SRF Pre-Application Workshop
Day 1 Presentation and Q&A
May 26, 2026
Introductions and Objectives
Introductions and Objectives
2
Panel Introductions: Office of State Lands and Investments (OSLI)
Introductions and Objectives
3
Panel Introductions: Office of State Lands and Investments (OSLI)
Introductions and Objectives
4
Panel Introductions: Office of State Lands and Investments (OSLI)
Introductions and Objectives
5
Panel Introductions: Office of State Lands and Investments (OSLI)
Introductions and Objectives
6
Panel Introductions: Department of Environmental Quality (DEQ)
Introductions and Objectives
7
Panel Introductions: Department of Environmental Quality (DEQ)
Introductions and Objectives
8
Panel Introductions: Wyoming Water Development Office (WWDO)
Introductions and Objectives
9
Panel Introductions: Wyoming Water Development Office (WWDO)
Introductions and Objectives
10
Workshop Objectives
Introductions and Objectives
11
The goal of this workshop is that you will…
Know what is expected to be turned in for your application
Understand the SRF program basics
Understand the basics of the application process
Today’s Agenda
Introductions and Objectives
12
Topic 1: SRF Program Overview
Topic 1: SRF Program Overview
13
Clean Water State Revolving Fund (CWSRF) Program Overview
Topic 1: SRF Program Overview
14
CWSRF Overview
Topic 1: SRF Program Overview
15
CWSRF: Eligible Applicants
Topic 1: SRF Program Overview
16
State agencies
Counties
Municipalities
Special districts
Joint powers boards
CWSRF: Eligible Projects
Topic 1: SRF Program Overview
17
Ineligible activities include operations and maintenance (O&M), such as routine monitoring.
Clean Water Emerging Contaminants (EC) Funding
Topic 1: SRF Program Overview
18
Drinking Water State Revolving Fund (DWSRF) Program Overview
Topic 1: SRF Program Overview
19
DWSRF Overview
Topic 1: SRF Program Overview
20
DWSRF: Eligible Applicants
Topic 1: SRF Program Overview
21
Publicly owned water systems
Counties
Municipalities
Special districts
Joint powers boards
DWSRF: Eligible Projects
Topic 1: SRF Program Overview
22
Ineligible activities include O&M, routine testing, water hauling/bottled water, system expansion, growth-driven projects, fire protection-only projects, dams, and reservoirs.
Note: Not all individual costs associated with an eligible project will be eligible for DWSRF reimbursement
Lead Service Line (LSL) Project Funding
Topic 1: SRF Program Overview
23
Drinking Water Emerging Contaminants (EC) Funding
Topic 1: SRF Program Overview
24
General Loan Terms, Interest Rates, and Application Details
Topic 1: SRF Program Overview
25
General Loan Terms, Interest Rates, and Application Details
Applicants must:
Topic 1: SRF Program Overview
26
Show that they can repay the loan, and
Adhere to federal environmental, social, and economic cross-cutting requirements and state procurement requirements.
Loan Applications
Topic 1: SRF Program Overview
27
Loan Terms
Loan terms cannot exceed the useful life of the assets.
Topic 1: SRF Program Overview
28
Typically 20 years, but can be up to 30 years in some cases.
Repayment starts one year after substantial completion or project completion in annual installments.
Interest Rates
Topic 1: SRF Program Overview
29
When Principal Forgiveness is not available, communities that would have qualified for…
Large Loan Incentive Interest Rates
Topic 1: SRF Program Overview
30
CWSRF:
Loan Amount (CWSRF) | Eligible Interest Rate (CWSRF) |
$7.5 million up to $10 million | 0.75% |
$10 million up to $15 million | 0.50% |
$15 million or higher | 0.25% |
DWSRF:
Loan Amount (DWSRF) | Eligible Interest Rate (DWSRF) |
$5 million up to $7.5 million | 0.75% |
$7.5 million up to $10 million | 0.50% |
$10 million or higher | 0.25% |
Topic 2: Eligible Costs and Timing
Topic 2: Eligible Costs and Timing
31
Eligible Costs
Topic 2: Eligible Costs and Timing
32
Eligible Costs
Contacts to discuss allowable costs:
Topic 2: Eligible Costs and Timing
33
DWSRF Technical Project Managers:
Jennifer Russell: 307-777-7626; jennifer.russell@wyo.gov
Riley Otto: 307-777-6251; riley.otto@wyo.gov
CWSRF Technical Project Managers:
Timothy Eisenhauer:
307-777-6371; timothy.eisenhauer@wyo.gov
Gregory Crocker: 307-777-6941; gregory.crocker@wyo.gov
SRF Application Steps
Submitted Needs Survey Project must be on the approved IUP's Project Priority List or Secondary Funding List in order to apply.
Topic 2: Eligible Costs and Timing
34
1. Pre-Application Meeting
2. Submit SRF Application
3. Application Review
4. Additional Documentation
5. SLIB Meeting
6. Funding Award
7. Loan Closing
8. Post-Loan Approval Meeting
Loan Phase
Award Phase
Application Phase
Timing
State Loan and Investment Board (SLIB) Meetings:
Topic 2: Eligible Costs and Timing
35
Timing
Deadlines (number of days prior to SLIB meeting):
Topic 2: Eligible Costs and Timing
36
Timing
SLIB meeting dates and application due dates can be found on:
https://lands.wyo.gov/boards/state-loan-and-investment-board
Topic 2: Eligible Costs and Timing
37
Topic 3: Federal Requirements and Equivalency
Topic 3: Federal Requirements and Equivalency
38
What Is Equivalency?
Equivalency is a unique feature of the SRF programs wherein certain program requirements apply only to a subset of SRF assistance agreements and activities referred to as “equivalency requirements.” The total amount of equivalency assistance agreements must equal the amount of the state’s annual federal SRF capitalization grant.
Topic 3: Federal Requirements and Equivalency
39
What Is Equivalency?
The SRF programs select assistance agreement(s) that will comply with equivalency requirements. Those assistance agreements are often called the “equivalency projects.” The remaining SRF assistance agreements (i.e., those outside of the equivalency projects) are not subject to and thus are not required to comply with the equivalency requirements.
Non-equivalency projects must still meet certain federal requirements (e.g. AIS and Davis-Bacon).
Topic 3: Federal Requirements and Equivalency
40
Federal Equivalency Requirements
Topic 3: Federal Requirements and Equivalency
41
Brooks Act (CWSRF Only)
Topic 3: Federal Requirements and Equivalency
42
Brooks Act
Topic 3: Federal Requirements and Equivalency
43
A/E services include:
Brooks Act: How to Comply
Topic 3: Federal Requirements and Equivalency
44
Brooks Act: How to Comply
Topic 3: Federal Requirements and Equivalency
45
Davis-Bacon Prevailing Wage Requirements�
for CWSRF Treatment Works and DWSRF Construction Projects
Topic 3: Federal Requirements and Equivalency
46
Davis‑Bacon Act
The Davis‑Bacon Act requires that all contractors and subcontractors performing construction, alteration and repair work under federal financial assistance contracts in excess of $2,000 pay their laborers and mechanics not less than the prevailing wage and fringe benefits for the geographic location.
Note: These wages are determined by the U.S. Department of Labor and may or may not coincide with other (e.g., WYDOT) labor wage rates.
Topic 3: Federal Requirements and Equivalency
47
Davis‑Bacon Act: How to Comply
Topic 3: Federal Requirements and Equivalency
48
Davis‑Bacon Act: How to Comply
Topic 3: Federal Requirements and Equivalency
49