1 of 11

Citizens’ Bond Oversight Committee��April 25, 2025

Current Projects

2 of 11

MARGARET SHEEHY ELEMENTARY

FRANKLIN ELEMENTARY

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

3 of 11

MARGARET SHEEHY ELEMENTARY SCHOOL

4 of 11

Margaret Sheehy Elementary School

Transportation Drop Off / Pick Up and Fencing

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

5 of 11

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

What still needs to be done?

  • Project Close Out
  • Notice of Completion

6 of 11

FRANKLIN

ELEMENTARY SCHOOL

7 of 11

Franklin Elementary School

Landscaping – Phase 2

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

8 of 11

Franklin Elementary School

Bidding – Phase 3

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

9 of 11

Franklin Elementary School

Phase 3 Timeline

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

Depending on NTP anticipated completion date is February 23, 2026

  • Bidding - 03/10/2025 – 04/7/25
  • NTP - 04/18/2025
  • Phase A - 04/18/2025 – 10/01/2025 - 20 Weeks
  • Closeout Phase A - 10/01/2025 – 11/12/2025 – 6 Weeks
  • Phase B - 11/12/2025 – 12/24/2025 – 6 Weeks
  • Phase C - 12/24/2025 – 02/18/2026 – 8 Weeks

10 of 11

CITIZENS’ BOND OVERSIGHT COMMITTEEApril 15, 2025

What still needs to be done?

  • Phase #3

11 of 11

Questions?