Middlefork School Capital Improvement

2 of 18

Middlefork School�Overview of Facility Needs

Repair/Replace Infrastructure

      • Replace “End-of-Life” Structures & Systems (Roof, Boiler & Chillers Units, Playground Equipment)
      • Replace/repair aging features (Windows, Doors, Canopy, Exterior Fascia/Soffits, Flooring, Ceiling Tile, Lighting, Paint)
      • Add accessible restrooms (Staff/Aultt & Student)
      • Increase storage space
      • Air-condition the gymnasium?

Add Instructional Spaces

      • Need Minimum of 20 “CLASSROOM SPACES” (Currently Have 17 Classroom Spaces)
        • -General Education Classrooms (Need Total of 14 core classrooms)
        • -Specials Classrooms (Art, Music, Spanish, Computer Science)
        • -Special Education Classrooms (K/1 & 2/3)
      • Add dedicated instructional spaces for special education “resource”, and intervention/support services

Enhance Safety & Security Features

Improve access controls and movement barriers

      • Enhance proactive & reactive safety/security systems and features inside and outside the building

Improve Accessibility

Indoors (Doorways & Bathrooms)

Outdoors (Playground)

3 of 18

Middlefork School Facility Needs

Systems & Infrastructure Repair/Replacement

WHAT WE HAVE

Aging Infrastructure

Operating Systems Requiring Continuous Repair

Boilers/Chillers at End of Life

Canopy in Need of Replacement

Roof at End of Life

WHAT WE NEED

New HVAC System, Roof, & Playground

Repair/Replace Aging Interior:

-Lighting, Flooring, Ceiling Tile

Repair/Replace Aging Exterior:

-Doors, Windows, Facia, Soffit, Canopy

4 of 18

Middlefork School Facility Needs

Instructional Space Needs

18% Increase in Enrollment Since 2010

Middlefork School Enrollment

5 of 18

Middlefork School Facility Needs

Instructional Space Needs

  • Added Computer Science Class at K-3rd Grades

  • Added Spanish Instruction at 1st-3rd Grades

  • Increased Music Instruction from 3.5 to 5 Days per Week

  • Expanded “Advanced Learning” Services for Accelerated Students

  • Added Full-time “Reading Intervention” Services for Struggling Readers

  • Reduced “Out-of-District Placements” for Students with Disabilities by 75%
    • -Average of 4-6 students with significant educational & space needs

Middlefork Programming Changes Since 2010

6 of 18

Middlefork School Facility Needs

Instructional Space Needs

WHAT WE HAVE

17 Classrooms Spaces

5 Intervention/Small Group Instructional Spaces

Music in the

Cafeteria

Spanish on a Cart

Small Group & Intervention Services in the Vestibule

Early Intervention Services

in the Lobby

WHAT WE NEED

At least 20 Classroom Spaces

8 Intervention/Small Group Instructional Spaces

7 of 18

Middlefork School Facility Needs

Safety & Security

WHAT WE HAVE

Main Entrance Security Features

Video Surveillance System

Digital & Analog Communication

WHAT WE NEED

Increased Security Features at all Points of Ingress

Interior Movement Barriers

Reinforced Interior Systems (Doors, Glass)

Secure Playground with Exterior Barrier from

Willow Park & Dog Area

Increased Interior Security Between School and

Park District

Enhanced Digital Communication Systems

Fire Suppression System (Interior Sprinkler System)

Storm Shelter

*Comparable to the New Sunset Ridge School

8 of 18

Middlefork School Facility Needs

Accessibility

WHAT WE HAVE

Inaccessible Playground

Three Adult Restrooms

One Handicapped Accessible Restroom

WHAT WE NEED

Updated & Accessible Playground

Handicapped Accessible Student and Adult Restrooms Ramps to Traverse Steps

Outdated, Unsecured, and Inaccessible Playground

Limited & Inaccessible Restrooms

9 of 18

Option A: Addition & Renovation

ESTIMATED COST

$21M

*New Playground not included

10 of 18

Option B: Construction of New School

ESTIMATED COST

$35M

*New Gymnasium not included

11 of 18

What Each Option Provides

Identified Needs Option A: Addition & Renovation Option B: New School

Replace End of Life Systems Replace HVAC & Roof Replace HVAC, Roof, & Playground

Add Classroom Space 18 Renovated/2 Additional Classrooms 22 New Classroom Spaces

Add Small Group Space 8 Renovated Spaces 10 New Small Group Spaces

Enhance Safety & Security AddsSome Safety/Security Features Maximize Safety & Security Throughout

Replace Exterior Finishes Repair Soffits & Remove Canopy New Canopy, Ext. Doors, Windows, Facia

Replace Interior Finishes Update Lighting, Ceiling Tile, Paint All New Interior Finishes

Add Accessible Restrooms Add One (1) Accessible Restroom Ensure all Restrooms are Accessible

Air Condition Gymnasium Not Addressed Ensure Air Conditioning in All Areas

Enhance Energy Efficiency HVAC System Only Maximize Energy Efficient of All Systems

Updated Technology Update Infrastructure Update Infrastructure

Add Storage Space Not Addressed Ensures Adequate Storage

New Furnishings New Classroom Furniture New Classroom Furniture

Storage Space Not Addressed Ensures Adequate Storage

Estimated Cost $21M (Based on Scope) $35M (Based on Scope)

12 of 18

POTENTIAL FINANCIAL SOURCES

DEBT SERVICE

Tax Levy Available without a Referendum

FUND BALANCE

Withdrawal from District Savings Account

REFINANCE EXISTING DEBT

Refinance current “Mortgage” on Sunset Ridge School

REFERENDUM

Increase in Tax Levy Approved by Majority of Voters

13 of 18

What Resources are Available?

The Debt Service Levy

Option:

Maximize Debt Service Levy to capture

up to $4.7M.

Benefit:

-Able to capture funds without a referendum.

Challenge:

-Once maximized, there is no future capacity for funding of construction/repair needs.

Education

Fund

Operations

Fund

Debt Service

TOTAL

TAX

LEVY

THE TAX LEVY BUCKETS

14 of 18

What Resources are Available?

The Fund Balance

Option:

Fund Balance withdrawal to capture

up to $10M.

Benefit:

-Can capture funds without a referendum.

Challenges:

-Limits available funds for program growth or unexpected expenses.

-Reduces Total D29 Fund Balance to

approx. 30% for one year, then at 50% through 2030.

“FUND BALANCE”

THE DISTRICT SAVINGS ACCOUNT

15 of 18

What Resources are Available?

Refinancing Existing “Mortgage”

Option:

Refinance Existing Capital Lease Certificates (“Mortgage”) to capture up to $9.3M.

Benefit:

-Can capture funds without a referendum.

Challenges:

-Increases term of existing “mortgage” from 2036 to 2046.

-Increases annual mortgage payment from $1.3M to $1.5M.

-Limits Available “Operating” Funds.

-Results in Projected Deficit Spending in 2030

THE DISTRICT 29 “MORTGAGE”

16 of 18

What Resources are Available to Fund

Capital Improvements?

If the District Leverages All of its Possible Resources to the Maximum Extent

DEBT SERVICE LEVY……………………………………………………….$4.7M

FUND BALANCE WITHDRAWAL………………………………………….$10.0M

REFINANCING EXISTING CAPITAL LEASE CERTIFICATES………………….$9.3M*

MAXIMUM FUNDS AVAILABLE…………………………………………..$24.0M

17 of 18

STAKEHOLDER FEEDBACK

OPTION A:

ADDITION & RENOVATION

DEBT SERVICE LEVY…...$4M

FUND BALANCE……...$10M

REFINANCE……………$7M

TOTAL COST = $21M

OPTION B:

PARTIAL NEW SCHOOL

FUND BALANCE……...$10M

REFERENDUM………..$25M

TOTAL COST = $35M

18 of 18

REFERENDUM IMPACT ON ANNUAL TAX BILL

$25M REFERENDUM

HOME VALUE $500,000

EST. IMPACT $450.83

HOME VALUE $750,000

EST. IMPACT $692.26

HOME VALUE $1,000,000

EST. IMPACT $933.69