SAP Plant Maintenance

Preventive Maintenance

Scenario

Breakout Plans

2 of 21

24 Equipments INSTALLED with +1 Equipment as SPARE

TOTAL 25 Equipment in FACTORY at a Time

with 24 Installed and 1 in the warehouse.

All Equipments have 4 Years Cycle

When Each Equipment is DUE at the 4 year cycle,

the SPARE will be Installed …

the Dismantled Equipment will send out for REFURB

which will take 1 month.

Constraint is the SINGLE Contractor can only do REFURB for ONE Equipment at a Time.

Therefore the DUE Dates for the the Equipments cannot coincide due to the 1 month Constraint.

3 of 21

24 Equipments created

4 of 21

Check the

Maintenance Plan

for EQ01

5 of 21

4 Years Cycle

EQ01

6 of 21

Time - key date will use same day in the plan date

Next cycle will be on the same day in 4 years time

01.06.2017 (cycle start)

01.06.2021 (next plan date)

Set call date 1 day b4 due date

Set 24 years period of scheduling

7 of 21

User SORT Field PUMP to collect the MP together

8 of 21

Use SORT field PUMP for MP Reporting

9 of 21

10 of 21

11 of 21

All Cycle Start Dates are Exactly 1 month apart from the first MP’s 01.06.2017.

Note after first scheduling, the Cycle Start Date cannot be changed.

12 of 21

IP30 scheduling (using Sort field to collect the PUMP MPs)

13 of 21

14 of 21

Due to Time - Key Date, Due/Plan Dates are on Same Days 01.06 for the next Cycles.

15 of 21

EQ01

Planned Dates on

01.06.20##

16 of 21

EQ02

Planned Dates on

01.07.20##

17 of 21

EQ03

Planned Dates on

01.08.20##

18 of 21

EQ04

Planned Dates on

01.09.20##

19 of 21

Since the Cycle is 4 years (48 months)

There are only 24 Equipments in this example, therefore none of the Planned Dates will Overlap

20 of 21

Graphical view of Schedules

21 of 21

Note, none of the Planned/Due Dates coincide and there each is exactly 1 month apart