Project Management
Dr. Sangeeta Arora � (HOD, P.G dept of computer science & IT)�
Key Definitions
CREATING THE WORK PLAN
A Workplan Example
Work Plan Information Example
Name of task Perform economic feasibility
Start date ` Jan 05, 2001
Completion date Jan 19, 2001
Person assigned Mary Smith, sponsor
Deliverable(s) Cost-benefit analysis
Completion status Open
Priority High
Resources needed Spreadsheet
Estimated time 16 hours
Actual time 14.5 hours
Identifying Tasks
Top Down Task �Identification
Phases
Phases with
high level steps
Work Plan Deliverables Estimated Actual Assigned
hours hours To
*
*
*
*
Estimating a Project Based on Industry Information
Planning Analysis Design Implementation
Industry
Standard
For Web 15% 20% 35% 30%
Applications
Time
Required 4 5.33 9.33 8
in Person
Months
Time Estimation Using a More Complex Approach
Estimation Trade-offs
Getting the Right Numbers for Estimation
Estimating Effort
COCOMO Estimation Calculation
Effort = 1.4 * thousands-of-
(in Person- lines-of-code
Months)
Example:
If LOC = 2000 Then...
Effort = (1.4 * 2000) = 28 Person Months
Estimating Schedule Time
Schedule Time (months)
=
3.0 * person-months1/3
Staffing Attributes
STAFFING THE PROJECT
Key Definitions
Motivation
Conflict Avoidance Strategies
CONTROLLING AND DIRECTING THE PROJECT�
Margins of Error in �Cost and Time Estimates
Typical margins of Error for
Well-done Estimates
Phase Deliverable Cost (%) time (%)
Planning System Request 400 60
Project Plan 100 25
Analysis System Proposal 50 15
Design System Specification 25 10
Source: Boehm et al. (1995)
Tracking Tasks Using Gantt Chart
Action Week
2 3 4 5 6 7 8 9 10 11 12 13
CASE Tools
Initiation Analysis Design Implementation
Upper CASE Lower CASE
Integrated CASE (I-CASE)
CASE Components
Procedural Metadata
Logic
Diagrams Screen
Designs
CASE Repository
Standards
Documentation
Managing Scope
Managing Risk
Classic Mistakes
Summary