
ACWP (AC) = 482,800,135.05
(SV) = (EV)–(PV)
= 478,172,457.61– 487,670,765.89 = -9,498,308.28 L.E (Behind Schedule)
(CV) = (EV)–(AC)
=478,172,457.61– 482,800,135.05= -4,627,677.44 L.E (over budget)
EARNED VALUE ANALYSIS
CPI = EV/AC
= 478,172,457.61/ 482,800,135.05= 0.990
(over budget)
SPI = EV/PV
= 478,172,457.61/ 487,670,765.89 = 0.980
(Behind Schedule)
EARNED VALUE ANALYSIS
Budget at Completion (BAC) = 656,391,268.32
Estimated at Completion (EAC)
= 482,800,135.05 + 656,391,268.32 - 478,172,457.61
= 661,018,945.8 L.E
= 482,800,135.05 + (656,391,268.32 - 478,172,457.61) / 0.990
= 662,819,135.8 L.E
= 482,800,135.05 + [(656,391,268.32 -478,172,457.61) / (0.990 * 0.980)]
= 666,492,992.9 L.E
Take the biggest value
EAC = 666,492,992.9 L.E
UPDATE TIME SCHEDULE
UPDATE TIME SCHEDUALE
CONTRACT
WHY WE NEED CONTRACTS?
Contracts provide a description of responsibilities.
Contracts can secure payment.
Contracts bind parties to their duties.
Contracts provide recourse when the relationship falters.
Contracts can establish a time frame for duties.
TYPE OF CONTRACTS
TYPES OF TENDERS
DELIVERY METHOD
CONTRACT VS FIDIC
IN CONTRACT:
IN FIDIC:
Comment:
No Difference between contract and FIDIC
IN CONTRACT:
IN FIDIC:
Comment:
No Difference between contract and FIDIC
CONTRACT VS FIDIC
Risk name
| Effect
| Penalty
|
| Delay in delivery for the whole project
| 100000 EGP/Day
|
| affect the workers and visitor’s life’s | 10000 EGP |
| affect the workers life's | 30000 EGP |
SOME RISKS AND PENALTIES
RISK MANAGEMENT
Risk has three components:
RISK MANAGEMENT
Project risk management PROCESS
PLAN RISK MANAGEMENT
Inputs:
Tools & Technics:
Outputs:
RISK BREAKDOWN STRUCTURE (RBS)
LIKELIHOOD EXPECTATION MATRIX
CONSEQUENCES SCALE MATRIX
RISK MATRIX
Risk IDENTIFICATION
Inputs:
Tools & Technics:
Outputs:
INFORMATION-GATHERING TECHNIQUES
RISK REGISTER
Risk Management Register For Egypt Mosque | ||||||
Risk Identification | ||||||
Categories | Risk ID | Risk Name | Risk Type | Trigger | Risk Owner | Primary Objective |
Design | D2 | Delay in design drawings | Threat | multiple changes by the owner | Design team | Time |
D8 | Release of new construction material | Opportunity | regular upgrades in construction material | - | Cost | |
Organizational | O2 | Losing critical staff member at crucial point of the project | Threat | - | Management Organization | Time |
O10 | Functional units not available, overloaded | Threat | - | Project manager | Time | |
Technical | T2 | inadequate or insufficient site information | Threat | lack of designs | Construction team | Time |
T5 | A technology currently being developed that will save time if released | Opportunity | regular upgrades in construction technology | - | Time | |
Risk Management Register For Egypt Mosque | ||||||
Risk Identification | ||||||
Categories | Risk ID | Risk Name | Risk Type | Trigger | Risk Owner | Primary Objective |
Economical | E1 | Inflation | Threat | - | - | Scope |
E4 | Change in equipment rent price | Threat | - | Project Manager & Procurement | Cost | |
E6 | annual market challenge | Opportunity | - | - | Cost | |
Management | M1 | Tight schedule | Threat | contract document | Planning team | Cost |
M8 | Delay in supply marble | Threat | - | procurment team | Time | |
M10 | Communications problem between construction team and design team | Threat | absence of coordinator | project coordinator | Time | |
Construction | C1 | Failure if happen to use of the bailey bridge formwork for the first time in building construction | Threat | - | Construction team & PM | Cost |
C5 | Failure during placing the main dome | Threat | failure in the lifting machine | Construction team & PM | Quality | |
C8 | Failure of the lifting machines | Threat | something wrong with the machine | Construction team & PM | Cost | |
Risk Management Register For Egypt Mosque | ||||||
Risk Identification | ||||||
Categories | Risk ID | Risk Name | Risk Type | Trigger | Risk Owner | Primary Objective |
Safety | S2 | Lack of safety signs | Threat | there are no signs in the site | Safety team | Quality |
S3 | Reuse existing safety Plan | Opportunity | - | Safety team & PM | Time | |
S10 | The death of one of the workers at any acceding | Threat | lack of safety plan | HSE (insurance) | Cost | |
Labor | L5 | Labor disputes | Threat | - | - | Quality |
Environmental | N4 | Earthquake | Threat | - | - | Cost |
Political | P4 | reduce in steel costs | Opportunity | - | procurment team | Cost |
P6 | Coercive force | Threat | increase the number of the infected civilians | - | Time | |
Quality | Q1 | Testing fails | Threat | test usually fail | Quality team & PM | Quality |
Q2 | Formwork failure during pouring | Threat | cracks in the formwork | Quality control | Cost | |
QUALITATIVE RISK ANALYSIS
Inputs:
Tools & Technics:
Outputs:
RISK SCORING MATRIX
Risk Management Register For Egypt Mosque | ||||||||
Qualitative Risk Analysis | ||||||||
Categories | Risk ID | Risk Name | Probability | Impact | Risk Score | Risk Probability Rate | ||
Level | Rate | Level | Rate | |||||
Design | D2 | Delay in design drawings | 2 | Low | 3 | Moderate | 6 | Moderate |
D8 | Release of new construction material | 3 | Moderate | 3 | Moderate | 9 | Major | |
Organizational | O2 | Losing critical staff member at crucial point of the project | 3 | Moderate | 3 | Moderate | 9 | Major |
O10 | Functional units not available, overloaded | 2 | Low | 2 | Low | 4 | Minor | |
Technical | T2 | inadequate or insufficient site information | 3 | Moderate | 3 | Moderate | 9 | Major |
T5 | A technology currently being developed that will save time if released | 2 | Low | 4 | High | 8 | Moderate | |
Economical | E1 | Inflation | 2 | Low | 3 | Moderate | 6 | Moderate |
E4 | Change in equipment rent price | 2 | Low | 3 | Moderate | 6 | Moderate | |
E6 | annual market challenge | 2 | Low | 4 | High | 8 | Moderate | |
QUALITATIVE ANALYSIS
Risk Management Register For Egypt Mosque | ||||||||
Qualitative Risk Analysis | ||||||||
Categories | Risk ID | Risk Name | Probability | Impact | Risk Score | Risk Probability Rate | ||
Level | Rate | Level | Rate | |||||
Management | M1 | Tight schedule | 4 | High | 5 | Extreme | 20 | Catastrophic |
M8 | Delay in supply marble | 4 | High | 4 | High | 16 | Major | |
M10 | Communications problem between construction team and design team | 2 | Low | 3 | Moderate | 6 | Moderate | |
Construction | C1 | Failure if happen to use of the bailey bridge formwork for the first time in building construction | 4 | High | 5 | Extreme | 20 | Catastrophic |
C5 | Failure during placing the main dome | 5 | Extreme | 4 | High | 20 | Catastrophic | |
C8 | Failure of the lifting machines | 3 | Moderate | 3 | Moderate | 9 | Major | |
Safety | S2 | Lack of safety signs | 3 | Moderate | 4 | High | 12 | Major |
S3 | Reuse existing safety Plan | 3 | Moderate | 3 | Moderate | 9 | Major | |
S10 | The death of one of the workers at any acceding | 1 | Very low | 5 | Extreme | 5 | Moderate | |
QUALITATIVE ANALYSIS
Risk Management Register For Egypt Mosque | ||||||||
Qualitative Risk Analysis | ||||||||
Categories | Risk ID | Risk Name | Probability | Impact | Risk Score | Risk Probability Rate | ||
Level | Rate | Level | Rate | |||||
Labor | L5 | Labor disputes | 1 | Very low | 3 | Moderate | 3 | Minor |
Environmental | N4 | Earthquake | 1 | Very low | 5 | Extreme | 5 | Moderate |
Political | P4 | reduce in steel costs | 1 | Very low | 5 | Extreme | 5 | Moderate |
P6 | Coercive force | 3 | Moderate | 3 | Moderate | 9 | Major | |
Quality | Q1 | Testing fails | 2 | Low | 4 | High | 8 | Moderate |
Q2 | Formwork failure during pouring | 2 | Low | 4 | High | 8 | Moderate | |
QUALITATIVE ANALYSIS
QUANTITATIVE RISK ANALYSIS
Inputs:
Tools & Technics:
Outputs:
QUANTITATIVE RISK ANALYSIS TOOLS AND TECHNIQUES
We tried to mitigate the risk of (Failure during placing the main dome) as possible by using the 3rd method of placing the main dome, the analysis steps are detailed in the Alternatives Study chapter.
QUALITATIVE EXAMPLE USING EXPECTED MONETARY VALUE (EMV)
EMV = (Probability %) x (Impact)
Example 2:
The costs of the building material undefined increase in material cost from November 2020 it was equal to 10,600 LE/Ton and in 2021 year as the steel costs increased by 20% from the beginning of the year till now the steel price were 12,250 LE/Ton but now it costs 14,500 LE/Ton (Ezz steel company) price, And the steel cost increased in 23 May 2021 by nearly 1000 LE/Ton. Then in 26 May 2021decreased by 150 LE/Ton.
Risk Event Alternative | Probability (%) | Impact (cost) | Expected Monetary Value (EMV) |
Reduce in steel costs | 10% | 200 L.E/Ton | 20 |
Increase in steel costs | 20% | 150 L.E/Ton | 30 |
Expected Monetary Value | 50 |
| |
The main causes of increasing the steel prices:
permits after the temporary suspension.
QUALITATIVE EXAMPLE USING EXPECTED MONETARY VALUE (EMV)
RISK RESPONSE PLAN
Inputs:
Tools & Technics:
Outputs:
RISK RESPONSE STRATEGIES
Risk Management Register For Egypt Mosque | ||||
Risk Response | ||||
Categories | Risk ID | Risk Name | Response Strategy | Response Actions |
Design | D2 | Delay in design drawings | Mitigation | making weekly meetings |
D8 | Release of new construction material | aceept | - | |
Organizational | O2 | Losing critical staff member at crucial point of the project | accept | - |
O10 | Functional units not available, overloaded | avoid | spare Functional units | |
Technical | T2 | inadequate or insufficient site information | Mitigation | detailed site investigation |
T5 | A technology currently being developed that will save time if released | accept | - | |
Economical | E1 | Inflation | accept | - |
E4 | Change in equipment rent price | accept | - | |
E6 | annual market challenge | accept | - | |
Management | M1 | Tight schedule | Mitigation | obtain a professional management team |
M8 | Delay in supply marble | Mitigation | alternative procurement route by utilizing an alternative contract strategy | |
M10 | Communications problem between construction team and design team | Mitigation | obtain a professional management team | |
RISK RESPONSE
Risk Management Register For Egypt Mosque | ||||
Risk Response | ||||
Categories | Risk ID | Risk Name | Response Strategy | Response Actions |
Construction | C1 | Failure if happen to use of the bailey bridge formwork for the first time in building construction | avoid | accurate calculations Then use the bailey bridge till the height of 18 meters above ground then establish plat form then execute with cup- lock formwork |
C5 | Failure during placing the main dome | avoid | detailed studies to avoid any failure could happen in placing the dome | |
C8 | Failure of the lifting machines | Mitigation | checking the equipment used | |
Safety | S2 | Lack of safety signs | Mitigation | follow the safety plan |
S3 | Reuse existing safety Plan | exploit | - | |
S10 | The death of one of the workers at any acceding | Transfer | insurance. | |
Labor | L5 | Labor disputes | transfere | HR |
Environmental | N4 | Earthquake | Accept | - |
Political | P4 | reduce in steel costs | Accept | - |
P6 | Coercive force | Accept | - | |
Quality | Q1 | Testing fails | mitigate | choosing different suppliers |
Q2 | Formwork failure during pouring | mitigate | Strengthening the formwork ( Having the proper ties) | |
RISK RESPONSE
QUALITY MANAGEMENT
QUALITY MANAGEMENT
Plan Quality
Perform Quality Assurance
Perform Quality Control
QUALITY MANAGEMENT
CONTROLLING QUALITY
The purpose of the Water leakage test is to ensure that no water leaks inside after installing the dome when it is exposed to rain.
CONTROLLING QUALITY
The test is an attempt to lift the dome.
CONTROLLING QUALITY
Metal cube mold
the specimen
Compression testing machine
�
INSPECTION REQUESTS
SAFETY MANAGEMENT
SAFETY IS IMPORTANT
Humanitarian
Financial
CONSTRUCTION IS HIGH HAZARD INDUSTRY
LIST OF HAZARD
| � |
| � |
| � |
| � |
LIST OF HAZARD
| � |
| � |
| � |
| |
CLASSIFICATION OF INCIDENTS
RESPONSIBILITY
RESBONSIBILTY
Employers MUST
RESBONSIBILTY
WORKERS ALSO HAVE THE RIGHT TO:
PERSONAL PROTECTIVE EQUIPMENT(PPE)
WORKING AT HEIGHTS (FALL PREVENTION)
There is real danger and unsafe act
SCAFFOLDING
EXCAVATION
Shoring
Stepping or Benching
Sloping
Pilling Sheets
Types of Excavation edge Protection System:
Stepping is used in site
TRAFFIC MANAGMENT
Avoid Death & Injury, SEPARATE People & Vehicles
Provide:
These simple steps save lives.
SAFETY INDICATION SIGNS
RISK ASSESSMENT
Hazard | Who is at risk | Severity | Likelihood | Risk Impact | Recommended Action | Person Responsible |
Buried objects | Excavation workers | Fatality | Likely | High | Doing soil borings and examining them using a mine detection device | Project manager |
Covied-19 | All the company employees | Fatality | very likely | High | provide Coronavirus Vaccine to all employees | External |
Fall | All site workers | Fatality | Unlikely | High | Edges and Slopes must be Inspected in the morning and in the evening. Special materials will be put away from edges | Project manager |
Not wearing personal protection system (PPE) | All site employees | Minor Injuries | Likely | Medium | Hire competent person and Provide training for workers | Project manager |
Extreme weather | All site employees | Negligible Injuries | Unlikely | Low | Provide first aid and places for emergency situations | External |
| | SCALE OF LIKELIHOOD | |||
|
| Very Likely | Likely | Unlikely | Highly Unlikely |
SCALE OF SEVERITY | Fatality | High | High | High | Medium |
Major Injuries | High | High | Medium | Medium | |
Minor Injuries | High | Medium | Medium | Low | |
Negligible Injuries | Medium | Medium | Low | Low | |
BIM
INTRODUCTION
BIM TECHNOLOGY IN OUR PROJECT
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
3D Modeling
2D Plan
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
3D Modeling
2D Plan
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
3D Modeling
2D Plan
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
3D Modeling
2D Plan
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
BIM TECHNOLOGY IN OUR PROJECT
3D Modeling
BIM TECHNOLOGY IN OUR PROJECT
Clash Detection
BIM TECHNOLOGY IN OUR PROJECT
Quantity Surveying
BIM TECHNOLOGY IN OUR PROJECT
Quantity Surveying
BIM TECHNOLOGY IN OUR PROJECT
Simulation
BIM TECHNOLOGY IN OUR PROJECT
Simulation
THANK YOU