Council Worksession

May 26, 2026

2 of 35

Capital Improvement Plan FY2027-2031

3B

Where quality meets life /

3 of 35

FY27 Active CIP Projects Proposed

3B

Total FY27 Projects

Total FY27 Budget

Total FY26 Projects

Total FY26 Budget

Facilities

11

$35,424,914

3

$185,093,627

Transportation

30

$82,012,113

35

$86,091,051

Parks

11

$13,492,666

8

$7,539,118

Drainage

3

$      808,594

0

$0

    Total General Fund

55

$131,738,287

46

$278,723,796

Water

10

$14,787,818

12

$134,648,337

Wastewater

13

$60,177,400

15

$144,225,118

Reclaimed Water

2

$  8,232,814

2

$     4,750,707

     Total Utility Fund

25

$83,198,032

29

$283,624,162

Overall Total

80

$214,936,319

75

$562,347,958

Where quality meets life /

4 of 35

FY27 CIP Projects Proposed in FY27 vs. FY26

3B

    FY27 Proposed         in FY26 CIP

FY27 Proposed

in FY26 CIP

FY27 Proposed 

in FY27 CIP

FY27 Proposed

in FY27 CIP

Facilities

6

$   2,159,416

11

$35,424,914

Transportation

35

$173,319,765

30

$82,012,113

Parks

7

$  16,134,318

11

$13,492,666

Drainage

8

$    3,087,583

3

$    808,594

     Total General Fund

56

$194,701,082

55

$131,738,287

Water

12

$  63,144,554

10

$14,787,818

Wastewater

16

$110,689,913

13

$60,177,400

Reclaimed Water

2

$    6,417,238

2

$ 8,232,814

     Total Utility Fund

30

$180,251,705

25

$83,198,032

Overall Total

86

$374,952,787

80

$214,936,319

Where quality meets life /

5 of 35

                     Proposed CIP Projects FY27

3B

7 Projects proposed with 

 2026 GO Bond $13,467,666

55 FY27 Projects fully funded ($$$179,808,979

18 FY27 Projects will need additional funding ($$21,659,676

Where quality meets life /

6 of 35

Facilities- General Fund FY2027- 8.5 Proposed Projects

3B

FA2203- DTE City Hall, Multi-Generational Rec Center and Infrastructure

FA2306-Public Works Complex ½ GF

Phase: Construction

2027 Budget: $15,088,853

Funding: $$

Completion:January 2027

Phase: Construction

2027 Budget: $5,305,960

Funding: $$

Completion: March 2027

FA2705-Library Roof Replacement

Phase: Not started

FY27 Budget: $350,000

Funding: $$

Completion: FY2027

Where quality meets life /

7 of 35

Facilities- General Fund FY2027

3B

Phase: Not started  

FY27 Budget: $619,480

Funding: $$ 

Completion: FY2027

FA2802 Evidence Processing Renovation

FA2304 ADA Transition Plan Facility Projects

Phase: Not started  

FY27 Budget: $300,000

Funding: $$

Completion: FY2027

FA2701A Justice Center Court Renovation

Phase: Not started

2027 Budget: $2,189,361

Funding:  $$

Completion: FY2027

Where quality meets life /

8 of 35

Facilities- General Fund FY2027

3B

FA2707 Public Works Building 1

Phase:  Not started

2027 Budget: $2,200,000

Funding: 2026 GO Bond

Completion: FY2029

Phase: Not started

2027 Budget: $25,000

Funding: $$ 

Completion: FY2028

FA2709 Downtown Parking Garage

Phase: Not Started

2027 Budget:$3,750,000

Funding: $ 2026 GO Bond (land only)

Completion:FY2028?

FA2704 New PAWS Animal Shelter

Where quality meets life /

9 of 35

Facilities- Utility Fund FY2027- 2.5 Proposed Projects

3B

FA2703 SCADA Network Fiber

Phase:  Not started

2027 Budget: $200,000

Funding: $$

Completion: FY2028

Phase: Not started

2027 Budget: $90,300

Funding: $$

Completion: FY2028

FA2708 Public Works Building 6

FA2306-Public Works Complex ½ UF

Phase: Construction

2027 Budget: $5,305,960

Funding: $$

Completion: March 2027

Where quality meets life /

10 of 35

Transportation FY2027 – 30 Projects

3B

TR2101 Picadilly Drive, Central Commerce Drive & Royston

TR2103 Immanuel Road Improvements

TR1904 Historic Colored Addition Infrastructure Improvements

Phase: Construction

2027 Budget: $3,657,751

Funding: $$

Completion: FY2027

Phase: Construction

2027 Budget: $11,273,185

Funding: $$

Completion: FY2028

Phase: Construction

2027 Budget: $2,802,175

Funding:  $$

Completion:  FY2027

Where quality meets life /

11 of 35

Transportation FY2027

3B

TR2008 E. Pflugerville Pkwy Realignment (Jesse Bohls) E. of Weiss

Phase: Construction

2027 Budget: $5,040,750

Funding: $$       

Completion: FY2027

Phase: Construction

2027 Budget: $8,762,917

Funding: $$ 

Completion: FY2028

TR2005 East Pflugerville Parkway (Colorado Sand to Weiss)

Where quality meets life /

12 of 35

Transportation FY2027

3B

TR2006 FM 685 Corridor Improvements Design

TR2106 East Pecan Street

Phase: Design

2027 Budget: $200,000

Funding: $$

Completion:  FY2027

Phase: Design

2027 Budget: $8,630,750

Funding: $$

Completion:  FY2028

Phase: Design

2027 Budget: $207,564

Funding: 

Completion: FY2029

TR2001 Kelly Lane Phase 3

Where quality meets life /

13 of 35

Transportation FY2027

3B

TR2104 Pfluger Farm Lane North Improvements

TR2010 City Intersection Improvements: FM 685 at Coppermine Overpass

TR2408 CR 138 @ Derby Day Intersection Control

Phase: Design

2027 Budget: $3,070,000

Funding:  $$

Completion:  FY2027

Phase: Design

2027 Budget: $3,409,854

Funding:  $$

Completion:  FY2027

Phase: Design

2027 Budget:$150,000

Funding: $$ 

Completion: FY2027

Where quality meets life /

14 of 35

Transportation FY2027

3B

TR2501 Parkway Dr Street Reconstruction and Drainage Improvements

TR2502 Dynamic Speed Feedback Signs

TR2503 Pflugerville Pkwy at Grand Avenue Pkwy and Heatherwilde Blvd- Left turn lanes

  Phase: Design

  2027 Budget: $1,170,000

  Funding: $$ 

  Completion: FY2027

Phase: Design

2027 Budget: $10,000

Funding:$$   

Completion:FY2027

Phase: Design

2027 Budget: $25,000

Funding: $$

Completion: FY2027

Where quality meets life /

15 of 35

Transportation FY2027

3B

TR2801 Limestone Commercial to Pfluger Farm Ln North (formerly Town Center Drive Extension)

Phase: Design

2027 Budget: $3,786,989

Funding: $$ 

Completion: FY2028

TR2906 Pfennig Lane Extension E. Pecan St to Wells Branch Pkwy

Phase: Design

2027 Budget: $2,250,000

Funding: $

Completion: FY2029

TR2907 Terrell Lane Extension

Phase: Design

2027 Budget: $1,035,000

Funding: $

Completion: FY2029

Where quality meets life /

16 of 35

Transportation FY2027

3B

TR2504 Picadilly Dr from IH 35 NBFR to Central Commerce Dr - Safety Lighting

Phase: Design

2027 Budget: $20,000

Funding: $$ 

Completion: FY2027

Phase: Design

2027 Budget: $6,866,333

Funding: $$

Completion: FY2027

TR2403 Weiss Lane Widening

Where quality meets life /

17 of 35

Transportation FY2027

3B

TR1903 Traffic Signal Improvement Implementation

Phase: In Progress

2027 Budget:$965,000

Funding: $$

Completion: FY2030

TR2011 2020 General Obligation Bond Program Management

Phase: In Progress

2027 Budget: $5,000,001

Funding: $

Completion: FY2030

Phase: In progress

2027 Budget: $100,000

Funding:  $$

Completion: FY 2027

TR2307 Pavement Maintenance Program

Where quality meets life /

18 of 35

Transportation FY2027

3B

Phase: Bidding 

2027 Budget: $1,547,000

Funding: $$ 

Completion: FY2028

Phase: Planning 

2027 Budget: $291,844

Funding: $$

Completion: FY2027

TR1906 Melber Ln

TR2206 FM 685 NB&SB Frontage Roads at Kelly Ln

TR2305 Intersection Design and Construction

Phase: Pre-Design

2027 Budget:$1,000,000

Funding: $

Completion: FY2030

Where quality meets life /

19 of 35

Transportation FY2027

3B

TR2601 Downtown Mobility Improvements Project

TR2405 Schultz Lane Safety Improvements

Phase: Not started

2027 Budget: $500,000

Funding: $

Completion: FY2031

Phase: Not started

2027 Budget: $5,700,000

Funding: $$ 

Completion:FY2028

TR2704 Pavement Condition Index Study

Phase: Not Started

2027 Budget:$ 200,000

Funding: $$   

Completion: FY2027

Where quality meets life /

20 of 35

Transportation FY2027

3B

Phase: Not started

2027 Budget:$ 2,405,000

Funding: $

Completion: FY2030

TR2904 Old Austin Hutto Road Extension and Pfennig Lane Extension to E. Pecan Street

Phase: Not Started

2027 Budget:$ 1,935,000

Funding: $$

Completion:FY2027

TR2410 CR 138 Widening(Future Southeast Loop)

Where quality meets life /

21 of 35

Water FY2027 – 10 Projects

3B

WA1901 Historic Colored Addition Subdivision Water Lines

WA2201 Secondary Colorado River Raw Water Line

WA2406 Water Line Rehab - Gatlinburg &Pflugerville Estates

Phase: Construction

2027 Budget:$136,037

Funding:  $$

Completion: FY2027

Phase: Construction

2027 Budget:$3,605,127

Funding:   $$

Completion: FY2027

Phase: Construction

2027 Budget:$842,127

Funding:  $$

Completion: FY2027

Where quality meets life /

22 of 35

Water FY2027

3B

WA2202 30-inch SH 130 and Pfluger Farm Lane Water Lines

WA2402 12-inch Looping Improvements in 794' Pressure Zone

Phase: Design

2027 Budget:$3,100,637

Funding: $     

Completion: FY2029

Phase: Design

2027 Budget:$3,086,369

Funding: $$

Completion: FY2028

Phase: Design

2027 Budget: $302,174

Funding: $

Completion: FY2029

WA2404 30/24-inch State Highway 45 Pump Station Discharge Line

Where quality meets life /

23 of 35

Water FY2027

3B

WA2601 5.0 MGD State Highway 45 Pump Station and 1.25 MGD Ground Storage Tank

Phase: Preliminary Design

2027 Budget: $847,704

Funding: $

Completion: FY2029

WA2103 12-inch Weiss Lane and Kelly Lane Water Lines

Phase: On hold

2027 Budget:$1,677,724

Funding: $$      

Completion: FY2029

Where quality meets life /

24 of 35

Water FY2027

3B

WA2401 Clearwell 1 Rehabilitation

Phase: Not Started

2027 Budget: $889,919

Funding: $$

Completion: FY2027

WA2702 Old Town (South) Water Lines Rehabilitation

Phase: Not Started

2027 Budget:$300,000

Funding: $$

Completion: FY2029

Where quality meets life /

25 of 35

Wastewater FY2027 – 13 Projects

3B

WW2001 6.0 Wilbarger Wastewater Treatment Plant

Phase: Construction

2027 Budget: $47,704,898

Funding: $$

Completion: FY2027

Phase: Construction

2027 Budget:$12,546

Funding: $$

Completion:FY2027

WW1902 Historic Colored Addition Wastewater Lines

Where quality meets life /

26 of 35

Wastewater FY2027

3B

WW2402 15-inch Northwest (NW) Wilbarger Wastewater Line Extension

Phase: Pending Land Acquisition

2027 Budget:$2,156,850

Funding:  $$

Completion: FY2027

Phase: Pending Land Acquisition

2027 Budget: $1,152,750

Funding: $$

Completion: FY2028

WW2401 18-inch Gilleland Creek Wastewater Interceptor

WW2503 New Sweden Lift Station and Force Main

Phase: Pending Land Acquisition

2027 Budget:$325,760

Funding: $  

Completion: FY2029

Where quality meets life /

27 of 35

Wastewater FY2027

3B

WW2304 12-Inch Bohls Place Wastewater Interceptor

WW2602 12-Inch Club Wastewater Interceptor

Phase: Design

2027 Budget: $2,033,953

Funding:  $$

Completion: FY2028

Phase: Design

2027 Budget: $731,560

Funding: $

Completion: FY2031

WW2306 Rehabilitation of Wastewater Lines

Phase: Design

2027 Budget: $2,498,982

Funding: $$

Completion: FY2029

Where quality meets life /

28 of 35

Wastewater FY2027

3B

WW2201 27-inch Kelly Lane Wastewater Interceptor

WW2403 Boulder Ridge Lift Station Rehabilitation and Expansion and 8-inch Force Main

Phase: Design

2027 Budget:$1,125,197

Funding:  $

Completion: FY2030

Phase: Design

2027 Budget: $1,346,946

Funding:  $$

Completion: FY2028

Where quality meets life /

29 of 35

Wastewater FY2027

3B

WW2601 24-inch South  Colorado Sands Interceptor

WW2705 24" Sun Light Near Way Force Main Rehabilitation

Phase: Not Started

2027 Budget: $342,475

Funding: $$  

Completion: FY2027

Phase: Not Started

2027 Budget:$400,000

Funding: $  

Completion: FY2029

Phase: Not Started

2027 Budget:$345,483

Funding: $

Completion: FY2029

WW2706 Central Wastewater Treatment Plant Rehab

Where quality meets life /

30 of 35

Parks FY2027 – 14 Projects

3B

Phase: Design

2027 Budget:$150,000

Funding: $$

Completion: FY2027

PA2602 Gilleland Creek Trail Study

Phase: Construction

2027 Budget:$2,167,666

Funding: $ 2026 GO Bond 

Completion: Ongoing

PA2603 Annual Trail Improvements

PA2403 Wells Point Park Improvements

Phase: Design

2027 Budget:$750,000

Funding: $$

Completion: FY2027

Where quality meets life /

31 of 35

Parks FY2027

3B

PA2402 Lake Pflugerville Park Phase 2

PA2006 Destination Playspace

Phase: Design

2027 Budget:$2,600,000

Funding: $$

Completion: FY2029

Phase: Design Solicitation

2027 Budget:$1,650,000

Funding: $

Completion: FY2031

Phase: In progress

2027 Budget:$700,000

Funding: $$

Completion: FY2029

PA2001 Parks 2020 GO Bond Program Management

Where quality meets life /

32 of 35

        Parks FY2027

3B

PA2704 2026 Parks GO Bond Program and Construction Management Services

Phase: Not started

2027 Budget:$2,100,000

Funding: $ 2026 GO Bond 

Completion: FY2031

Phase: Not started

2027 Budget:$150,000

Funding: $  2026 GO Bond

Completion: FY2029

PA2703 Reunion Park

Phase: Not started

2027 Budget:$125,000

Funding: $$  

Completion: FY2028

PA2801 Parks, Recreation and Open Space Master Plan Update

Where quality meets life /

33 of 35

Parks FY2027

PA2705 Park Land Acquisition

Phase: Not started

2027 Budget:$2,500,000

Funding: 2026 GO Bond

Completion: FY2030

3B

PA2701 1849 Park Phase 3

Phase: Not started

2027 Budget:$600,000

Funding: 2026 GO Bond

Completion: FY2030

Where quality meets life /

34 of 35

Drainage FY2027 – 3 projects

3B

DR2403 Caldwell Elementary at Upper Gilleland Creek Channel Improvements

DR2402 Immanuel Road/Pecan Park at Upper Gilleland Creek Channel Improvements

DR2802 Drainage Master Plan Update

Phase: Not started

2027 Budget: $161,595

Funding:

Completion: FY2030

Phase: Not started

2027 Budget:$271,999

Funding: $     

Completion: FY2030

Phase: Not started

2027 Budget:$375,000

Funding: $$ 

Completion: FY2028

Where quality meets life /

35 of 35

Reclaimed Water FY2027- 2 projects

3B

RW2401 Reclaimed Waterline to 1849 Park

RW2801 Reclaimed Water Master Plan Update

Phase: On Hold

2027 Budget:$7,982,814

Funding: $$

Completion: FY2028

Phase: Not started

2027 Budget:$250,000

Funding: $$

Completion: FY2028

Where quality meets life /