SAP Project System
Unit 5
Project Materials
Exercise 30
Perform a Material
Availability Check
Open
T-600##
Select Network Header
Edit - Availability - Material
All Material Available
Material T-20600 increase +1 Qty
Qty 2 -> 3
Select Network Header, the
Edit - Availability - Material
ATP = 2
Commited 2
Check Group at Material MRP3
data view
Check Rule at
Network Order Type
What to consider during ATP check
MPST
Missing Parts Status
Should have MPST status
AV check group
Check Rule assignment
Order creation check rule
Order release
rule
Network Order Type
AV check rule