1 of 16

Data Centers and Local Impacts in Virginia

Tim Cywinski

Communications Director · Sierra Club Virginia Chapter

2 of 16

THE SHORT VERSION

Virginia: The Data Center Capital of the World.

550+

projects existing, under construction, or in the pipeline

1,600

data center buildings those projects could add up to

432M

square feet of development

250+

substations built or planned for data centers

1

Nearly half of Virginia’s jurisdictions

either have data centers or are approving them, and local land use applications keep coming.

2

There is no universal “type” of data center

Size, cooling, power draw, and water use vary wildly. The words tell you almost nothing about what is coming.

3

There are no universal safeguards

No statewide proximity, noise, water, or efficiency standards. Localities are on their own.

4

Key details are hidden by NDAs

25 of Virginia’s 31 data center localities have signed one. Officials often vote without the facts.

Sources: Sierra Club Virginia Chapter project tracking; Virginia DEQ permit data; Virginia Mercury / University of Mary Washington NDA survey

3 of 16

What happens without

safeguards

Our Bills · Our Neighborhoods · Our Water · Our Air

4 of 16

YOUR ELECTRIC BILL

They create the demand. The demand justifies the buildout. You pay for it.

1 · THE DEMAND

70 GW

of data center applications Dominion is now holding. Virginia data centers draw about 6 GW today.

Equal to

  • 41 new nuclear plants
  • 80 new coal plants

2 · THE BUILDOUT

That demand justifies building things we would not otherwise build.

250+

substations built or planned

$7.59B

in Dominion transmission through 2031, two-thirds data center driven

2029

a new Chesterfield gas plant comes online, built for data center demand

3 · YOUR BILL

+$43

A month on a typical bill since 2022:. That's about $520 more a year.

  • +$11.24 base rates, Jan. 2026
  • +$7.97 fuel, July 2026
  • About $4.60 more already approved for 2027

You pay for every plant, plus Dominion's profit

Every new power plant goes on your bill at 100% of its cost. Dominion then earns a 9.8% return on each plant, every year it runs.

Chesterfield gas plant: $1.47 billion to build. $4.5 billion charged to customers through 2064.

Sources: Dominion Energy SCC filings, IRP 2025 and 2022 bill breakdown; Virginia SCC 2025 biennial review order; WTVR (Sept. 2026); Cardinal News (May 2026); The Center Square; JLARC 598.

5 of 16

YOUR NEIGHBORHOOD

How close is too close?

Amazon data center adjacent to a residential neighborhood, Loudoun County

55%

of Fairfax County data centers sit within 200 feet of homes

70%

sit within 500 feet

100–200 ft

is a typical buffer, even next to neighborhoods

“It’s affected me financially, emotionally, and in every other way I can think of. If I would have known what I was walking into a few years back, I would not have chosen this place.”

Carlos Yanes, resident — Washington Post

Northern Virginia is the preview of what the industry is planning for central Virginia and southwestern region. The I-95 corridor is the industry’s fastest-growing expansion zone, but proposals are popping up along 64 and 81.

Sources: Piedmont Environmental Council; Cywinski et al., Fairfax County Data Center Proximity Report; Sierra Club Virginia Chapter

6 of 16

OOUR WATER

How much water this actually takes

Henrico County

1M

gallons a day already in use. 37 data centers today, 17 more buildings planned. Now in extreme drought.

Loudoun County

2B+

gallons used since 2023. A 250% jump in drinkable water. Six of the county’s seven largest water users are data centers.

Caroline County

2.63M

gallons a day would be allocated to three planned campuses drawing on the Rappahannock.

A single hyperscale campus can use up 1 to 12 million gallons a day. That is a town of 10,000 to 70,000 people.

Sources: Virginia DEQ; Henrico County Planning; Loudoun Water FOIA; Friends of the Rappahannock; VPM News; Virginia Mercury, 2026

7 of 16

OUR WATER

“Recycled Water” Claims deserve a follow-up question

25%

A Caroline County presentation found a data center could recycle only about a quarter of the water it uses. The rest evaporates. Evaporation is gone. It cannot be recycled by anyone, ever.

Withdrawn

Total water pulled from the source.

Consumed

The share that never comes back, mostly evaporated.

Recycled

Water re-circulated on site, or sourced from reclaimed supply.

Three different numbers. Developers quote whichever one sounds best.

Ask this instead

  • Is that percentage of water withdrawn, or of water consumed?
  • What is your cycles-of-concentration figure and blowdown volume?
  • Where does blowdown go, and is it tested for PFAS?
  • Is the recycling commitment enforceable, or just a statement?

Sources: Virginia Mercury reporting on a Caroline County Public Utilities presentation, January 2024; JLARC Report 598; ICPRB, March 2026

8 of 16

WHEN IT GOES WRONG

Water Gone Wrong Case Studies

NEWTON COUNTY, GEORGIA

Meta broke ground in 2018. Neighbors 1,000 feet away watched their well go from full pressure to nothing. Sediment ruined their appliances three times over. They have spent $5,000 and cannot afford the $25,000 to replace the well.

Meta commissioned its own study and said it found no connection. No independent study was ever required.

LOUISA COUNTY, VIRGINIA

Recent Reports

“My well made it through four major droughts since the ’50s and never had an issue. Never had an issue with it ever until they started doing things over there.”

​

– Austin Newsom, Luisa resident describing disruptions after Amazon started construction on data center

Sources: New York Times, July 2025; Virginia Mercury, July 2026; U.S. District Court, Western District of Virginia

9 of 16

OUR AIR

Every campus runs on diesel. Rules on usage keep changing.

Diesel backup generators venting over a residential area. Ashburn, June 2025.

14,000

permitted diesel generators statewide, tied to over 470 data centers. About 9,000 are Tier II, the dirtier class without full pollution controls.

1

They built the problem

Generators run at just 7% of permitted capacity today. Under existing permits, 93% more pollution is already legal.

2

They changed the rules

September 2025: DEQ expanded the definition of “emergency” so dirtier Tier II units can run during planned outages on 14 days notice.

3

Nobody is measuring it

Residents get no notification when generators run. No study has assessed current or projected emissions, and the state monitoring network cannot characterize local or cumulative exposure.

Sources: Virginia DEQ permit data; DEQ Guidance Memo APG-578, September 2025; Sierra Club Virginia Chapter; Piedmont Environmental Council; SELC

10 of 16

OUR AIR

Data centers now out-pollute a gas-fired power plant

In 2024, Northern Virginia data centers exceeded Possum Point Power Station on most pollutants, running generators less than one hour per week on average.

5×

Possum Point-sized power plants

Public health impact of running generators under one hour a week

3

premature deaths per year

Attributable to data center generator emissions (VCU / UW)

14K

asthma episodes per year

Triggered by generator pollution (UC Riverside / Caltech)

Lower-income communities and renters face the highest exposure.

Sources: Washington Post / VCU Prof. Damian Pitt; Virginia DEQ data, May 2026

11 of 16

WHAT YOU ARE NOT TOLD

What NDAs hide

25 of 31

Virginia localities with data centers have signed a non-disclosure agreement with a developer.

CASE STUDY — BOTETOURT COUNTY, PROJECT RASPBERRY (GOOGLE)

The regional water authority signed an NDA covering Google’s water usage figures. The county’s electric utility was under a separate NDA. The public had no way to assess the project’s full resource demands before approval. A local newsroom had to go to court to get the numbers.

Chesterfield County

An NDA with the Economic Development Authority covered Google’s three sites for seven years. Water figures were still unavailable.

Hanover County

NDAs were part of the deal that brought a 1,200-acre data center to Beaverdam.

What it costs you

Officials vote without knowing or disclosing water draw, power draw, or who the tenant actually is.

Sources: Roanoke Rambler; WVTF; VPM News; WRIC; Virginia Mercury / University of Mary Washington; Chesterfield County records, 2024–2026

12 of 16

THE TALKING POINTS

What they say. What’s true.

“We pay for our own energy.”

They pay their power bill. They do not pay for the grid being rebuilt around them. JLARC found generation and transmission that would not otherwise be built gets spread across all customers. The data center tax exemption reached $1.9 billion in 2025 alone.

“Using your phone or email supports data centers.”

Virginia has nearly 150 hyperscale facilities. Most are facilities built for one company’s AI training. Your email does not require an 8 million square foot campus.

“Our cooling is a closed loop system.”

The loop gets flushed. Concentrated chemical water called blowdown goes into sewers and waterways. There is no universal requirement to test it for PFAS before discharge.

Sources: JLARC Report 598, December 2024; Virginia SCC; Virginia Economic Development Partnership; Virginia Mercury; U.S. EPA

13 of 16

GOOCHLAND'S WEST CREEK, ON THE HENRICO LINE

The Threat Next Door

Four data center campuses are proposed in Goochland's West Creek, right on the Henrico line.

2,900 MW

proposed across the four campuses

6,700+

homes within 1 mile of a site

25,700+

homes within 3 miles. 84% of them are in Henrico.

10

public schools within 3 miles, everyone of them in Henrico

The closest neighbors live in a county that gets no vote.

Sources: Western Henrico Neighbors (sites, MW); U.S. Census 2020 (homes built since are not counted); NCES 2024-25 (schools). Boundaries approximate.

14 of 16

THE THREAT NEXT DOOR

Why This One Is Different

1

Hanover already said no to this developer

On May 27, 2026, Hanover voted 4‑3 to deny Tract's 900 MW Mountain Road campus, citing water. Tract is now proposing another 900 MW campus here.

2

Most of it needs no public hearing

Three of the four campuses, about 2,000 MW, are by‑right under Goochland's overlay district. Only Tract's site requires a permit and hearings.

3

A power plant could follow

The same district allows a gas peaker plant or a small modular nuclear reactor by conditional use permit. Nothing is proposed yet.

4

Who pays for the grid?

A new Dominion line, about $98 million, serves West Creek. The SCC has ordered Dominion to draft rules making large users pay for what is built for them.

The ask: Henrico should use its leverage on water, sewer and roads, and put a data center pause with cross-border protections in its legislative package.

Sources: Richmond BizSense (May 28, 2026); Virginia Mercury (July 27, 2026); Virginia Business (Feb. 10 and July 31, 2026); WRIC; Western Henrico Neighbors.

15 of 16

BEHIND THE METER

Behind the Meter: The Next Escape Hatch

When the grid can't connect them fast enough, data centers can build their own power plant and skip the line.

On the grid

How it works today

Dominion grid

Meter

Data center

  • Answers to the State Corporation Commission
  • Covered by the Virginia Clean Economy Act
  • Ratepayer protections and public review
  • Waits in Dominion's connection line

Behind the meter

The escape hatch

Gas turbines on site

Data center

No grid. No meter. No line to wait in.

  • The data center becomes its own private utility
  • May fall outside the Clean Economy Act
  • Turbines can be permitted through a DEQ air permit
  • Runs around the clock, next to whatever is nearby

Why now: Dominion says a new grid connection can take up to seven years. A gas plant on site can take far less.

Sources: Virginia Mercury (July 20 and July 27, 2026); Piedmont Environmental Council.

16 of 16

BEHIND THE METER

It's Already Here, and the Door Is Open

1

Loudoun: already running

Vantage VA2 in Sterling is the first Virginia data center to run on its own gas power around the clock: 8 gas turbines, plus 51 diesel backup generators. A PEC-commissioned study estimates 17 to 33 premature deaths over five years. DEQ disputes the study.

2

Goochland: written into the zoning

The Technology Overlay District on Henrico's border allows a gas peaker plant or a small modular nuclear reactor by conditional use permit. Nothing is proposed yet.

3

Texas: the loophole

Gov. Abbott's August 3 pause covers data centers in the grid connection queue. Legal analysts say projects that generate their own power may fall outside it.

4

The merger: the strategy

NextEra, which is buying Dominion, told investors "the market is heading towards bring your own generation" and has over 20 GW of gas in development. SCC hearings begin Nov. 5.

The fix: Any pause has to name behind-the-meter generation. Treat on-site gas as a power plant, with the same air standards, siting review and community consent.

Sources: Piedmont Environmental Council; Virginia Business (Feb. 10, 2026); Foley & Lardner (Aug. 2026); Power Engineering (Dec. 2025); WTVR (Sept. 2026).