KHNP’s Confidence
for the Dukovany project
Contents
1 KHNP’s Strengths
2 On Time & Within Budget
3 Licensability for European Requirements
4 Substantive Localization
5 Mobilization of Manpower
6 KHNP, The Preferred Bidder
7 Cooperation with the Region
8 Czechia-Korea Cooperation
KHNP’s STRENGTHS
EXCELLENT CONSTRUCTION KNOW-HOW
COMPETITIVE COSTS
RELIABLE SAFETY
EXCELLENT PROJECT SCHEDULE
Design basis earthquake: 0.3g
Resistant to magnitude 7.0 earthquakes
Passive Auxiliary Feedwater System (PAFS)
Removes decay heat from the reactor core without power supply for at least 24 hours in the event of an accident
Severe Accident Mitigation System
Minimizes the off-site release of radioactive materials after a serious incident without external power or operators
PROJECT | KOREA (APR1400) | FRANCE (EPR1600) |
DOMESTIC | Saeul 1 (98 months) | Flamanville 3 (2007 to present) |
OVERSEAS | Barakah 1, 2, 3 (104, 107, 101 months) | Olkiluoto 3 (212 months) |
Accumulated construction expertise over 50 years
TOTAL | |||
IN OPERATION | 28 | UNDER CONSTRUCTION | 3 |
DOMESTIC | 25 | DOMESTIC | 2 |
OVERSEAS | 3 | OVERSEAS | 1 |
36 UNITS
Planned for construction: 2 units
Shutdown: 2 units
Awaiting life extension: 1 unit
K
H
N
P
Source: IAEA PRIS
1
Dukovany New Nuclear Build
Latest most competitive cost
Cost reduced due to building 2 units
200 bil. CZK per 1 unit
ON TIME & WITHIN BUDGET
KHNP has never requested any deadline extension so far.
Dukovany Nuclear Power Plant (EDU5) will be completed in 2036.
MARCH 2022
INVITATION TO BID
BID PROCESS
NOV. 2022
Submitted INITIAL BID
2022 to 2023
OCT. 2023
Submitted UPDATED INITIAL BID
FEB. to MAY 2023
Participated in CLARIFICATION MEETINGS with THE OWNER (5 TIMES)
EVALUATION & NEGOTIATIONS
JULY 2024
PREFERRED BIDDER SELECTION
2024
MARCH 2025
CONTRACT CONCLUSION
PROJECT EXECUTION
2029 ONWARDS
2029
CONSTRUCTION STARTS
2036
COMMERCIAL OPERATION
APRIL 2024
Submitted UIB SUPPLEMENT
2
ON TIME & WITHIN BUDGET
KHNP has simultaneously constructed 9 units of nuclear power plants.
KHNP will deliver everything on time.
2000
2010
2020
2030
SHIN-KORI 1&2
SHIN-WOLSONG 1&2
SAEUL 1&2
SHIN-HANUL 1&2
SAEUL 3&4
SHIN-HANUL 3&4
BARAKAH 1&2
BARAKAH 3&4
SAEUL 2,
SHIN-HANUL 1&2,
SAEUL 3&4,
BNPP 1 to 4
CONSTRUCTED �9 UNITS AT THE SAME TIME
DUKOVANY 5
50 Years of Non-stop Construction
Success Story in the UAE
2
Unit 4 COD 5th of Sep.
Unit 1~3 in operation
FIRST NPP in the MIDDLE EAST
LICENSABILITY FOR EUROPEAN REQUIREMENTS
EUR CERTIFICATION
KHNP is familiar with European requirements, has acquired EUR certification for the APR1000
Discussions between regulatory bodies of both countries are ongoing to secure licensability
KHNP is pursuing Korean Standard Design Approval (SDA) for the APR1000 on time for licensing documentation submission for Dukovany NPP
STANDARD DESIGN APPROVAL (SDA)
REGULATORY COOPERATION
3
Classification | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | |
Dukovany Project | | | | | | | | |
SDA for APR1000 | Preparation Phase | | | | | | | |
Review Phase | | | | | | | | |
Issuance of Certificate | | | | | | | | |
EPC Contract
(Mar. 2025)
Construction Commencement
(Aug. 2029)
Application for SDA
(Dec. 2024)
Issuance of Safety Evaluation Report
(Sep. 2026)
Issuance of SDA Certificate
(Mar. 2027)
EUR Certificate for the APR1000
Schedule for SDA of APR1000 for Dukovany
SUBSTANTIVE LOCALIZATION
“KHNP is the only company that will utilize the turbines produced in the Czech Republic.”
AREA | CORE STRATEGY | CZECH COMPANIES |
Design | Consultation & joint design with Czech companies | UJV Rez, I&C Energo, OSC, SKODA JS, Bilfinger Tebodin, etc. |
Components | Subcontracting, categorizing based on technical difficulties | ABO Valve, I&C Energo, MICo, NUVIA, OSC, Sigma Group, SKODA JS, Skoda Power, VES, ZAT, BAEST, Chemcomex, IBC Praha, Infer, TES Vsetin, VALVEA, ZVVZ, etc. |
Construction | Local workforce, materials, construction equipment and logistics, etc. | Metrostav DIZ, Arch. Design, Algeco, Baucomex, Bohemia Müller, CHB Logistics, Colas CZ, ELECTROTRANS, Hilti, Hutni Montaze, Reko Praha, etc. |
Maintenance | OJT&OJP (Training&Participa- tion) based plant maintenance | I&C Energo, TES, Betvar, G-Team, HOCHTIEF, etc. |
Nuclear fuel | Consultation for core design & safety analysis of nuclear fuel | UJV Rez, ALVEL, etc. |
KHNP’s Localization Strategy
Over 200 companies identified by KHNP, total 1,000 companies by Korean companies & 76 MOUs concluded
4
MOBILIZATION OF MANPOWER
Labor Forces
(Expected 3,000 for 1 unit, 5,000 for 2 units)
Mobilize the labor forces from EU and other European countries in case of lack of workers in the Czech Republic
Mobilize the labor forces from the Czech Republic first as many as possible considering localization
Mobilize U.A.E. experienced labor forces under the Czech authority’s approval in case No. 1 & 2 are insufficient
Czech workers
European workers
Other workers
KHNP will mobilize Czech workers first as many as possible considering localization.
Priority
1
2
3
Countries preferred by the Czech Republic are priorities.
5
KHNP, THE PREFERRED BIDDER
6
“The Decision was unanimous.”
“The Korean offer was better practically in all assessed criteria.”
- Prime Minister
· Shared Vision
for the Project’s Sucess
· KOR Government’s willingness
to Support
Special Envoys to Czechia
CEOs of CEZ and KHNP
Negotiation Kick-off
· Beginning the Preparation for the � Final Contract in March 2025
Press Briefing on the Selection of the Preferred Bidder(17th July)
COOPERATION WITH THE REGION
7
Construction Infrastructure
Facilities for workers
· Preparing for Full-scale Construction starting from 2029
· Cooperation with the region is KHNP’s priority
KHNP will continue communicating with the region through ET and OHK Trebic
PROJECT PREPARATION
PROJECT EXECUTION
NEGOTIATIONS
2025
ENGINEERING
2027
LICENSING
2029
CONSTRUCTION STARTS
MAR. 2025
CONTRACT CONCLUSION
Dukovany 1~4
Dukovany 5&6
COOPERATION WITH THE REGION
7
Sponsor since 2018
Invitation program to Korea
Donation
Volunteer Program since 2017
KHNP will explore new collaboration programs based on the successful cooperation with the region.
CZECHIA-KOREA COOPERATION
IT & 5G
First country to commercialize 5G network (2019)
TOURISM
SEMICONDUCTORS
BATTERIES
No. 2 in the global market share for secondary batteries in 2021
Secured supply chain for automotive semiconductors between the Czech Republic & Korea
DEFENSE & TRANSPORTATION
HYDROGEN
Cooperation in the nuclear industry can expand to multiple sectors.
8