FY 2025

OPERATIONAL PLAN

Mid Year Assessment

2 of 41

Operational Plan Targets

OFFICE OF THE

UNIVERSITY PRESIDENT

3 of 41

OFFICE OF THE UNIVERSITY PRESIDENT

OFFICER-IN-CHARGE

LEGAL UNIT

Atty. Ma. Cecile Candida Y. Rueda

INTERNATIONAL AFFAIRS OFFICE

Dr. Iris Bejasa

INTERNAL AUDIT UNIT

Mr. Michael Noel D. Obrino

PUBLIC RELATION OFFICE

Dr. Rhio C. Dimakiling

PLANNING OFFICE

Ms. Jonah L. Salcedo

GSIPMO

Engr. Marlon D. Sobreviga

PROJECT DEVELOPMENT UNIT

Mr. Redem D. Tingzon

4 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

100% legal review of MOAs, MOUs, policies and contracts.

100

Processed review of MOAs, MOUs, policies and contracts.

0%

FOR FINALIZATION WITH GAD DIRECTOR

REVIEW OF THE MANUAL WITH GAD DIRECTOR & COMMITTEE

100%

Assist departments in identifying/reviewing policy/ies gaps in compliance with

applicable laws, rules, guidelines

100%

Assisted the departments in identifying policy/ies

0%

INTERNAL POLICY - APPROVED

MOP FOR FINALIZATION

100%

establish workflows for common legal tasks

100%

workflows established for common legal tasks

0%

WORKFLOW ESTABLISHED DATED: FEB.2025

100%

Finalize and approve manual for the Legal Services Unit

0%

4TH QTR

0%

4TH QUARTER TARGET IMPLEMENTATION

(waiting for the onboarding of team members.)

100%

Achieve 100% MCLE compliance within compliance period

100%

for the 8th compliance period (April 2022 - April 2025)

0%

ACCOMPLISHED

100%

(1/1)

Facilitate/deliver one dedicated legal advocacy session per year, made available to any requesting department.

100%

(1/1)

Delivered one (1) session annually upon request of interested department/s

0%

WOMEN'S MONTH CELEBRATION - PDL

BJMP MARCH 30, 2025

100%

(1/1)

One (1) Team member certified in 2025

0%

FOR THE 4TH QTR

-100%

WAITING FOR TEAM MEMBERS (STILL IN THE PROCESS OF STAFFING THE TEAM) FOR THE PARALEGAL CERTIFICATION, ETC

LEGAL UNIT

5 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

Create one (1) benchmarking partner & organize one (1) site visit/benchmark to learn about processes, policies and tools to existing legal units in universities & other government agencies

0%

in-progress/finalizing proposal

-1

TARGET PERIOD FOR IMPLEMENTATION: 3RD TO 4TH QTR (AWAITING ONBOARDING OF TEAM MEMBERS)

1

Draft and finalize one agreement with internal/external partner

0%

PROPOSAL PREPARATION STAGE

-1

TARGET PERIOD FOR IMPLEMENTATION: 3RD TO 4TH QTR

1

Support 1 project/extension

0%

with forthcoming schedule with GAD Director - JULY 2025

-1

TARGET PERIOD FOR IMPLEMENTATION 3RD QTR

100%

Formalize one joint-legal clinic service in collaboration with internal or external partners.

0%

FINALIZING PROPOSAL - ULAS GUIDELINES

-100%

3RD QTR

6 of 41

SUMMARY OF PERFORMANCE

LEGAL UNIT

TOTAL NO. OF TARGETS9

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

11

5

1* with draft subject to review by the committee

5

45.5%

9%

45.5%

7 of 41

Human Resource/s Support/Manpower:

Staffing & Recruitment

Training & Professional Development:

Budget and time allocation for mandatory continuing legal education (MCLE), specialized training (e.g., new laws, specific industry regulations, negotiation skills, compliance software/application).

Technological & Infrastructure/Workspace Support

  1. Dedicated and Secure Workspace
  2. Secure Document Storage
  3. PC/laptop, printer, scanner

SUPPORT NEEDED

LEGAL UNIT

8 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

Explore further collaboration

2

Explored further collaboration

0

Accomplished

ahead of target date

(TVU-1st Quarter)

1

Invite interested agencies

1

Invited interested agencies

0

Accomplished

(DThu-2nd Quarter)

1

Conduct promotional activities

0

1

Target implementation on 3rd Quarter

1

Conduct and attend conferences, summits, etc.

1

Conducted and attended conferences, summits, etc.

0

Accomplished

(March 2025)

1

Membership in local and international organizations

2

Membership in local and international organizations

0

Accomplished ahead of target date

(AUAP, ATU-Net, 1st Quarter)

1

Meet and discuss with partners on the duties, responsibilities, and expected outcomes of the agreements

1

Met and discussed with partners on the duties, responsibilities, and expected outcomes of the agreements

0

Accomplished

(TVU-March 2025)

INTERNATIONALIZATION

9 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

Finalize and formalize the MOA or MOU

Internationalization: Facilitate on the renewal of expired MOA/MOU

1

Finalized and formalized the MOA or MOU; Facilitated on the renewal of expired MOA/MOU

0

Accomplished ahead of target date

(TVU- March 2025)

1

Conduct monitoring, reposting, and post evaluation

To be accomplished on the 4th Quarter

1

Process post-evaluation results for

enhancement

Target implementation on the 4th Quarter

1

Internationalization:

1. Apply for Authority to Accept Foreign Students from Bureau of Immigration

Target implementation on the 3rd & 4th Quarter

1

Maintain open communication and coordination of related concerns to satisfy the needs of both parties

1

Maintained open communication and coordination of related concerns to satisfy the needs of both parties

0

Accomplished ahead of target date

10 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

Fulfill the terms and conditions agreed upon by the parties

1

Fulfilled the terms and conditions agreed upon by the parties

0

Accomplished ahead of target date

(TVU MOU/MOA-March 2025)

Act on the concerns raised in the post evaluation.

In process

(Target implementation on the 4th Quarter)

1

Attend/participate international engagement

1

Attended/participated international engagement

0

Accomplished

1

Conduct benchmarking and redo best practices of successful organizations and internationalization.

Target implementation on the 3rd and 4th Quarter)

Develop or enhance academic degree program

N/A

Since this is the responsibility of the Academic Division)

11 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

(Faculty Mobility) Establish Linkage/Partnership internationally.

1

(Faculty Mobility) Established Linkage/Partnership internationally.

0

Accomplished

(TVU-March 2025)

1

(Student Mobility) Establish linkage /partnership internationally

1

Established linkage /partnership internationally

0

Accomplished

(TVU-March 2025)

12 of 41

INTERNATIONALIZATION

TOTAL NO. OF TARGETS

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

18

11

0

7

61.11%

38.89%

SUMMARY OF PERFORMANCE

13 of 41

Increase of budget

Assistance of offices incharge for the needed

SUPPORT NEEDED

INTErnationalization

14 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(1/1)

Revisit and align the Internal Audit Manual with the provisions of DBM's NGICS, RPGIAM, and the COA's IASPPS and ICSPPS and other relevant guidelines and regulations for the year.

100%

(1/1)

Revisited and aligned the Internal Audit Manual with the provisions of DBM's NGICS, RPGIAM, and the COA's IASPPS and ICSPPS and other relevant guidelines and regulations for the year.

0

Accomplished.

Already produced an Internal Audit Manual (awaiting for review of the IAU Head)

100%

(1/1)

No impairment of independence (100% Independence Rate); independence confirmation is performed and monitored periodically

100%

(1/1)

No impairment of independence (100% Independence Rate); independence confirmation is performed and monitored periodically

0

Accomplished

240

At least eighty (80) hours of relevant internal audit training is completed by each internal audit personnel within the year. (80x3=240 hrs)

78%

(188/240)

hours of relevant internal audit training is completed by each internal audit personnel within the year.

52

Accomplished

100%

(1/1)

Internal audit team to engage benchmarking activities, and establish meaningful relationship with at least one (1) state universities

0%

(0/1)

Internal audit team was not able to engage in benchmarking activities, and establish meaningful relationship with at least one (1) state universities due to resignation of the head.

-1

Unmet

Coordinate with Budget Office and Key officials

100%

(1/1)

Internal audit team to attend at least 1 major internal audit conference/convention, trainings, etc.

0%

(0/1)

Schedule in 3rd and 4th Quarter (3 personnel of the IAU)

1

Not Applicable for this Rating Period

INTERNAL AUDIT UNIT

15 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(4/4)

Perform adequate reporting of the internal audit unit's performance monitoring, audit findings and recommendation of identified gaps/deficiencies as regards the University's risk, control, and governance, in accordance with the targets set by the DBM through NGICs, COA recommendations, and individual and university targets - Submission of 4 Quarterly Internal Audit Reports

50%

(2/4)

Submitted 2 accomplishment report for first two (2) quarters

2

Remaining 2 (two) for 3rd and 4th Quarter

100%

(2/2)

Conduct two (2) pre-orientation of auditees for the internal audit function of the IAS

50%

(1/2)

Conducted one (1) pre-orientation of auditees

1

1 remaining for 2nd Half

100%

(2/2)

Prepare a 3-year Strategic Plan and one (1) Annual Work Plan for 2025 (Approved by the Board and the University President)

0%

(0/2)

2

Unmet

Schedule a meeting with the UP to align with his strategic vision

100%

(1/1)

Perform Baseline Assessment of the Internal Control Systems (BAICS) of all auditees within the audit period.

0%

(0/1)

Currently in the Understanding the Environment phase of BAICS.

1

On-going

16 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

2

Perform Audit Execution - Compliance Audit on two (2) auditees

0/2

Currently in the understanding the environment phase of BAICS.

2

Ongoing

2

Perform Audit Execution - Management Audit on two (2) auditees

0

Scheduled in 3rd Quarter

0

Not Applicable for this Rating Period

2

Perform Audit Execution - Operations Audit on two (2) auditees

0

Scheduled in 3rd Quarter

0

Not Applicable for this Rating Period

1

Perform Special Audit on SALN on key officials

0

Scheduled in 3rd Quarter

0

Not Applicable for this Rating Period

1

Report the results of audit: 4Cs (criteria, condition, conclusion, and cause) for all audits

0

Scheduled in 4th Quarter

0

Not Applicable for this Rating Period

1

Prepare audit recommendations based on the current audit cycle report and release to auditees

0

Scheduled in 4th Quarter

0

Not Applicable for this Rating Period

17 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

100% monitoring and follow up implementation of recommendations and prepare an audit follow-up report (AFR)

0

Scheduled in 4th Quarter

Not Applicable in this Rating Period

97%

Conduct client satisfaction surveys post-audit and achieve a satisfaction rate of at least 97% from all auditees.

0

Scheduled in 4th Quarter

Not Applicable in this Rating Period

5

Perform at least five (5) advisory engagements for the year and provide granular and effective recommendations

2

Conducted two (2) advisory services

3

Remaining 3 for the 3rd and 4th Quarter

100%

Perform 100% monitoring of COA Findings for Human Resource Management, Supply and Property Management, Supplies and Materials Inventory, Records Management, Financial Operation and Management, Budget Generation and Utilization, Status of Liquidations, and help the various offices in resolving the findings through adequate appraisal of controls, including policies and procedures, and granular and effective recommendations. Create an institutional document for monitoring COA Findings.

73%

73% of the AOMs are monitored.

On going monitoring of the AOMs up until year end

18 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

4

Perform adequate reporting of the internal audit unit's performance monitoring, audit findings and recommendation of identified gaps/deficiencies as regards the University's risk, control, and governance, in accordance with the targets set by the DBM through NGICs, COA recommendations, and individual and university targets - Submission of 4 Quarterly Internal Audit Reports

2/4

Submitted Accomplishment Reports for the first two (2) quarters

Remaining 2 for 3rd and 4th Quarter

19 of 41

INTERNAL AUDIT UNIT

TOTAL NO. OF TARGETS

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

20

9

2

9

45%

10%

45%

SUMMARY OF PERFORMANCE

20 of 41

Manpower, office equipment

SUPPORT NEEDED

INTERNAL AUDIT UNIT

21 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

1

Conduct one (1) BPA/Stakeholders Assembly per year.

0

Scheduled in 4th Quarter

-100%

Not Applicable for this Rating Period

100%

Update the P/A/P entries in the PIPOL System

0

Scheduled in 4th Quarter

-100%

Not Applicable for this Rating Period

100%

Compliance to the Budgetary Requirements for Congress, Senate, and CHED

0

Scheduled in 3rd Quarter;

OUP Memo No. 18, series of 2025

-100%

Not Applicable for this Rating Period

100%

Compliance to PASUC Survey Requested Documents

0

Scheduled in 3rd Quarter

Released OUP Memo No. 18, series of 2025 in preparation

-100%

Not Applicable for this Rating Period

100%

Secure LGUs, RDC, NEDA and DBM Endorsements for the Priority Projects, Programs, and Activities

100%

(4/4)

Secured the necessary endorsements of the Priority Projects, Programs, and Activities from LGU, RDC, NEDA, and DBM.

0%

PLANNING OFFICE

22 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Submission of documentary requirements needed FY 2026 Budget Preparation (Physical Targets, BEDs, etc.)

100%

(29/29)

Submitted the documentary requirements needed FY 2026 Budget Preparation (Physical Targets, BEDs, etc.)

0%

Accomplished

100%

Facilitate (2) Quarterly Monitoring for first rating period, and another (2) for the second rating Report of Accomplishment for GAA Targets (APR)

100%

(2/2)

Facilitated (2/2) Quarterly Monitoring Report of Accomplishment for GAA Targets

0%

Accomplished

100%

100% Preparation for the Baseline Data of the Proposed New PREXC Indicators

No movement in the National Commission on Higher Education

Not Applicable for this rating period

100%

Submission of Agency Performance Report (APR)

100%

(1/1)

Submitted the APR on the deadline

0%

Accomplished

100%

Conduct (6/6) for first rating periods, and (6/6) Monthly Monitoring of Operational Plan

100%

(6/6)

Conducted Monthly Monitoring of Operational Plans

0%

Accomplished

23 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(2/2)

Conduct one (1) Mid-Year Evaluation of Strategic Plan and one (1) Operational Planning Workshop within July 2025

0%

Scheduled in June 30-July 4, and July 13-16, 2025 to be held in BDC and Caluwayan Palm Island Beach & Resort.

-100%

Not Applicable for this rating period

100%

(1/1)

Conduct one (1) Year-end Evaluation within December 2025 and SPMS Re-Orientation

0%

Scheduled in 4th Quarter

-100%

Not Applicable for this rating period

100%

(1/1)

Publish Operational Plan Accomplishment FY 2025

100%

(1/1)

Published Operational Plan Accomplishment FY 2025 in the website

0%

Accomplished

100%

Monitor the submission of the content in transparency seal.

100%

(24/24)

Monitored the submission of the content in the transparency seal.

0%

Accomplished

100%

Facilitate submission all the requirements for PBB with 95% accuracy and within the timeframe.

0%

Waiting for the new issuance of requirements; 100% (32/32) documents were prepared based on Memorandum Circular 2023-1 as the latest issuance.

-100%

Not Applicable for this rating period

24 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Assistance in processing the WURI application.

100%

(3/3) Project Entries were submitted

0%

Accomplished

100%

Submission of the requested documents for ISO compliance.

100%

(7/7)

Submission of Required Documents for ISO

0%

Accomplished

100%

Assistance in ensuring requested submission of requirements to Times Higher Education portal.

100%

(249/249)

Assisted in monitoring the data requirements, and facilitated the packaging of THE submission, 249 available data entries/indicators were posted in the website and submitted in the THE Portal coming from various units.

Accomplished. Obtained 46.8 out of 100, NwSSU Ranked 1501+ out of 2318 institutions, Participated in 16 out of 17 SDGs

0%

Accomplished

100%

Assistance in submission of requested documents to ensure the attainment of the Philippine Quality Assurance Award.

30%

Ongoing

-70%

Not applicable for this Rating Period

25 of 41

Planning office

TOTAL NO. OF TARGETS

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

19

10

0

9

52.63%

0%

47%

SUMMARY OF PERFORMANCE

26 of 41

SUPPORT NEEDED

planning office

Consistent and Reliable Data from each office.

27 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment in the preparation of the revised campus development plan considering the facilities of new proposed programs to be offered by the university.

100%

Accomplished in the preparation of the revised campus development plan considering the facilities of new proposed programs to be offered by the university.

0

On Target

100%

Accomplishment in the preparation of the detailed plans/drawings and program of works of the (15) priority infrastructure projects of the university for 2026 NEDA/DBM/PPP budget proposal submission.

100%

Accomplished in the preparation of the detailed plans/drawings and program of works of the (15) priority infrastructure projects of the university for 2026 NEDA/DBM/PPP budget proposal submission.

0

On Target

100%

Accomplishment in the preparation of the detailed plans/drawings, program of works (POW), and scope of works (SOW) of identified university's infrastructure projects under GAA 2025 Insertion/FLR budget, ready for procurement.

0%

*No insertion/FLR budget given as of this date.

-

Not Applicable for this rating period

100%

Accomplishment in the preparation of the detailed plans/drawings, program of works (POW), and scope of works (SOW) of identified university's infrastructure projects under Special Trust Fund (STF)/other funding agencies ready for procurement.

80%

Accomplished the preparation of the detailed plans/drawings, program of works (POW), and scope of works (SOW) of identified university's infrastructure projects under Special Trust Fund (STF)/other funding agencies ready for procurement.

-20%

Not Applicable for this rating period

100%

Accomplishment in the preparation of technical project proposals with detailed plans/drawings and program of works of selected infrastructure projects of the university for 2026 budget proposal submission thru Public-Private Partnership program.

0%

*To start with the identification this July 2025

-

Not Applicable for this rating period

GSIPMO

28 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment in the implementation of the infrastructure projects under GAA 2025 Capital Outlay and Insertion/FLR budget, as programmed and scheduled.

75.89%

accomplished in the implementation of the infrastructure projects under GAA 2025 Capital Outlay and Insertion/FLR budget, as programmed and scheduled.

+40%

Above Target

(Construction of Students’ Dormitory - Phase 7)

100%

Accomplishment in the implementation of the infrastructure projects under Special Trust Fund (STF)/other funding agencies, as programmed and scheduled.

0%

*No project yet for implementation

-

Not Applicable for this rating period

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to concrete, masonry, and other related works.

72.73%

(16/22)

Accomplished the approved scheduled repair and maintenance activities in relation to concrete, masonry, and other related works.

-27.27%

Below Target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to carpentry works and other related works.

100%

(149/149)

Accomplished the approved scheduled repair and maintenance activities in relation to carpentry works and other related works.

0%

OnTarget

29 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to painting and other related works.

90%�(18/20)

Accomplished the approved scheduled repair and maintenance activities in relation to painting and other related works

-10%

Below target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to steel, aluminum, glass, and other related works.

100%�(65/65)

Accomplished the approved scheduled repair and maintenance activities in relation to steel, aluminum,glass and related works

0%

On Target

100%

Accomplishment of the approved scheduled activities in relation to plumbing and sanitary works.

89.66%�(52/58)

Accomplished of the approved scheduled activities in relation to plumbing and sanitary works.

-10.34

Below target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment of the approved scheduled activities in relation to landscaping, safety, and environment organization.

100%�(33/33)

Accomplished of the approved scheduled activities in relation to landscaping, safety, and environment organization

0%

On Target

80%

Accomplishment in the preparation of water supply and distribution system development plan for main campus lots.

80%

Accomplished the preparation of water supply and distribution system development plan for main campus lots.

0%

On Target

30 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment in the compliance of the cost-cutting measures established by the office.

100%

(30/30)

Accomplished the compliance of the cost-cutting measures established by the office.

0%

On Target

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to plumbing for water supply system.

92.06%�(58/64)

Accomplished of the approved scheduled repair and maintenance activities in relation to plumbing for water supply system.

-7.94

Below target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment in the preparation of drainage system development plan for main and campus lots.

75%

Accomplished in the preparation of drainage system development plan for main and campus lots.

+8.33%

Above Target

100%

Accomplishment in the preparation of sewerage system development plan for main campus lots.

75%

Accomplished the preparation of sewerage system development plan for main campus lots.

+8.33%

Above Target

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to drainage and sewerage system repair and maintenance.

100%�(1/1)

Accomplished of the approved scheduled repair and maintenance activities in relation to drainage and sewerage system repair and maintenance.

0%

On target

31 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment in the preparation of electrical distribution system development and expansion plan for main campus lots.

92%

Accomplished in the preparation of electrical distribution system development and expansion plan for main campus lots.

+25.33%

Above Target

100%

Accomplishment in the compliance of the cost-cutting measures established by the office.

80%

(24/30)

Accomplished in the compliance of the cost-cutting measures established by the office.

-20%

Below Target

Solar power system for Hamorawon Fence lamp post is defective

Fix solar powered lamp posts.

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to mechanical and electrical works.

100%�(245/245)

Accomplished of the approved scheduled repair and maintenance activities in relation to mechanical and electrical works.

0%

On Target

100%

Accomplishment in the preparation of electronics and communication system development plan for main campus lots.

75%

Accomplished the preparation of electronics and communication system development plan for main campus lots.

+8.33%

Above Target

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to electronics and communication works.

94.12%�(16/17)

Accomplished of the approved scheduled repair and maintenance activities in relation to electronics and communication works.

-5.88

Below Target

Improve monitoring and control to properly manage activity status.

32 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

Accomplishment in the preparation of environmental and pollution control management system.

50%

Accomplished the preparation of environmental and pollution control management system.

0%

On Target

50%

Accomplishment in the preparation of development plans for sanitary landfill, waste treatment plant, and other pollution control facilities.

15%

Accomplished the preparation of development plans for sanitary landfill, waste treatment plant, and other pollution control facilities.

+2.5%

Above Target

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to janitorial works and services.

94.97%

Accomplished the approved scheduled repair and maintenance activities in relation to janitorial works and services.

-5.03%

Below Target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment of the approved scheduled repair and maintenance activities in relation to proper waste disposal.

90%

Accomplished the approved scheduled repair and maintenance activities in relation to proper waste disposal.

-10%

Below Target

Improve monitoring and control to properly manage activity status.

100%

Accomplishment of the approved scheduled activities in relation to the provision of environmental and pollution control signages.

72%

Accomplished the approved scheduled activities in relation to the provision of environmental and pollution control signages.

+22%

Above Target

33 of 41

SUMMARY OF PERFORMANCE

GSIPMO

TOTAL NO. OF TARGETS

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

29

17

8

4

58.62%

27.59%

13.79%

34 of 41

SUPPORT NEEDED

GSIPMO

  • Allotment of fund for the continuation of the hiring of COS engineers for the regular preparation of required documents of the priority infra-projects.
  • Utilization of STF for small value infra-projects to speed up infrastructure development.
  • Adequate fund for the hiring of additional Janitorial/Helper/Utility personnel.
  • Salary increase for the hiring of Job Order Skilled Personnel to attract qualified and experienced applicants.
  • Allocation of adequate fund for the procurement of repair and maintenance materials.

35 of 41

PROJECT DEVELOPMENT UNIT

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(2/2)

accomplishment in sustaining/monitoring partnerships with two (2) private companies / institutions

100%

(2/2)

partnerships with two (2) private companies / institutions sustained and monitored

Accomplished ahead of the deemed rating period

100%

(2/2)

accomplishment in sustaining/monitoring partnerships with two (2) government institutions

100%

(2/2)

partnerships with two (2) government institutions

sustained & monitored

Accomplished ahead of the deemed rating period

100%

(2/2)

100% accomplishment in securing partnerships with private institution/s for proposing two (2) projects/programs

100%

(2/2)

partnerships with private institution/s for proposing two (2) projects/programs

secured

Accomplished ahead of the deemed rating period

100%

(2/2)

accomplishment in securing partnership with government institution/s for proposing two (2) projects/programs

50%

(1/2)

Ongoing

Not applicable for this rating period

100%

(2/2)

100% accomplishment in translating two (2) engagements in 2024 into forged partnerships (government or private)

50%

(1/2)

One engagement in 2024 forged into partnerships `

-1

(Below target)

Accomplished

Will facilitate forging of partnership with one more institution from 2024 engagement

36 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(2/2)

accomplishment of two (2) project/programs approved in the previous year/s, managed or co-managed for continuous development or sustainability

100

(2/2)

Two (2) project/programs approved in the previous year/s, managed or co-managed for continuous development or sustainability

0

Accomplished

100%

(2/2)

accomplishment of two (2) project proposals developed and presented to the Administrative or Academic Council

1 project, ongoing development

Not applicable for this rating period

100%

(2/2)

accomplishment in providing technical assistance to two (2) administrative / non-teaching office on project development

150%

(3/2)

Three (3) administrative / non-teaching office on project development provided with technical assistance

50%

(+1)

Above Target

100%

(2/2)

accomplishment in providing technical assistance to two (2) college department on project development

100%

(2/2)

Two college / academic department provided technical assistance on project development

0

Above Target

100%

(10/10)

accomplishment in providing technical coaching for ten (10) project proposals submitted to the PDU

100%

5/5

five out of five project proposals submitted to the PDU were provided with TA/coaching

Accomplished ahead of the deemed rating period

37 of 41

Target

% Accomplished

Variance

Remarks

Catch-Up Plan

100%

(1/1)

accomplishment in conducting one (1) seminar-orientation on Public-Private Partnership Code

100%

(1/1)

One (1) seminar-orientation on Public-Private Partnership Code conducted

0

Accomplished

100%

(1/1)

accomplishment in the conduct of one (1) write-shop on project development and networking principles and practices

100%

(1/1)

submission of one (1) policy recommendation relevant to PDO and/or PDSO practices

400%

(4/1)

Four policy relevant to PDO and/or PDSO practices recommended

300% (+3)

Above Target

100%

attendance and participation in policy-making activities (i.e. Administrative Council Meeting)

400%

(4/1)

Participated in one (3) policy-making activities (i.e. Administrative Council Meeting)

300% (+3)

Above Target

100%

(1/1)

accomplishment in the conduct of one (1) writeshop on the drafting of University Partnership Policy

100%

(4/4)

accomplishment in engagement with four (4) potential funding partners (government or private, local or international)

100%

(4/4)

Four (4) potential funding partners (government or private, local or international), engaged

0

Accomplished

38 of 41

SUMMARY OF PERFORMANCE

PROJECT DEVELOPMENT UNIT

TOTAL NO. OF TARGETS

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

16

10

1

5

62.50%

6.25%

31.25%

39 of 41

SUPPORT NEEDED

PDU

  • Allotment of fund for the Writeshop for the Crafting of the University Partnership Policy
  • Physical Office dedicated for the Project Development Unit which can also house the ETEEAP Center and its Staff
  • Support by the Extension Services Office to fund the Writeshop on Project Development as agreed by both Office Heads

40 of 41

SUMMARY OF PERFORMANCE

OFFICE OF THE UNIVERSITY PRESIDENT

OFFICE

MET

(Targets within the rating period that were accomplished.)

UNMET

(Targets within the period that were NOT accomplished.)

Not Applicable

for this Rating Period

(Targets that fall in the 3rd and 4th Quarters)

TOTAL NO. OF TARGETS

LEGAL UNIT

5

1

5

11

INTERNATIONAL AFFAIRS OFFICE

11

0

7

18

INTERNAL AUDIT UNIT

9

2

9

20

PLANNING OFFICE

10

0

9

19

GSIPMO

17

8

4

29

PROJECT DEVELOPMENT UNIT

10

1

5

16

TOTAL

62

12

39

113

OVERALL PERCENTAGE

54.87%

10.62%

34.51%

100.00%

41 of 41

THANK YOU!