Engineering Project Management
Instructor: Angelo Mago
I.D. #99003
Course Objectives
By the end of this course you will be able to:
Seminar Modules
1.
2.
3.
4.
5.
3
Seminar Modules
6
7.
4
MODULE 1: PM OVERVIEW & INTRODUCTION
Sources of Project Variability?
Outside the control of PM
Within the control of PM
WHY
6
Issues facing the Project Manager
Within the control of PE
WHY
7
Additional Issues facing a Product Manager
WHY
8
The Constraint Triangle
Project Managers are constantly balancing both Customer requirements and organizational influences (EEF) against constraints. The traditional expression of these constraints is:
Time
Performance
Cost
The Statement of Work (SOW) should identify and document these influences, constraints and assumptions.
As these factors can often be outside the control of the Project team, communication of these issues to the project stakeholders (customer, sponsors, etc.) is essential.
WHY
9
The Updated Constraint Triangle
A new expression for project constraint, which places focus more squarely on benefit and value is proposed by Angelo Baratta* and is shown as:
Capability
Value
Scope
Baratta states that the value delivered is a function of the scope of the project opportunity and the capability of the process used to deliver it. Expressed in equation form
Value = ƒ(scope, capability)
This better aligns with the idea of value creation presented in the new PMBOK, with a focus on developing technology and processing capabilities within the organization which provide improved benefit to their customers.
WHY
10
What is a Project?
pg 4
Projects :
WHAT
11
Project Management as Risk Management
a combination of constraint and uncertainty
WHAT
12
Knowledge Areas of TPM
The PM Body of Knowledge defines 10 areas, each of which must be managed to ensure project success.
WHAT
Pg 25
For this course we will only cover the areas highlighted in RED.
13
How Much Project Management Do I Need?
Application of PM should be appropriate to:
14
Differentiating Project, Program, and Line Management
Pg 11
WHO
15
Competencies of a �Successful Project Manager
KNOWLEDGE
Pg 56
PERFORMANCE
PERSONAL
WHO
16
Typical Project Management Models
17
Agile (SCRUM ) Delivery Model
Agile is a blanket term for many frameworks or approaches to non-traditional PM.
Agile is especially useful for high uncertainty projects such as exploratory or ER&D as opposed to definable work such as carry-over product development.
Most Agile frameworks consist of the following elements:
18
SPRINT BACKLOG
OUTPUT
DAILY TEAM MEETINGS
SPRINTS
1-4 WEEKS
24 HRS
Example of a SCRUM Model
Scope validated between customer and Product Owner
PRODUCTBACKLOG
19
Differentiating Between Project Management Models
20
CRITERIA | + | - |
Changing or evolving requirements | AGILE | TPM |
Customer is very involved | AGILE | TPM |
Organizational Structure not well defined | AGILE | TPM |
Personnel availability dedicated to Project | AGILE | TPM |
PM teams and staff are local | AGILE | TPM |
Product deadline date is mandated | TPM | AGILE |
Experience with required technology | TPM or AGILE | |
Formal documentation is important | TPM | AGILE |
PM Life Cycles
The application of Project Management involves understanding 3 distinct and nested life cycle processes:
Product
Project
Project Management
21
Product Life Cycle
Product
Project
Project Management
22
All products go through5 Phases from Concept through End of Useful Life which include:
R&D efforts
Useful Life
Market Decline
Design Freeze
Product Life Cycle
23
Project Life Cycle
Product
Project
Project Management
24
Pg. 38
Types of Project Life Cycles
25
LINEAR (TRADITIONAL) MODEL
PHASES
26
Source: DOD 5002.R
Linear Example 1 - DOD PRODUCT LIFE CYCLE
27
Linear Example 2 - AUTOMOTIVE (APQP)
28
V – MODEL of PROJECT DEVELOPMENT
for
SYSTEMS
29
DEFINE
DESIGN
VERIFY
LAUNCH
Component
Sub-system Level
System Level
Vehicle Level
Target Cascade
Design Verification
KO
PS1/2
SI
SC
PH
PA
PR
CC
LR
LS
J1
ST
CP
FORD FPDS as an example of V – MODEL
30
WATERFALL MODEL FOR
SOFTWARE DEVELOPMENT LIFE CYCLE
Gather Requirements
Systems Analysis
Coding
Testing
Implementation
Software Design
Operations & Updates
Disposition
Feasibility Study
SDLC
Integration
31
EVOLUTIONARY (SPIRAL) MODEL
The Spiral model combines features of the Waterfall and the incremental prototype approach.
In this model the radial distance is a measure of effort expended, while the angular distance represents progress made.
Source: DOD Systems Engineering Handbook
32
Project Phase Characteristics
Each Project Phase has the following common characteristics:
The Design and Phase Reviews serve to evaluate the achievement of project and product characteristics established by the contract and the project plan.
33
Project Management Life Cycle
Product
Project
Project Management
34
Project Boundaries
Project Initiator/ Sponsor
Project Inputs
Project Deliverables
Project Records
End
Users
Process Assets
Monitoring & Controlling Processes
Planning Processes
Executing Processes
Initiating Processes
Closing Processes
Fig. 3-4 pg. 54
Outputs
Project Management Life Cycle
35
Project Level of Activity� Grouped by Process Area
36
EXERCISE 1:
PROJECT FAMILIARIZATION
&
AND INITIAL PROJECT RISK ASSESSMENT
Exercise – 1�Project Familiarization and Initial Risk Assessment
1. FOCUS - Your company is embarking on a new project. The project focuses on supplying a next generation product to the customer GOCAR.
2. TIMING – Prior to contract award
a) Review the following documents:
b) Using the data above and the 2 slides entitled “Typical issues facing the PRODUCT and PROJECT Manager” as a guide, complete the Team Feasibility Commitment form (TFC) located in the PMP EXCEL file.
38
MODULE 2:
ESTABLISHING PROJECT SYSTEM SUPPORT
STAKEHOLDER MANAGEMENT
Plan Stakeholder Management
41
Stakeholders/Sponsors
42
For successful projects, it's not enough to deliver on the customer's demand; projects have to address all Stakeholder and Sponsor expectations.
Identifying and differentiating stakeholders and sponsors is essential first step since many of the important decisions are made by these stakeholders.
Stakeholders:
Sponsors (often called “champions”):
Stakeholder Management Techniques
Several techniques common to PMBOK are:
43
Stakeholder Register
44
Example of a Stakeholder Register
STAKEHOLDER REGISTER | |||||
INFORMATION | SWOT ANALYSIS | ||||
Name | Project Role | Team Expectations | Strengths | Weakness | Opportunities |
Barbara French | VPO | Provide personnel and financial resources during the project | | | |
Carl Gross | Plant Manager | Better working relationship with Engineering | | | |
GOCAR | Customer | Timely communication and approval of Design and Manufacturing changes when required | | | |
TBD | Lead Eng | Responsible to lead all engineering design decisions and serve as liaison with Customer | | | |
Budzey | Material supplier | Partner supplier in R&D efforts to develop new materials | | | |
Bob Carmen | Director of Eng | Project Sponsor - Provide personnel resources during the project | | | |
45
Manage/Control Stakeholders
Power/Interest Grid or Power/Influence Grid
46
Example of a Stakeholder Power/Interest Grid
|
|
|
| ||
| ||
| ||
| ||
| ||
| ||
| ||
| ||
| ||
|
|
|
| ||
| ||
| ||
| ||
| ||
| ||
| ||
| ||
| ||
LOW | | |
| |
Keep Satisfied
Keep Informed
Manage Closely
Monitor
ENG
VPO
Supplier
TEST
MFG
POWER
INTEREST
Pg. 397
47
EXERCISE 2:
ASSESSMENT OF PROJECT STAKEHOLDERS
EXERCISE 2 Assessment of Stakeholders
49
PROJECT INTEGRATION
Project Integration
The identification of project requirements, business need, project risks, and resource requirements.
Involves setting up systems and processes (OPAs) to address outside and uncontrollable influences to the project (EEFs).
Pg. 63
Knowledge Area 4
51
External Project Influences
All project are influenced by factors that are outside of the control of the Project Team and must be addressed in the Project Management Plan.
PMBOK refers to these as Environmental Enterprise Factors and defines this term as:
EEFs can have positive or negative impacts on a project and must be identified by the project team to develop strategies to mitigate the risks presented by these factors.
Pg. 29
52
Enterprise Environmental Factors (EEF)
Pg. 29
53
Organizational Process Assets (OPA)
Organizational Process Assets help address Environmental Enterprise (Organizational) influences typically consist Organization-specific categories such as:
Project Integration
Pg. 27
54
Project Management Plan – Automotive Specific
A Mobility Project Management Plan consists of elements and documents specific to the Mobility Industry such as:
55
1) Lessons Learned Register
Managing (corporate) knowledge involves not just a process to collect historical information, but also involves:
OPA
These management systems do not need to be overly complex but should use a platform that is appropriate to the size of the organization and the complexity of the projects being undertaken.
Also these knowledge databases should be structured so that information can be easily updated when new information becomes available. An example of a typical Mobility register is shown on the next page.
56
TGR/TGW REPORT (Sample) | |||||||
Category | Status | Deficiencies | Recovery Plan | Due Date | Responsible Person | ||
| RED | YEL | GRN |
|
|
|
|
Product Readiness | x |
|
| DVP&R interim approvals issued for : | DVP&R issues undergoing investigation. 100% sorting in place as interim action. New rubber material trials to address BSR. | Oct-16 | Eng. Manager |
Material Strength of Barrel/Head | |||||||
BSR problems at Pilot trials | |||||||
Flashlights failed Corrosion testing | |||||||
Process Planning Readiness | x |
|
| Process Capability too low for barrel machining operation. CpK = 1.60 vs. required = 1.8 | Low process capability due to tooling issues. Dies have been reworked however Stamping Press unable to maintain consistent Process Capability. Press replacement scheduled for 2015. | Sep-16 | Eng. Manager |
Production Planning Readiness |
|
| x | No Issues |
| Feb-17 |
|
Measurement & Testing Systems Readiness | x |
|
| CMM equipment under repair. CMM fixtures did not meet GRR 20% requirement. | CMM Repair PO submitted and to be completed 9/99. FORD to waive GRR requirement to 25% for Pilot. | May-17 | Quality Manager |
GRR for gages is greater than 20%. | Waiver issued to use current gages. QM to have gages reworked by gage vendor. | Jan-17 | Quality Manager | ||||
Sub-Supplier Readiness | x |
|
| Late Deliveries for both O-rings and bulbs | Supplier Quality Manual to be updated to reflect more stringent delivery requirements. | Apr-17 | Purchasing |
Material Handling Readiness |
|
| x | No Issues |
|
|
|
Personnel Readiness |
| x |
| PPAP documents quality poor, e.g. FMEA and Control Plan. Ineffective APQP processes. | Training delayed due to budgets cuts in HR. | Nov-16 | HR |
Quality System Readiness | x |
|
| Plating flaking on barrel | Waiver issued based on 200% sorting. SQA to conduct on-site audit at Crescent Lake Paints. | Oct-16 | Quality Manager |
PSW Readiness | x |
|
| 6 Interim PPAP Approvals issued based on issues listed above. | Program Review scheduled with FORD STAs and ENG. | Dec-16 | Quality Manager |
57
Governing Standards�for �Mobility�Product Development
2nd Edition
5th Edition
IATF-16949
3) Policies and Procedures
58
Project Integration establishes the systems and databases necessary for project success such as:
PRODUCT
Typical Product & Project Level
Policies and Procedures
OPA
PROJECT
59
Mobility –Specific OPA procedures
The following have a unique approach in the Automotive Industry:
60
Best Practice as Knowledge Management
Knowledge Management seeks to make the best use of the data that is available to an organization, leading to Best Practices throughout the organization.
This requires a distinction to be made between information, data, and knowledge:
61
4) Change Management� AKA: Configuration Management
Definition: The control and recording of changes made to a product throughout its Project Life Cycle with respect to the product’s hardware, software, and related documentation.
An effective change control system contains the following features:
pg 94
62
5) Communication Planning
Today’s rapidly-changing customer environment requires organizations to not only respond quickly but also to communicate effectively across internal and external channels.
PMBOK presents several dimensions to consider in the Communications Planning process: (Section 10.1.2, pg 291)
These typically are documented in a Communications Management Plan (CMP).
63
MODULE 3: SCOPE PLANNING
Project Scope
5 sub-processes
Key Output - Development of the Scope of Work
Knowledge Area 5
Pg. 105
65
Generic Steps of Project Scope Development
Task
Deliverable Document(s)
Identify VOC and Contract Type
Translate VOC into Requirements document(s)
Establish project objectives and outline project tasks via WBS
Create Sub-Project, and Design/ Phase Review schedules from MTS
Org Structure and RASIC
Monitor Project Cost or Man-hour usage through EVA reporting
Engineering Change Management
66
1. Scope Definition - Capturing VOC
There are seven (7) levels of VOC which the Project team must evaluate.
Although each project will not necessarily have each voice, each should be evaluated to determine its applicability to the project.
67
1. Scope Definition - Capturing VOC
Voice of the Customer (VOC) must be identified, organized, analyzed, and evaluated to determine what needs to be included ( and not included) in the Project Scope within the imitations of the project resources.
VOC Identification techniques:
VOC Analysis techniques:
68
REQUIREMENTS COORELATION AND TRACEABILITY MATRIX | |||||||||||
Project Name: | High Intensity Flashlight |
| |||||||||
Project File No. | DX-777 | ||||||||||
Customer | GOCAR | ||||||||||
Project Manager |
| ||||||||||
ID | Reference Document(s) | Technical Assumption(s)�and/or Customer Need(s) | Design Responsibility | Functional�Requirement | Threshold Value | Technical�Specification | Applicable System�Component(s) | Software�Module(s) | Test Requirements | Verification Test | Additional�Comments |
| ESOW 4.1.2 |
|
| Craftsmanship Requirements |
|
|
|
|
|
|
|
|
|
| CO | BSR/NVH | Minimum |
|
|
| BSR Profile test | GOCAR PC-8889 |
|
|
|
| C | Fit and Finish (see Appendix A) | Appendix A |
|
|
| Corrosion Test Procedures for Painted Automotive Parts | SAE J1563 |
|
|
|
| C | Surface Finish | Brightstar DX777 |
|
|
|
|
|
|
|
|
| C | Color Harmony | TBD |
|
|
| Munsen Color plates | AAR |
|
|
|
| C | Styling | TBD |
|
|
| Vehicle Build Trial | TBD |
|
|
|
| CO | The following product features must allow for ease of use | TBD |
|
|
| Vehicle Build Trial | TBD |
|
|
|
|
| a) Switch Mechanism |
| Brightstar DX777 |
|
|
|
|
|
|
|
|
| b) Bulb Replacement |
| Brightstar DX777 |
|
|
|
|
|
|
|
|
| c) Beam Adjustment |
| Brightstar DX777 |
|
|
|
|
|
|
|
|
| Performance |
|
|
|
|
|
|
|
|
|
| C | Beam Distance | 261 m | ANSI/NEMA FL 1-2009 |
|
|
|
|
|
|
|
| C | Peak Beam Intensity | 17000 cd |
|
|
|
|
| |
|
|
| C | Run Time | 2 hrs |
|
|
|
|
| |
|
|
| C | Light Output | 180 lumens |
|
|
|
|
|
Sample Requirements & Traceability Matrix
69
Competitive Technical Assessment
Goals and Targets
Warranty
Regulatory Issues
Co-Relationships
Column Weights
QFD Matrix Worksheet
Customer
Reqt’s
Technical
Reqt’s
Competitive Evaluations
Complaints
70
Waterfall (Phased) Deployment of QFD
Customer Requirements
System Level Requirement Matrix
SLRM
Product Characteristics Matrix
PCM
Manufacturing/Supplier
Matrix
MSM
QC Matrix
71
Affinity Diagram for Travel Mug
AFFINITY DIAGRAM | ||||||
Next Generation Travel Mug | ||||||
| | | | | | |
Quality Appeal | | Ergonomics | | Features/Capabilities | | Performance |
| | | | | | |
Stylish | | Easy to drink from without looking | | Easy to clean | | Keeps drink hot for a reasonable time |
| | | | | | |
Sleek design | | Easy to hold in all conditions | | Easy to remove lid | | Durable |
| | | | | | |
Feels like a quality product | | Balanced feel | | Dishwasher safe | | Keeps drink cold for a reasonable time |
| | | | | | |
Value | | Not too heavy | | No "sweating" | | Spill-proof |
| | | | | | |
Reasonably priced | | | | | | Safe to use |
| | | | | | |
Reliable | | | | | | |
72
Prioritization Diagram for Travel Mug
73
2. Scope Planning
Within the Mobility Industry, product development can take two discrete paths, each of which has a unique approach to scope planning:
New Product Development:
Carry-Over Product Development:
74
Process Decision Program Chart (PDPC)
A PDPC is one of the 7M techniques and is useful for systematically identifying what might go wrong with a plan. Countermeasures are developed to prevent or offset those problems.
Different shapes within the hierarchy are used to highlight risks and identify possible countermeasures (often shown as 'clouds' to indicate uncertainty).
The PDPC is similar to the FMEA in that both identify risks, consequences of failure, risk rating, and recommended actions.
The PDPC extends the levels of the Tree Diagram levels further to identify risks and countermeasures.
Objective
Solutions
Constraints
Countermeasures
75
2. Scope Planning Flowchart
SOR
SOW
WBS
Phase Reviews
Design Reviews
PDS
Cost Tracking
Contract
TGR/TGW
ECMS
DV/PV Testing
76
Statement of Requirement (SOR)
Details the PRODUCT performance requirements.
Often times in Automotive, these documents are combined to form what is termed an
Engineering Statement of Work (ESOW)
PRODUCT & PROJECT DOCUMENTS
Statement of Work (SOW)
Details the PROJECT performance requirements.
77
Statement of Requirements (SOR)
Product Performance document which:
If the SOR is not written in the Organization’s technical language then there is the intermediate step of translation into a PDS (Product Definition Specification)
Documenting VOC
78
Statement of Work (SOW)
Project performance document which:
79
Terms Specific to SOR/SOW
80
EXERCISE 3:
REQUIREMENTS & TRACEABILITY MATRIX
(RTM)
EXERCISE 3 RT Matrix
82
WORK BREAKDOWN STRUCTURE
(WBS)
Work Breakdown Structure (WBS)
What is it?
pg 125
84
Work Breakdown Structure (WBS)
How Does it Work?
85
Simple WBS Structure – Graphic Model
Flashlight
Assembly
Endcap
Assembly
Barrel
Assembly
Head
Assembly
Switch
Assembly
Barrel
Grip
Level 1
Level 3
Level 2
86
WBS – MS Project
WBS
Elements
87
Work Breakdown Structure (WBS)
Types
88
Examples of Major WBS Types
Flashlight
Assembly
Production
Engineering
Quality
Train on
Unigraphics
Design Barrel
Conduct Switch
Design Simulations
Level 1
Level 3
Level 2
Product
Organizational
Flashlight
Assembly
Endcap
Assembly
Barrel
Assembly
Head
Assembly
Switch
Assembly
Barrel
Grip
89
EXERCISE 4:
CONSTRUCTING THE WBS
EXERCISE 5 WBS Roll-up APQP – Program Approval
91
MODULE 4:
Quality Management
3 sub-processes
Key Output – Robust Design that can be economically manufactured
Knowledge Area 8
Pg. 227
93
Quality Planning
Quality Planning involves identifying which quality standards are relevant to the project and determining the best approach to achieve the project objectives.
Each industry has a specific QM system that they use for their daily ongoing processes, such as engineering, production, purchasing, HR, etc.
Examples of common QM systems are:
94
Quality Planning
If the determination is made that the organizational QMS cannot manage the risks presented by the customer’s request then PM is necessary.
Quality Planning also involves identifying which New Product Development process (NPD) the project team will use.
In addition to the QM system, a company which is design responsible has an NPD* process for managing projects outside the capability of the company QMS.
For the Mobility industry the base model is the AIAG 5-Phase APQP
95
ROBUST DESIGN
A method which is aimed at:
reducing a product’s sensitivity to external NOISE.
This “noise” is expressed in engineering terms as variation.
96
ROBUST DESIGN CONCEPTS
Sources of uncontrollable variations are:
97
Robust Design Methodology�RDM
* Taguchi's Robust Design methods were introduced to Ford Motor Co. in the early 1980’s
98
ROBUSTNESS METHODS & TECHNIQUES
There are several analytical methods that work together to aid the design team in organizing the mass of VOC data.
This helps the design team differentiate between major and minor concerns and prioritize product improvements.
Some of the more essential techniques are:
99
Design for Service
Design for Manufacture
Design for Safety
Design for Commonality
Design for Reliability
Design for Environment
Design
to Cost
Design for Assembly
DFX
DFX as a Robustness Strategy
Notice that each method is only a PORTION of the total DFSS process
100
Parameter (P)-Diagram
101
Now that the boundaries and interfaces are properly understood by the FMEA team, the P-Diagram can be created to identify the INPUTs, noise factors, control factors, required OUTPUTs and error states as associated with the established function(s)*.
Sources for this include:
101
Parameter (P)-Diagram
PRODUCT SYSTEM
Noise Factors
Input Signals
Controllable Factors
Output Signals or Response
Error States
102
103
According to the book, FMEA with Robustness Linkages by FORD, a system interface matrix is defined as:
“an illustration of the relationships between the subsystems, assemblies, subassemblies, and components within the
object [design] as well as the interfaces with the neighboring systems and environments.
A system interface matrix documents details such as types of interfaces, strength/importance of interface, and potential effect of interface.”
An Interface Matrix plots four primary relationships or interface on both the vertical and horizontal axes and is used in preparation for a System or Design FMEA.
Interface Matrix
104
Interface Defined
An interface is the point or surface where two components or subsystems meet.
There are 4 primary types of Interfaces:
Since interfaces can contain up to 50% or more of the total failure modes, it is essential part of a FMEA analysis.
INTERFACE MATRIX
Example of an Systems Interface Matrix
105
The FMEA, is primarily a Risk Assessment method which asks the following questions:
Failure Mode
Effect and Severity
Occurrence
Design Control
RPN
FMEA
106
107
Function/Requirements
Failure Modes
Effects
Causes/Mechanisms
RPN/SO/CM
Recommended Actions
Goals of a Design FMEA:
FMEA Field:
FMEA
Types
There are various types of FMEAs used in industry today, therefore FMEAs can be divided into categories and types as follows:
Categories
Design for Manufacture and Assembly (DFMA)
Defined as the process of :
109
DFM and DFA
DFM Considerations
DFA Considerations
Figure 1-4 Producability Handbook pg 28
110
DFM�Design for Ease of Manufacture
Design improvements for ease of manufacturing can be divided into three (3) major parameters.
111
DFA�Design For Assembly
Improvement of assembly methods can be divided into three (3) major groups.
112
Comparing B-D and Lucas Methods
These two methods are the most widely used in industry and are based on a "point scale" which gives a relative measure of assembly difficulty. Although both methods are similar in approach the Lucas method has the prelimianry step of the “quick” analysis of DFM efficiency.
Lucas
Boothroyd-Dewhurst
113
Lucas Assembly Worksheet | | | | | | | | | | | | | |||||||||
COMPONENT | QTY | Essential | NON Ess | Handling Analysis = Ah + [Σ P0 + Σ Pg] | H | Fitting (Insertion) Analysis = Af + [ΣPf + Σ Pa] | F | Line Total | Cma = C1 * (H + F) | ||||||||||||
Ah | P01 | P02 | Pg | Σ Po | Af | Pa | Pf1 | Pf2 | Pf3 | Pf4 | Pf5 | Pf6 | Σ Pf | Cma ($) | |||||||
Fuel pump | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $20.21/hr |
Canister, plastic | 1 |
| 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Separator shafts | 3 | 2 | 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Shaft spring | 3 | 2 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Seal, Top, Fuel Pump | 1 |
| 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Seal, Bottom Fuel Pump | 1 |
| 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Cap, top, plastic | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Fuel Indicator Gage assembly | 1 | 1 |
|
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Electrical connector, black | 1 |
|
|
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Electrical connector, white | 1 | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Wiring harness, FP to vehicle | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Wire, Fuel indicator Gage | 1 |
| 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Hose, Fuel interlink | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Seal, pump to Fuel Tank | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Hangar | 1 | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| $0.0000 |
Float | 1 | 1 | 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
|
|
|
|
|
Retainer, washer, Float | 1 |
| 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Wiring, Fuel pump to connector | 1 | 1 | 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
Zip clip (wiring FP to connector) | 1 |
| 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Filter screens | 2 | 1 | 1 |
|
|
|
| 0 | 0 |
|
|
|
|
|
|
|
| 0 | 0 | 0 | $0.0000 |
|
| $0.0000 |
Assembly Name | A |
| B | C | D | E | F | | | |
Component | Times Op Performed | Part Count | Handling Code | Handling time/part | Installation Code | Installation time/part | TOTAL Operation Time (sec) | Elimination?�Yes=0;� No=Min # parts | Comments/Design Improvements | |
|
|
|
|
|
|
| | Part count Min |
| |
|
|
|
|
|
|
| |
|
| |
Fuel pump |
| 1 |
|
|
|
|
| 1 |
| |
Canister, plastic |
| 1 |
|
|
|
|
|
|
| |
Separator shafts |
| 3 |
|
|
|
|
| 2 |
| |
Shaft spring |
| 3 |
|
|
|
|
| 2 |
| |
Seal, Top, Fuel Pump |
| 1 |
|
|
|
|
|
|
| |
Seal, Bottom Fuel Pump |
| 1 |
|
|
|
|
|
|
| |
Cap, top, plastic |
| 1 |
|
|
|
|
| 1 |
| |
Fuel Indicator Gage subassembly |
| 1 |
|
|
|
|
| 1 |
| |
Electrical connector, black |
| 1 |
|
|
|
|
|
|
| |
Electrical connector, white |
| 1 |
|
|
|
|
| 1 |
| |
Wiring harness, FP to vehicle |
| 1 |
|
|
|
|
|
|
| |
Wire, Fuel indicator Gage |
| 1 |
|
|
|
|
| 1 |
| |
Hose, Fuel interlink |
| 1 |
|
|
|
|
| 1 |
| |
Seal, pump to Fuel Tank |
| 1 |
|
|
|
|
| 1 |
| |
Hangar |
| 1 |
|
|
|
|
| 1 |
| |
Float |
| 1 |
|
|
|
|
| 1 |
| |
Retainer Washer. Float |
| 1 |
|
|
|
|
|
|
| |
Wiring, Fuel pump to connector |
| 1 |
|
|
|
|
| 1 |
| |
Zip clip (wiring FP to connector) |
|
|
|
|
|
|
|
|
| |
Filter screens |
| 2 |
|
|
|
|
| 1 |
| |
|
| |
|
|
| tma = | 0 | 15 | Design Eff (η) = |
|
Boothroyd-Dewhurst Assembly Worksheet
114
EXERCISE 5:
COMPLETING A PARAMETER DIAGRAM
EXERCISE 6 Parameter Diagramming
116
Special Characteristic System
Most Automotive OEMs will identify a particular set of performance or dimensional product characteristics as those items that the customer has identified as requiring “special care”.
Special (or Key) Characteristics are those which historically have been, or have the potential to be, sensitive to design constraints or process variations under the current technology.
These special characteristics must appear on the following APQP documents:
117
Special Characteristic System (SC)
The SC System breaks product and process characteristics into three categories:
Each OEM typically uses their own system of identifying SC on drawings and specifications.
118
Special Characteristic System (SC)
Acceptable Types of Controls �for Special Characteristics (SC)
The following indicate some of the techniques that are acceptable to avoid shipment of non-conforming product to the customer if identified as an SC:
119
THE DESIGN REVIEW PROCESS
Design Review Process
121
Design Review IS – IS NOT
122
Design Reviews and Product Liability
Lesson: Use Design Reviews to catch and correct errors early
123
Verification
RASI
Design Reviews
Risk Criteria
Information Collection
Training
Risk Assessment Methods
Scope Development
RMP
DR is part of a Complete Risk Management Strategy
Notice that Design reviews are only a PORTION of the total RMP package
124
Categories of Design Reviews
125
* Also known as GATE reviews
The Peer Review
126
What: an in-depth critique of assumptions, calculations, alternate interpretations, methodology, and acceptance criteria employed, and of conclusions drawn from the original scope. Peer reviews confirm the adequacy of the work and are informal, smaller meetings.
Who: Peer reviews are typically conducted by persons having technical expertise in the subject matter to be reviewed to a degree at least equivalent to the project technical scope. At least some of the members of the peer review need to be independent of the project under review.
When: as required with no set schedule, although peer reviews are usually conducted in preparation for formal Design Reviews.
Focus: mainly on technical level issues at Design group level but can include resourcing challenges presented by the technical issues.
What: A formal and documented assessment of the design maturity of the project to verify compliance to predetermined requirements such as customer specifications, regulatory and industry standards and required technological, engineering, and industry practices in the areas of:
Who: Design Reviews are typically conducted by the project PDT and led by the Lead Design Engineer or Design Release Engineer to the functional (line) managers.
When: Design Reviews are regularly scheduled meetings, usually occurring on a set cyclic schedule.
Focus: The formal Design Review focuses on the product readiness for either prototype verification or production validation.
127
The Design Review
What: A formal and documented assessment of the risks of the project in the areas of:
Who: Design Reviews are typically conducted by the project PDT, led by the Project Manager, to (executive level) project sponsors.
When: Phase Reviews are regularly scheduled meetings aligned with established customer or organizational milestones.
Focus: The Phase Review focuses on decisions that need to be made regarding the project readiness to proceed to the next phase in the areas of:
128
The Phase Review
What: A formal and documented strategic level assessment of all currently active organizational projects with regards to their:
Who: Executive Reviews are typically led by the Project Manager of each project presenting to (executive level) project sponsors.
When: Executive Reviews are typically conducted quarterly.
Focus: The Executive Review focuses on decisions that need to be made regarding the project health and viability to the overall organizational strategy in the areas of:
129
The Executive Review
130
Base Document
Typical Design Review Process
Design Review
Phase Review
Product
Project
Product Specification
SOR
Project Specification
SOW-WBS
Tied to Project Milestones
Regular schedule (weekly-biweekly)
Graphic Relationship of DR within NPD
Focus
TECHNICAL Design Reviews
Essential
Additional
Refer to Appendix C for DR task sheets that outline typical agenda items for each of these DRs
131
Additional Reviews
Project (Phase) Reviews
Technical (Design)Reviews
132
Technical reviews Overlaid onto APQP Timing
Concept Exploration
Concept Approval
Program Approval
Prototype
Pilot
Launch
Operation & Support
Concept Exploration & Initial Technical Development
System Design & Demonstration
System – Component Product Verification
Full Scale Production and
Deployment
SRR
PAO
PDR
CDR
PRR
IPR
SSR
TRR
MODULE 5
SCHEDULE MANAGEMENT
Plan Schedule Management
5 sub-processes
Key Output - Development of the Project Timeline
Knowledge Area 6
Pg. 141
134
Why Time Management?
Time management is one of the triple threats of Project Management.
And most important, Time is the one resource that, when expended, cannot be recovered.
Proper Time Management requires and understanding and application of several things:
Time
Performance
Cost
135
Personal Time Management
One study cited in Business News daily cited the following as the top reasons of poor time management
Time
Performance
Cost
136
Personal Time Management
In the mobility industry today, the vast majority of companies do not have a dedicated Project Manager and require that the lead engineer serve as both engineer and manager.
This transition is often difficult for the typical engineer as PM skills are not well developed in the Engineering curriculum.
For this reason, organizations need to seriously consider a baseline education for entry-level project manager candidates and mentoring programs for new project managers.
Time
Performance
Cost
137
Personal Time Management
The following is a partial list of effective time management skills:
Time
Performance
Cost
138
Time Management of Project Teams
Like most commercial industries, the mobility industry, depends upon on-time delivery of their supplier’s product.
Thus, it is imperative that project manager, at both the OEM and supplier level are able to use apply Time Management methods to:
Time
Performance
Cost
139
The following are Time Scheduling methods typical in the mobility industry
Milestone Charts
Gantt Charts
Networks
Simplicity
Precision
Time
Performance
Cost
Project Scheduling Methods
140
Milestone Charts
A Milestone chart is not a valid schedule methodology since work at the Level of Effort level is not visible.
141
Gantt (Bar) Charts
*Such as task ID and duration.
142
Insert 3 slides on preparation of Gantt Chart
Example Gantt Chart – MS Project
143
Network Diagramming Methods
144
Precedence Diagram Method (PDM)
145
PRECEDENCE DIAGRAM
Use of a PRECEDENCE DIAGRAM can help visualize alternative assembly sequences which might not be immediately evident.
146
This is a simple PRECEDENCE DIAGRAM for the process of getting dressed
PERT and CPM
147
PERT and CPM Differences
148
PERT Calculation Table
For example purposes let’s use the following situation
PERT Time Calculation Example (using Beta Distribution) | ||||||
Activity | Activity Description | Predecessor | Duration Estimates (weeks) | PERT Time Estimate | ||
|
|
| Optimistic | Best case | Pessimistic | tE = (tO + 4*tBC + tP)/6 |
A | Develop Concept model | None | 3 | 4 | 4 | 3.8 |
B | Install UG Software | None | 1 | 2 | 3 | 2.0 |
C | Train Designers on UG | B | 1 | 1 | 1 | 1.0 |
D | Design Product on CAD | A,B,C | 7 | 10 | 12 | 9.8 |
E | Build prototypes for testing | D | 2 | 4 | 6 | 4.0 |
F | Conduct DV Testing on Prototypes | E | 1 | 2 | 3 | 2.0 |
G | Prepare and deliver final report | G | 1 | 1 | 1 | 1.0 |
149
Network Diagram - PERT
ES
LS
EF
LF
B
0
0
3
4
A
3
4
10
16
C
3
4
13
20
D
20
32
21
35
F
13
20
20
32
E
21
35
22
36
G
0
0
1
3
B
This is the PERT diagram for the previous example
150
Network Diagram - CPM
Node or Event
Activity Duration
Paths Path Length
1-2-5-7 2+5+4 = 11
1-3-4-5-7 1+3+2+4 = 10
1-3-6-7 1+1+6 = 8
Critical Path = Longest path = 11
Dotted line indicates “dummy” activity
151
Scheduling from Estimates - CPM
Or
152
Critical Path Definition and Advantages
Critical Path (CP) is the longest path through a network.
153
Important Scheduling Terms
Fast Tracking
Crashing
154
Other Scheduling Terms
155
EXERCISE 6:
CALCULATING CRITICAL PATH
&
CRASH COST ESTIMATION
EXERCISE 6 Calculating Critical Path APQP – Program Approval
157
MODULE 6:
Resource Management
6 sub-processes
Key Outputs
Knowledge Area 9
Pg. 255
159
What is Involved in Resource Planning?
160
Team Structure
What is the most effective structure for the project team and from where will the resources be acquired – Team Charter
Work Specialization
To what degree are the tasks broken out – WBS
Project Hierarchy
To whom do project team members report – RASIC
Span of Control
What is the manager to team member ratio?
Centralized and Decentralized Operations
What is the decision making authority and how are decisions made - RACI
Degree of Formalization
What are the documentation requirements for each of the project requirements – SOR/SOW, RMP, HRP, ECMS, CMP, and PPAP
Sample Questions for Resource Planning?
161
Communication Planning
Today’s rapidly-changing customer environment requires organizations to not only respond quickly but also to communicate effectively across internal and external channels.
PMBOK presents several dimensions to consider in the Communications Planning process: (Section 10.1.2, pg 369)
These typically are documented in a Communications Management Plan (CMP).
162
Issues facing Project Communication
Communications Management
Pg 290
Communication Process
Understanding the communication process (CP) is critical to developing communication planning and the CMP.
The 5 WHYS can help*:
b - WHO will provide the information necessary to be communicated.
165
Communication Process (cont)
The remaining 5 WHYS :
166
WHO : Managing Project Size�Communication Channels
No. of Cc = N(N-1)/2
167
Impact of Adding Team Members
3 Team members requires
3 Communication Channels
Cc = 3(3-1)/2 = 3
6 Team members requires
3 Communication Channels
Cc = 6(6-1)/2 = 15
Adding 3 persons TRIPLES the number of required communication channels!
168
WHAT: Communications Inputs
Project communication management requires several important input documents, (some of which were covered in previous sessions)
These inputs provide critical information and understanding between the organization and the project stakeholders and are necessary when developing key CMP documents.
Some of these inputs include:
WHAT: Communications Outputs
Project communication management uses various processes and documents (some of which will be covered in different sessions),
These provide critical links and information between all project stakeholders and are necessary to ensure timely and effective communications.
Some of these more critical outputs are listed below.
HOW: Communications Technology
One factor that influences project communication channels is the use of communications technology:
HOW: Communications Methods
Pg 295
TEAM FORMATION
AND
TEAM DYNAMICS
Organizational Planning and Structures
174
Traditional Hierarchal Structure
Program and Project Management occurs at the Functional Level
175
Matrix Structure – Weak
Each DRE assigned as Project Coordinator for a particular project
Program Management occurs at the Functional Level
176
Matrix Structure – Strong
Each Project Manager is managed by the Program Manager
177
Matrix Structure – Balanced
Each DE operates as Project Manager for a particular project
Program Management occurs at the Functional Level
178
Projectized (Silo) Structure
Each Functional Manager controls staff horizontally
ENG Manager
MFG
Manager
Quality
Manager
Each PM controls staff vertically
Program Manager
179
Spider Web Structure Figure 10.6
ME
CAD
TE
DE
QE
180
MANAGEMENT STYLES
In 1957, Robert Tannenbaum and Warren Schmidt, Management theory professors, published a model of leadership explaining the different ways that leaders interact with their staff.
Their idea was that as the project team matures and becomes more self-sufficient and self-directing, the PM’s style should:
The Tannenbaum and Schmidt Continuum
182
Commanding
Selling
Participating
Delegating
Management Continuum
183
Conflict Resolution
The Ingredients of Conflict
185
Conflict is not always negative
If effectively managed it can lead to:�
186
Conflict Management Strategies
187
Conflict Management Strategies
Collaboration
188
Conflict Management Strategies
Compromise
189
Conflict Management Strategies
Competition
190
Conflict Management Strategies
Accommodation
191
Conflict Management Strategies
Avoidance
192
Team Performance Metrics
The goal of performance reporting is to establish a system which consistently, effectively, and objectively tracks:
Two categories:
Non-Contact Method
Contact Method
Pg 301
193
NON-CONTACT
Non-Contact�Change Control Management
Must be active throughout Project Life Cycle
An effective change control system contains the following features:
pg 93-99
195
Non-Contact Method - PM Dashboards
PM Dashboards have become increasingly popular, especially on business and marketing projects and is now appearing in more technical-based projects.
A Dashboard can be thought of as a report card of the project at each phase of the project or some other cyclic reporting period.
Dashboards typically use charts, graphs and performance indicators to highlight key areas of the project by displaying data in formats that are easy to interpret by multiple layers of management.
PM Dashboards can be helpful as a NON-CONTACT management tool to allow the project manager to review, monitor and manage data without the need for physical interaction such as meetings or phone calls.
Once a trend or “critical value” is observed the PM can take specific and “surgical” action to remedy an issue without involving project team members who are unaffected.
In this way a Dashboard can also help to prevent project managers from micromanaging a project.
196
197
EXERCISE 7: SPECTRUM MAPPING
MAP THE DIVERSITY OF PERSPECTIVES ON A TOPIC BY ORGANIZING THEM INTO A SPECTRUM. THIS CAN REVEAL INNOVATIVE IDEAS AND SHOW THE DIVERSITY OF OPINIONS WITHIN A TEAM. IT CAN ALSO ENCOURAGE PEOPLE WITH UNCONVENTIONAL VIEWS WHO OTHERWISE WON’T SPEAK UP TO PARTICIPATE.
DURATION: 20 MINUTES
OBJECTIVE: EXPRESS VIEWS AND SHARE DIVERSE VIEWS
TASK:
1. USING THE PRODUCT AND PROJECT DATA COLLECTED THUS FAR EACH GROUP WILL IDENTIFY THE TOP 6 CONCERNS (3 PRODUCT RELATED AND 3 PROJECT RELATED THAT THEY FEEL ARE A SIGNIFICANT RISK TO PROJECT SUCCESS.
2. APPOINT A RECORDER AND MAP EACH PARTICIPANT’S CONCERNS ALONG A HORIZONTAL LINE
3. ONCE ALL PARTICIPANT CONCERNS ARE RECORDED, ALL GROUPS WILL ARRANGE THE NOTES AS A "RANGE" OF IDEAS. GROUP SIMILAR IDEAS TOGETHER TO THE LEFT. PLACE OUTLYING IDEAS TO THE RIGHT. (THINK AFFINITY DIAGRAM)
4. CONTINUE DOING THIS UNTIL YOU'VE ARRANGED ALL IDEAS AS A "SPECTRUM" WITH MOST POPULAR IDEAS TO THE EXTREME LEFT, THE LEAST POPULAR IDEAS ON THE EXTREME RIGHT.
GOAL: BUILDING A SPECTRUM MAP TELLS YOU THE DIVERSITY OF YOUR TEAM'S VIEWS ABOUT A TOPIC.
Types of Meetings
and
Meeting Protocol
Meetings
Meetings are an inseparable part of the work process. When used properly they :
Team Development
200
Top Ten Meeting Problems
1. Getting off track
2. Meeting inconclusive with no results
3. Missing goals, purpose or agenda
4. Too lengthy
5. Disorganized and lacking control
6. Late starts
7. Poor preparation by most or all attendees
8. Too much information being discussed leading to lack of focus
9. Individuals monopolize discussions
10. Interruptions (side discussions and attendees in and out)
Team Meetings Tips
Team Development
201
Why are We Meeting?!
Team Meetings Tips
Team Development
202
Project Kick-Off Meeting
Team Development
203
MEETING PROTOCOL
Meeting Structure
Team Meetings Tips
Team Development
205
Orient the Meeting
Team Meetings Tips
Team Development
206
Establish Common Reference Frame
Team Meetings Tips
Team Development
207
Monitor Meeting “Talk Time”
Team Meetings Tips
Team Development
208
Use Smaller Meeting
Team Meetings Tips
Team Development
209
Meeting Roles
Team Meetings Tips
Team Development
210
Leadership Responsibilities
Team Meetings Tips
Team Development
211
Attendee Responsibilities
Team Meetings Tips
Team Development
212
Facilitator
Team Meetings Tips
Team Development
213
Recorder
Team Meetings Tips
Team Development
214
Team Development
Team development includes both enhancing the ability of stakeholders to contribute as individuals as well as enhancing the ability of the team to function as a team.
Development of a team is critical to the project’s ability to meet its objectives.
Knowledge Area 9
Team Development
215
Intercultural Team Dynamics
216
Team Member Enablement
217
Exercise – 8�Which Meeting is Right?
Focus
Offer several real world scenarios and for your team to determine which meeting would be the most appropriate type to handle the specific situation.
Tasks:
218
Risk Management
MODULE 7
Risk Management
5 sub-processes
Key Output - Development of the Risk Management Plan
Knowledge Area 11
Pg. 309
220
Risk Management
“There are known knowns; these are things we know that we know.�(Project Budget)
There are known unknowns; that is to say there are things that we now know we don't know.�(Contingency Reserves)
But there are also unknown unknowns – these are things we do not know, we don't know.”
(Management Reserves)
Knowledge Area 11
United States Secretary of Defense, Donald Rumsfeld
221
Risk Management Planning
The Risk Management Plan (RMP) describes how project risk will be identified, assessed, addressed and responded to during the course of the project.
Typical elements of the RMP include:
222
Elements of a Typical Risk Management Plan
223
Risk Identification
Risk identification (or assessment) is a method to:
In most instances, more than one analytical technique is necessary to assess risk at a both a project and design level:
224
Risk Response and Control
Response
How the project team plan to deal with the identified risks.
Part of the Risk Management Plan
Control
Implementation of the Risk Management Plan
225
Risk Response and Control
226
Risk Assessment Methods
Product
Project
227
Personal protective equipment
Eliminate
hazards through
design improvements
Protect or guard
against the hazard
Warn the user about the hazard
Train the user to avoid the hazard
Hazard Response Hierarchy Pyramid
BEST
Product Risk
DFMEA
228
Project Checklists
The use of checklists as planning documents helps to ensure that the same concerns are addressed for each new program.
Checklists can also:
Project Risk
229
Preparation of Checklists
230
Preparation of Checklists
231
Preparation of Checklists
232
Risk Priority Table – Example 1
233
Risk priority | Definitions of priority | Time frame to resolve |
High | Issue present but is outside the authority of the PDT to resolve and requires sponsor level intervention. Consider cessation of work process. Potential impact to customer master timing. | Now |
Medium | Issue present but within the authority of the Project Team. Consider short term and/or long term actions. No impact to customer master timing. | 1 – 3 weeks |
Low | No known issues present. | None |
Risk Priority Table – Example 2
234
ADDITIONAL RISK ANALYSIS METHODS
Risk Breakdown Structure*
Project Risk
236
Sample Risk Register
Project Risk
The results of the Timing and Scope columns will be plotted on a Quadrant Map to help prioritize Risk mitigation efforts.
237
Quadrant Risk Mapping
Low Probability�High Impact
Low Probability �Low Impact
High Probability�High Impact
High Probability �Low Impact
High
Low
High
Timing Impact of Risk Event
Severity of Scope Impact
Project Risk
238
Engineering Changes
Lab Certification
UNI-GRAPHICS
Resources
Final
Score
Quality
Scope
Schedule
Cost
Impact Value (see scale range)
Current Value from Historical Data
SOR
para number
SOR
Reqt
Risk Item
Probability Impact Matrix
Sample P-I Matrix See scoring criteria in PMBOK, fig. 11-1, pg. 407
Project Risk
239
Expected Value Matrix (EVM)
Steps for constructing a payoff matrix:
Step 1 Develop project strategies
Step 2 Determine likely events
Step 3 Assign probabilities to those events
Step 4 Determine the outcome ($) for each event
Step 5 Calculate the Expected Value (EV) for each strategy to determine best strategy.
Project Risk
240
36
40
40
0
Lease Equipment
-8
80
-20
-500
Purchase In-House Humidity Test equipment
37
60
20
-50
Conduct Humidity Test at Intl Test Labs
60%
30%
10%
Expected Value
Multiple Contract use
Single use for this contract only
Lose
Contract
EV
Event C ($00)
Event B ($00)
Event A
($00)
Strategies
Probability of occurrence
Sample EVM
Project Risk
241
Risk Management Software
TRIMS
242
EXERCISE 9:
IMPROVING THE CHECKLIST
EXERCISE 10 Improving the Checklist
Now that your team is at the end of the project life cycle it’s time to update the original TFC document that you completed at Exercise 2. Therefore, using the checklist improvement slides and your product and project knowledge received by going through this project
244
In Summary…….
245
APQP AND PPAP PRIMER
What APQP IS
247
What APQP IS NOT
(Actually, APQP is a subset of PM under PMBOK item 8 – Quality Management)
248
Who is Involved in APQP?
“The first step in Product Quality Planning is to assign responsibility to a multi-disciplinary team.” APQP Manual, pg. 3
Typical team membership includes:
Core Team
249
Document Deployment of APQP
Detect
Prevent
R
P
N
D
E
T
O
C
C
S
E
V
Action
Taken
Action Results
Response &
Target
Complete
Date
Recommended
Actions
R
P
N
D
e
t
e
c
Current
Controls
O
c
c
u
r
Potential
Cause(s)/
Mechanism(s)
Of Failure
C
l
a
s
s
S
e
v
Potential
Effect(s) of
Failure
Potential
Failure
Mode
Item /
Process
Step
Detect
Prevent
R
P
N
D
E
T
O
C
C
S
E
V
Action
Taken
Action Results
Response &
Target
Complete
Date
Recommended
Actions
R
P
N
D
e
t
e
c
Current
Design
Controls
O
c
c
u
r
Potential
Cause(s)/
Mechanism(s)
Of Failure
C
l
a
s
s
S
e
v
Potential
Effect(s) of
Failure
Potential
Failure
Mode
Item /
Process
Step
Function
DFMEA
Voice of Customer (VOC)
Robustness Tools
QFD
SC Matrix
Dimensional Plan
Boundary Diagram
P-Diagram
Interface Matrix
Cascade relationship from VOC to Manufacturing
VAL/VER
DFM/DFA
DVP&R
Build Trials
Supplier Reviews
Process Tools
Special Characteristic Matrix
Process Flow Diagram
Process and Machinery FMEA
Process Control Plan
PPAP
250
Analysis of the 5 Phases of APQP
5 Phase Process
251
Objective – Document VOC and Readiness for Final Quote
Objective – Work tasks understood and verification that resources are appropriate to project requirements
1. CONCEPT PHASE
2. PROGRAM APPROVAL PHASE
Objective – Approval to source Production tooling
3. PROTOTYPE PHASE
Objective – Continual Improvement
5. LAUNCH PHASE
Overview of APQP Objectives by Phase
Objective – Full PPAP approval. Begin Production Launch Ramp-up
4. PILOT PHASE
252
AUTOMOTIVE CONTRACTING FORMATS
Common Types of Contracts
Customer Risk
Performance Detail
Supplier Risk
Performance Detail
LO
HI
HI
LO
254
Subcategories of Requirements Contracts�Automotive Specific
Customer Risk
LO
HI
Supplier Risk
LO
HI
255
by order of magnitude)
Identifying Sources of Scope Creep
256
PRODUCTION PART APPROVAL PROCESS
(PPAP)
PPAP BACKGROUND
258
APPLICABILITY of PPAP
PPAP shall apply to internal and external supplier sites of :
Page 1, AIAG PPAP Manual
259
All the items submitted for PPAP approval must be production intent to qualify for approval under the PPAP process.
This means the supplier demonstrate use of the final version of the production process. Think Fishbone Diagram:
Terms
PRODUCTION INTENT
Material
Gages
Operators
Tooling and Equipment
Process Flow
Environment
APPROVED PPAP
260
A SIGNIFICANT Production Run is one in which production intent parts have been manufactured from a process that represents a “steady state” operation. This typically requires:
Page 3, AIAG PPAP Manual
SIGNIFICANT PRODUCTION RUN
Terms
261
18 PPAP Requirements
Page 18, PPAP Manual
262
Design Record File
Proper maintenance of the PPAP documents, and specifically the Design Record file, are critical since these are the records that will be used during a product liability suit to determine the level and conduct of “engineering due diligence”.
However, within Automotive, there is no set format or template for how a Design Record file is to be maintained and this has caused much variation in the structure and maintenance of Design Record files.
Once such existing structure can be borrowed from the Medical Device industry which, together with the FDA, has quite a bit of experience in establishing and maintaining Design Records.
In addition to being federally mandated the Medical Device Industry has significant experience in product liability cases.
263
The Design Record file must reflect a complete record of what went into the development of the particular product design.�An industry standard which is very adaptable to Automotive projects is the process used by the medical device industry.�This industry uses three (3) terms to fully define a Design Record File:
Design Record File - DRF
DHF - Design History File
DMR - Device Master Record
DHR - Device History Record�
264
Design Record File
PM
Responsible
Plant
Responsible
265
Device (Product) Master Record (DMR)
The DHF is the collection of all specifications which describe how the product is to be designed, built, and tested and includes records of:
266
Design History File (DHF)
The DHF is the collection of all records which describe the design history of the product and includes records of:
Record Description Sample Document
267
The design history file contains or references the records necessary to demonstrate that the design was developed in accordance with the approved Customer Requirements document for each system and subsystem, and component contracted.��Note that the DHF needs only contain those products which are “saleable product” which in some cases does not include component design information since that is potentially supplier proprietary.�Typical items included in the DHF are:
Design History File
268