1 of 8

Executive Staff Meeting

August 26, 2013

OPEN SOURCE

OPEN SOURCE

2 of 8

Shuttleworth Expectations

  1. CEB Press design is revised, the 3 machines are updated with the new design elements and successfully used during the microhouse build scheduled for 28 September.

  • The LifeTrac design is revised to version 6, the LifeTrac 6 machine built and used effectively together with the CEB Presses during the microhouse build scheduled for 28 September.

  • The build, test, and data collection of the ironworker and backhoe is complete.

  • Only GVCS machines are used in the microhouse build of 28 September.

  • The microhouse build is completed successfully by 30 October 2013.

OPEN SOURCE

OPEN SOURCE

3 of 8

3rd Quarter Priorities (July - September)

  1. Development Process - LifeTrac 6 Beta testing process
    • By end of September
  2. Schedule and execute objectives for 3rd Quarter
  3. Microhouse
  4. Support Equipment - LifeTrac 6, CEB, Soil Pulverizer, 50hp Power cube
  5. Build, Test, and Data Collection of
        • Backhoe (complete by October 30)
        • Iron worker (complete by October 30)

  • Schedule objectives for 4th Quarter (October-December)

OPEN SOURCE

OPEN SOURCE

4 of 8

Current Week Priorities

Week Priorities

Previous Week

Current Week

Issues/Risk

Quarterly Goal

Project Manager Scheduling

Complete LifeTrac 6 schedule

Schedule:

Microhouse

Soil Pulverizer

50hp Pwr Cube

Backhoe

Ironworker (75%)

  • Some of the items are missing POCs responsible

3rd Quarter (July-September)

4th Quarter (October-December)

LifeTrac 6

Implement use of Development Boards and provide feedback next meeting.

Status of LifeTrac 6?

If PL not onsite, then connection to DPV is difficult. If DPV spends too much time on a single task, then poor experience.

Build LifeTrac 6 while beta testing process and documenting to then improve process

OPEN SOURCE

OPEN SOURCE

5 of 8

Current Week Priorities

Week Priorities

Previous Week

Current Week

Issues/Risk

Quarterly Goal

6 in 60 Documentation

DPV and Design Sprint Recruiting

TCM diverted to planning

1) Document INTERIM DPV Strategic Plan

2) ## Touchpoints

1) INTERIM due to lack of schedule

2) LifeTrac 6 workplan

End of September - 3 DPVs

OSE Structuring

501(c)(3) response to Letter 1312

Sourcing Benefits

CAB step by step

Uploading LifeTrac 5

CAB Step by step

OPEN SOURCE

OPEN SOURCE

6 of 8

Schedule Review

  • Project Manager
  • OSE Schedule (migrate to PM - if feasible)

OPEN SOURCE

OPEN SOURCE

7 of 8

Other Tasks

Date Added

Tasks

Status

August 22

Development Process - Product Development Board’s Step Instructions and Sample Deliverables

August 26

July 15

Cloverdale steel pick up

August 19

Socialize INTERIM OSE Org and Ops Manual inputs so everyone is informed

August 16

ED respond to FAQ#Reporter Questions

August 26

OM source Benefits

August 26

DM create "Get Involved" frame for all OSE videos - keeping it simple by using positional emails

OM: This may be complete, verify with DM

August 26

Sweiger Shop - steel pick up

August 20

Mo-kan Fasteners (KC) bolts pick up

Urgent - going out of business

Reference: Parking Lot

Reference: Other Tasks

OPEN SOURCE

OPEN SOURCE

8 of 8

Strategic Issues for Discussion

  1. Gravel lay down and bridge installation prior to fall rain
  2. Steel Pick up

Reference: Parking Lot

Reference: Other Tasks

OPEN SOURCE

OPEN SOURCE