Delta BDI Commissioning

Document Number: INS-SOP-0170-03

Revision: 3

Copies of this SOP including PDFs and paper copies are uncontrolled and may be out of date.

Standard Operating Procedure

2 of 45

Field Operations Standard Operating Procedure

This SOP describes the procedure for commissioning a Delta BDI inverter.

Topics covered in this SOP:

  • Overview
  • Related Documents
  • Materials/Tools
  • App Activation
  • Connecting to the inverter
  • Establishing communication
  • Software Updates
  • Setting the Grid Code
  • Busbar Protection
  • Verification
  • Backup Testing
  • Leave State

IMPORTANT: Installation must be performed by a licensed electrician in accordance with local, state, and National Electrical Code ANSI/NFPA 70 requirements.

Standard Operating Procedure

Overview

3 of 45

Ford Charge Station Pro Installation and Wiring SOP - INS-SOP-0158

Ford Charge Station Pro WiFi Pairing and Intelligent Backup Commissioning - INS-SOP-0165

Ford Charge Station Pro Installation and Wiring SOP - INS-SOP-0158

Ford Home Integration System (Delta MID, Delta BDI Inverter, Delta Accessory Battery Pack) - INS-SOP-0226

Delta BDI Commissioning - INS-SOP-0170

Ford Charge Station Pro Installation and Wiring SOP - INS-SOP-0158

Delta BDI Commissioning - INS-SOP-0170

Ford Charge Station Pro Installation and Wiring SOP - INS-SOP-0158

Delta BDI Commissioning - INS-SOP-0170

LG (Gen 3) Battery Installation - INS-SOP-0133

EV Charger Only

EV Charger + HIS Equipment

EV Charger + HIS + PV

EV Charger + HIS + PV + Battery

Ford Charge Station Pro WiFi Pairing and Intelligent Backup Commissioning - INS-SOP-0165

Ford Charge Station Pro WiFi Pairing and Intelligent Backup Commissioning - INS-SOP-0165

Ford Charge Station Pro WiFi Pairing and Intelligent Backup Commissioning - INS-SOP-0165

Ford Home Integration System (Delta MID, Delta BDI Inverter, Delta Accessory Battery Pack) - INS-SOP-0226

Ford Home Integration System (Delta MID, Delta BDI Inverter, Delta Accessory Battery Pack) - INS-SOP-0226

Overview, cont’d

Standard Operating Procedure

4 of 45

Related Safety Documents

Related Documents

Standard Operating Procedure

Requirements of the following related documents are also requirements of this SOP.

5 of 45

Ensure all Arc Flash PPE is worn during the shown portion of the Installation SOP.

Photo or screenshot required for the Foreperson Installation Checklist (FIC).

Pro Tip to help the installation procedure.

Indicates to Tap on a screen or device within an application or website.

This symbol indicates a safety-specific call out

Standard Operating Procedure

Legend

Eye irritant, skin irritant, or both

Flammable

See the Safety Data Sheet in the Related Documents list for additional information relating to OSHA Hazard Pictograms.

Health Hazard

Acutely Toxic

Pressurized Gas Hazard

Corrosive Hazard

Environmental Hazard

Oxidizing Hazard

Explosive Hazard

Safety Hazards

General

6 of 45

Estimated Time:

15 to 30 minutes per inverter

Materials:

  • Phone
  • Fluke Multimeter

Tools:

Standard Operating Procedure

Tools & Materials

7 of 45

INSTALL THE M PROFESSIONAL APP

IMPORTANT: Skip to Step 2 if your device already has the M Professional App installed and activated.

  • Download M Professional from Google Play Store or Apple App Store.

    • M Professional requires Android 4.4 or higher, and iPhone 6 (iOS 9.0) or higher

  • Open the M Professional App

Step 1

Standard Operating Procedure

8 of 45

IMPORTANT: The first time the M Professional app is used with a new device it will require activation.

ACTIVATE THE M PROFESSIONAL APP

Tap Settings

Tap Activation “Not Active”

Enter 6532,

Tap OK

Verify Activation is “Active”

Tap Devices

Step 1, cont’d

Standard Operating Procedure

9 of 45

POWER ON ALL ELECTRICAL EQUIPMENT

IMPORTANT: Turn ON AC and DC power sources to all of the electrical equipment (batteries, inverters, AC disconnects, circuit breakers, etc.) prior to beginning commissioning.

When applicable

Turn LG Gen 2 Battery ON.

Turn auxiliary switch ON first then the DC main breaker second.

When applicable

Turn LG Gen 3 Battery ON.

Turn ON the DC main breaker.

DC Main ON Second

Turn the inverter’s red DC Disconnect Switch to the ON position by pushing up and turning it to the left.

Step 2

Standard Operating Procedure

10 of 45

CONNECT TO THE INVERTER THROUGH THE M PROFESSIONAL APP

The inverter may show an update is required, Tap Next to bypass this screen. Updates will be completed in a later step once the Inverter is connected to the customer’s Wifi to speed up the firmware update process.

  • Tap the search icon to scan for available devices

  • (1) Select the Inverter once its available

  • (2) Enter the data code 6532

  • (3) Tap Ok

3

Step 3

Standard Operating Procedure

2

1

11 of 45

MAIN SCREEN

Main screen displays basic information: including (Inverter name, type, serial number, firmware versions current power, energy produced today, energy produced totally, running status, synchronize process, AC voltage, current and frequency, PV voltage and current.

Main screen functions include:

  1. Menu on the upper-right: to other functions, available in active mode (Check Activation)
  2. Energy: to power curve (Check Power Curve).
  3. Running status: the entrance to errors page will show up if the status is Error (Check Current Error).
  4. Sync process: to synchronize details (Check Sync Process).
  5. AC & PV: the entrance to AC and PV information (Check AC & PV).
  6. EVSE: the entrance to EVSE information (Check EVSE information).
  7. Power Flow: to power flow (Check Power Flow)

Step 3, cont’d

Standard Operating Procedure

12 of 45

CONNECT TO CUSTOMER WIFI NETWORK

Tap Menu

Tap Communication Card Setup

Tap Network Name

Select the Customer’s Wifi Network and enter the Password

Customer’s WiFi

Step 4

Standard Operating Procedure

13 of 45

  • Verify Connection = Cloud Connected

  • Verify Gateway Network = Wifi

CONNECT TO CUSTOMER WIFI NETWORK

Step 4, cont’d

Standard Operating Procedure

14 of 45

UPDATE SOFTWARE

Observe the Version “Update available”

Tap Menu

Tap Software Update

(1)Tap File to reveal the drop down menu then,

(2)Tap Inverter File

Tap Play

IMPORTANT: Keep the device within 3’ of the inverter while the software is being downloaded and installed.

Step 5

Standard Operating Procedure

1

2

15 of 45

  • While the firmware is downloading, the percentage of completion will be displayed.

NOTE: The LEDs on the inverter will blink while the firmware is being downloaded and installed.

  • When the status bar indicates 100%, the download is complete.

  • Tap Back to return to the main menu

UPDATE SOFTWARE

Step 5, cont’d

Standard Operating Procedure

16 of 45

Follow the SOP link that applies:

If the installation includes a battery then proceed.

If the installation does not include a battery then skip to Step 6.

Standard Operating Procedure

Step 5, cont’d

UPDATE SOFTWARE: BATTERY

IMPORTANT: This portion of the step only applies to systems that have a battery installed.

17 of 45

UPDATE SOFTWARE: BATTERY

IMPORTANT: This is only required for the LG Gen 3 Battery. Skip this step for LG Gen 2 Installation.

Observe the Version “Latest”

Tap Menu

Tap Software Update

Tap File to reveal the drop down menu then,

Tap Battery File

Tap Play, when the update is completed (status bar at 100%)

Tap Back

Step 5, cont’d

Standard Operating Procedure

2

1

2

1

18 of 45

UPDATE SOFTWARE: VERIFY SOFTWARE

Tap Devices

  • Allow the App to scan for available devices

  • (1) Select the Inverter once its available

  • (2) Enter the data code 6532

  • (3) Tap Ok

2

Tap Refresh

Step 5, cont’d

Standard Operating Procedure

3

1

1

2

19 of 45

UPDATE SOFTWARE: VERIFY SOFTWARE

  • Verify all applicable equipment = Good/Pass

    • If a LG Gen 3 Battery is installed.

      • Battery D2D 1 shall be ≧ 1.2.

      • Battery BMS 1 shall be ≧ 2.3.0.4

      • These versions will match Battery 2 if installed.

    • LG Gen 2 Battery will show the following:

      • Battery D2D 2 and Battery BMS 2 will say Incapable for single-battery systems.

  • Tap Next after all information is verified.

Single-battery system

Dual-battery system

Step 5, cont’d

Standard Operating Procedure

20 of 45

SMART GRID CONFIGURATION

Tap Menu

Tap Smart Grid

IMPORTANT: Smart grid settings need to be set according to the utility requirements for the area the installation takes place. Technicians shall be responsible for knowing/inquiring about what grid code is required for the installation.

  • Complete the following Steps to configure the Grid Code

Step 6

Standard Operating Procedure

21 of 45

SMART GRID CONFIGURATION

  • (1). Verify that the Grid Code is set correctly (almost always 240V).

    • To change, Tap Edit, then enter the correct setting.

Note: If a password is required to change the settings use the following code 6532 or delta.

  • (2). Configure the Utility Code, Tap Utility Code, then choose the appropriate code for region/utility.

    • If the installation region does not have a dedicated utility code, then select IEEE_1547A

Note: Some Utility Code settings will automatically change the Power Priority to “Reactive” rather than “Active.”

Step 6, cont’d

Standard Operating Procedure

1

1

2

2

22 of 45

IMPORTANT: Follow step 7 if configuring PCS as listed on the electrical page of the plan set.

If not setting PCS, skip to step 8

Standard Operating Procedure

Follow the SOP link that applies:

Step 7

SET BUSBAR PROTECTION

23 of 45

  • From the menu tap Additional Feature > PCS Settings > Bus Bar Protection

  • Tap the Protection Enable slider and enter the values:

    • MAXIMUM TOTAL CURRENT ON THE CONTROLLED PANEL = Maximum allowed current at busbar

    • FAIL SAFE GENERATION BACKFEED CURRENT SUPPLY = Fail Safe Current

  • Values are listed on the CD-2.0 page

NOTE: 100 A and 0 A are the default values entered in app.

Standard Operating Procedure

PCS - BUSBAR PROTECTION

Step 7, cont’d

XXX

XX

Example of CD-2.0 page

XX

XX

XX

XA

24 of 45

ACTIVATE CELLULAR DATA PLAN

Tap Menu

Tap Communication Card Setup

Tap Update

Verify firmware is up to date,

Then Tap Back

Step 8

Standard Operating Procedure

2

1

1

25 of 45

ACTIVATE CELLULAR DATA PLAN

  • Navigate back to the Menu Screen

Tap Menu

Tap Data Plan

Tap Activate Plan

Verify the data plan is active, then

Tap Main Screen

Step 8, cont’d

Standard Operating Procedure

26 of 45

  • Return to the Communication Card Setup screen

NOTE: Both the WiFi and Cellular networks should be connected at this point. The Gateway Network should be set to WiFi and the connection status should read Cloud Connected.

  • Tap Connection/Cloud Connected to access the status screen

  • Verify connection status:
    • Wi-Fi Status = OK
    • Cellular Status = OK

VERIFY NETWORK CONNECTIONS

Step 9

Standard Operating Procedure

27 of 45

SYSTEM VERIFICATION

  • Verify the following information from the Main Screen:

    • Running Status = Normal

    • Network Status = Cloud Connected (Wi-Fi) or Cloud Connected (4G)

  • Verify the following information from the Communication Card Screen:

    • Gateway = Plugged In

    • Connection = Cloud Connected

    • Gateway = Wi-Fi

Step 10

Standard Operating Procedure

E10_BDI SN:0005

28 of 45

  • Tap the Running Status bar to view a list of errors

IMPORTANT: If errors are present and CTs need to be reoriented, make sure to power down the meter first. Never remove CTs when the meter is live.

Possible errors in app

Error indication

Standard Operating Procedure

SYSTEM VERIFICATION: CT ERRORS

Step 10, cont’d

E10_BDI SN:000005

One/both CTs facing wrong direction or CTs are on the wrong phases

Meter is not powered or not communicating

CT not connected

Check CT connections

29 of 45

Standard Operating Procedure

SYSTEM VERIFICATION: ACREL METER LED GUIDE

Step 10, cont’d

LED

LED color

Function

Indication

Troubleshooting

Run

Green

Flashing ON/OFF (for 1 second)

Working normally

 

Red

ON for > 3 seconds

Internal error

Contact support

Yellow

Flashing ON/OFF (for 1 second)

No communication

Check if the communication wires are connected correctly.

L1 / L2

Green

ON for > 3 seconds

No current

 

Flashing ON/OFF (for 1 second)

Positive power

 

Red

Flashing ON/OFF (for 1 second)

Negative power

 

Flashing with green LED alternately

High voltage > 130 V

Check if the line voltages meet the meter rating.

Flashing with yellow LED alternately

Low voltage < 70 V

Yellow

Flashing ON/OFF (for 1 second)

Critical low voltage < 30 V

ON for > 3 seconds

Frequency is below 45 Hz or above 70 Hz

Check if any high noise

30 of 45

SITE CONTROLS

IMPORTANT: These settings only apply when a battery is installed on site.

  • Navigate to Menu > Site Control.

  • Set Backup SOC (State of Charge) to 35%.

  • Set Protection Limit SOC to 15%.

  • Select Solar Only Backup

  • When prompted to enter the password for advanced editing mode, use the same 4-digit code as you used previously: 6532.

NOTE: if 6532 does not work, try “delta” - all lower-case letters.

  • Tap Save

Step 11

Standard Operating Procedure

31 of 45

SYSTEM VERIFICATION

Verify the following information from the Main Screen.

  • Version is Latest

  • System is producing power (Watts)

  • Running Status = Normal

  • Network Status: Cloud Connected (4G) (or WiFi)

  • Battery SoH (State of Health) is 100%.
    • Battery status should be charging or discharging. Or, if the Battery is charged to 100%, the status will show as “Idle.” This applies to all batteries installed.

1

2

3

4

5

1

2

3

4

5

Standard Operating Procedure

Step 12

E10_BDI SN:000005

32 of 45

Standard Operating Procedure

Rapid Shutdown Test:

IMPORTANT: Verify that the system will comply with NEC rapid shutdown requirements:

  • With the inverter on and producing power, measure DC voltage on a single string.

  • Turn off the inverter DC disconnect. Confirm that the voltage drops below 30 Volts within 10 seconds. If not, review the Sunrun SOP on APS Rapid Shutdown Installation to ensure that the APS units were installed correctly.

  • Repeat the steps above for each string of modules.

  • Once a successful rapid shutdown test has been performed, turn the DC disconnect back ON and verify that the system is up and running again.

Step 12, cont’d

SYSTEM VERIFICATION

33 of 45

POWER FLOW VERIFICATION: POWER ON

  • Scroll to the bottom of the Main Screen

  • Tap Power Flow

  • Tap Show Detail to show the detailed readings for import and export values.

NOTE: Selecting Show Detail shows the full power values, rather than abbreviated values. When taking required screenshots full values need to be displayed.

Step 13

Standard Operating Procedure

34 of 45

POWER FLOW VERIFICATION: POWER ON

  • Verify that all power import/export values add up correctly:

    • Identify the sources that are exporting power:
      • Solar
      • Battery, if “Discharging”
      • Grid, if showing a positive value

    • Identify the sources that are importing power:
      • Home loads
      • Battery, if “Charging”
      • Grid, if showing a negative value

  • The sum of all sources exporting power should be within 100 W of the sum of all sources that are importing power.

Step 13, cont’d

Standard Operating Procedure

35 of 45

Standard Operating Procedure

Step 14

SUMMARY SCREEN

Take a screenshot of the summary.

Tap Menu > Additional Feature > Summary

NOTE: Upload the summary screenshot to the commissioning category of the FIC.

This will replace many of the individual screenshots previously required.

36 of 45

BACKUP MODE TEST

  • Simulate a grid outage by turning off power to the entire home.
    • Ensure there are readings from the PV system before taking the required Backup Mode Test photo.

NOTE: In some cases, the inverter will temporarily shut off for up to 5 minutes after the system goes into Backup mode. Wait for the PV system to begin producing again.

    • Leave the system in Backup Mode for a minimum of fifteen minutes to make sure there are no issues.

  • Make sure that some backed up loads are running (i.e., drawing power).

  • Still on the Power Flow screen, verify that the grid icon shows “OFF.”

Solar Only

Step 15

Standard Operating Procedure

37 of 45

  • Verify that all power import/export values add up correctly:

    • Identify the sources that are exporting power:
      • Solar
      • Battery, if “Discharging”

    • Identify the sources that are importing power:
      • Home loads
      • Battery, if “Charging”

  • The sum of all sources exporting power should be within 100 W of the sum of all sources that are importing power.

  • Again, if no Acrel meter, you just need to verify that power values are shown for the Solar and the Battery, and that the Battery shows as either Charging or Discharging

BACKUP MODE TEST

Step 15, cont’d

Standard Operating Procedure

38 of 45

Follow the SOP link that applies:

Step 16A: Describes the procedure for leaving the system on and in standby mode for remote activation.

Step 16B: Describes the procedure for leaving the system OFF.

Standard Operating Procedure

Step 16

SYSTEM LEAVE STATE

IMPORTANT: This step indicates the state a system is left in upon completion of the installation. This is typically dictated by the AHJs rules that either allow the system to remain ON and be activated remotely after Permission To Operate (PTO) is received, or the system remains OFF and requires someone to physically turn on the system after PTO.

39 of 45

  • If the AHJ/utility allows for remote activation of PV systems, set the system into Sleep Mode.

  • From the Menu, select Additional Feature > Tap Sleep Mode.

  • Tap “Go Sleep.”

  • Verify the inverter state has Sleep Mode “Enabled.”

LEAVE STATE: REMOTE ACTIVATION

Step 16A

Standard Operating Procedure

40 of 45

If the AHJ/utility does not allow remote activation of PV systems, ensure that all of the following are left in the OFF position:

  • Battery On/Off switch in the OFF position.

  • All AC disconnects.

  • All PV breakers.

  • Inverter DC disconnect.

  • Sunrun will contact the customer to walk them through activating the system, once PTO is granted.

LEAVE STATE: NO REMOTE ACTIVATION

Step 16B

Standard Operating Procedure

41 of 45

Standard Operating Procedure

Feedback

Please use the links below to provide feedback on SOPs and/or Products:

SOP/Work Instruction Feedback

Product Feedback

42 of 45

Approvals

Prepared by: D. Shumway

2022.03.17

Training:

Reviewed by: B. Sistrunk

2022.03.17

Safety:

Electrical:

Structural:

Design:

CRT:

Product:

Other:

Quality: B. Vollbrecht

2022.03.17

Other:

Standard Operating Procedure

43 of 45

Standard Operating Procedure

Revision

Date

Description

Approval

1

2022.05.31

Initial Release

J. Costner

2

2023.08.15

Revised in accordance with CO-0079

J. Costner

Revision History

44 of 45

Document Control SOP Change Order

Field Operations

Change Order number: CO-0079

New SOP Revision: 02

Submitted By & Date: J. Costner 08/15/2023

SOP Title and Number: (Ford) Delta BDI Commissioning SOP - INS-SOP-0170

Reason for Change (in detail):

Power control and busbar protection limiting and CT error indication became available for Delta inverters.

Description of Change (in detail):

  • Updated step 7 to detail setting protection limits for backfeed and where on the plan set those limits are listed.
  • Added verification check for CT errors in step 10

Effectivity: (Installations in field, New installations, Work in Progress, list other documents affected)

All new Delta inverter installs with “PCS” noted on the plan set. This affects PV Only as well as Shift and backup configurations.

Approvals

Training:

Quality:

Safety:

Product: J. Costner

Electrical:

Structural:

Other:

Other:

Other:

Other:

Other:

INS-FRM-0001-01

45 of 45

Document Control SOP Change Order

Field Operations

Change Order number: CO-97

New SOP Revision: 03

Submitted By & Date: J. Costner 1/19/2024

SOP Title and Number: Delta E SHIFT Systems: Commissioning- INS-SOP-0225

Reason for Change (in detail):

Updated screenshots to reflect Output Limit feature, CT error codes, and power flow. SOP changed to new format.

Description of Change (in detail):

Removed redundant and out of date slides to make the commissioning process more intuitive.

Acrel meter LED guide added to verification step 8.

Added new step 13 (summary screen) to reduce the number of overall screenshots to be taken.

Effectivity: (Installations in field, New installations, Work in Progress, list other documents affected)

All new Delta E installations in the PV-Only configuration.

Approvals

Training:

Quality:

Safety:

Product: J. Costner

Electrical:

Structural:

Other:

Other:

Other:

Other:

Other: