1 of 13

The Social and Environmental Impacts of Data Centres

Rory Murphy and Professor Sarah Hartley

Centre for Responsible Innovation

September 2026

2 of 13

Our research

2

Report focus

  • AI Growth Zones and UK policy context
  • Evidence review of energy, water, minerals, and place impacts
  • International case studies
  • Analysis of UK data centre approval in Lincolnshire
  • Policy recommendations

​

​

​

Research Question: How can data centre growth in the UK be managed in ways that simultaneously support digital development, energy security, water resilience, decarbonisation, mineral sustainability and environmental justice? 

3 of 13

Data centre overview

3

​

Warehouse facilities to store and operate computer systems, including networking and data storage, to enable processing for cloud and AI computing

​

  • Viewed as essential for economic competitiveness, national security, and technological sovereignty

​

  • UK Compute Roadmap, AI Opportunities Action Plan and AI Growth Zones

​

  • Estimated 450-550+ in the UK

​

  • Energy, water, mineral and land demands raise social and environmental justice concerns – largely unexamined

​

​

​

​

​

​

4 of 13

Energy impacts

4

Pressure on electricity infrastructure

​

​

Decarbonisation and emissions challenges

​

​

Potential increase to consumer bills

​

​

Monitoring, disclosure and governance frameworks are underdeveloped

​

​

​

5 of 13

Water impacts

Water demand is poorly understood

​

Monitoring, disclosure, and impact assessment is insufficient

​

Priority supply may deplete local community drinking water

​

Water depletion and wastewater emission can generate ecosystem harms

​

Indirect demand can outweigh direct water use

​

6 of 13

Mineral impacts

6

Data centres require critical and essential minerals

​

Socio-environmental impacts are often concentrated in Global South

​

Extraction, refining and disposal of minerals and e-waste create localised harms

​

Mineral impacts absent from sustainability assessments

​

7 of 13

Nature/place impacts

Biodiversity impacts from land loss

​

​

Community and ecology restriction from land-use lock-in

​

​

Noise, heat and fossil fuel pollution create local and global harms

8 of 13

Elsham Tech Park – UK public perceptions

Background

​

  • UK’s largest ever data centre (1 GW), complementing Lincolnshire AI Growth Zone bid - 435 acres - roughly 300 football pitches

​

  • Approved on March 11th 2026, following two consultations generating 438 public comments

​

​

Findings

​

  • First data on UK public engagement around data centres

​

  • Significant problems with process of engagement

​

  • No Environmental Impact Assessment (EIA)

​

Public views

​

  • Concern over high water demand from assumed evaporative cooling

​

​

  • Fears over amplified Lincolnshire water stress

​

​

  • Concern at absence of sustainable energy strategy

​

​

​

​

9 of 13

Elsham Tech Park – UK public perceptions

Public views

​

  • Anger at fossil fuel reliance, increased carbon emissions and planetary harm

​

​

  • Perceived conflict with existing decarbonisation and net zero commitments

​

​

  • Fears over disruption to place identity and agricultural livelihood

​

10 of 13

Lessons learned

Publics are engaged, but impact is limited

​

Meaningful transparency and documentation are essential

​

Direct resource consumption and carbon emissions are major concerns

​

Concerns are contextualised at local, national and planetary levels

​

Data centre opposition was often conditional, not fixed

​

​

11 of 13

UK data centre knowledge gaps

Future AI infrastructure demand and need

​

​

Cumulative socio-environmental impacts

​

​

Resource consumption and infrastructure

​

​

Carbon emissions and decarbonisation impacts

​

​

Governance, transparency and accountability

​

12 of 13

What kind of AI infrastructure do we want, where should it go, and under what conditions?

  1. Govern

Create cross-government coordination and a National Sustainable Data Centre Strategy

​

2. Engage�Embed environmental and social justice into AI policy, supported by public participation

​

3. Measure�Mandate data centre environmental reporting and establish a National Data Centre Observatory

​

4. Plan

Incorporate AI infrastructure into long-term energy and water planning, supporting forecasting with cumulative environmental assessments

​

5. Regulate �Recognise data centres as a distinct infrastructure category and establish minimum environmental performance standards

​

13 of 13

International case studies

Facebook Data Centre (Clonee, Ireland)

Microsoft Agriport (Middenmeer, Netherlands)

Colón Industrial Park (Querétaro, Mexico)

Ireland

Anger at cheaper energy pricing for data centre operators

​

Data centre energy demand diverted renewables

​

Data centres proposed as energy grid contributors

Netherlands

Municipal executives negotiated deals without public scrutiny

​

Actual water use far exceeded developer projections

​

Local anger developed into national outcry

Mexico

Unjust Indigenous and communal land loss

​

Facilities exempted from environmental impact assessments

​

Depletion of local community water supply

​

​

​

​

US

Indirect water use vastly exceeds operational use

​

Cooling demands peak when drought is worst

​

Data centre energy demand justified fossil fuel use

​

​

​

​

Meta Mesa Data Centre (Phoenix, Arizona)