Oxford deserves a better flood scheme�Public Meeting Oxford Town Hall �17 April 2023
Community comment on Regulation 25 Consultation
Introduction �and �The Costs and Benefits of the�Oxford Flood Alleviation Scheme
Tim O’Hara
Surveyor and North Hinksey resident
Oxford Flood Alleviation Scheme
The flood channel will cause environmental damage and incur social costs because of its:
Proposed flood channel – central section highlighted in yellow
The channel does not provide significant extra benefit
Environment Agency Benefit – cost analysis | Present Value (£ million) of option | |
Scheme with the whole flood channel | Scheme without the whole flood channel* | |
Benefits (damages avoided by option) | 1536 | 1501** |
Damages caused by floods | 174 | 209 |
Costs (construction etc) | 145 | 121 |
** This is 98% of 1536. 1501 divided by 1538 = 0.98 (to 2 decimal points)
Sources: EA CPO Statement of Reasons 2023; EA App. Q (2023) to planning application
How the scheme with and without the channel will protect property
* No channel from 200m south of Botley Road to Old Abingdon Road
Source: EA App. Q (2023) to planning application
Options for flood protection | Homes and non-residential properties at risk in floods of a severity that would only occur every…… | ||||
5 years | 10 years | 50 years | 75 years | 100 years | |
Existing measures, (but no temporary defences after 25 years) | 77 49 | 266 98 | 862 201 | 1126 253 | 1319 284 |
Scheme without the flood channel* | 1 12 | 37 56 | 156 116 | 234 147 | 524 210 |
Scheme with the whole flood channel | 1 8 | 7 27 | 105 92 | 180 122 | 367 151 |
The Importance of Flood Meadows
Professor Kevan Martin, Thames Valley Wildflower Meadow Restoration Project
(Restorers of Christ Church Meadow and other Oxford College meadows)
Floodplain meadows:
rare, rich and irreplaceable in our lifetime.
Prof. Kevan AC Martin,
Thames Valley Wildflower Meadow Restoration Project
Emma Rothero, Irina Tatarenko, David Gowing,(2020)
J. Nature Conservation
Ben A. Woodcock, Alison W. McDonald. Richard F. Pywell (2011)
J. Applied Ecology
Further Environmental Damage
and its ‘Mitigation’
Jocelyn Wogan-Browne, Professor Emerita,
Osney Island resident, Oxford Flood and Environment Group member
Hedgerows, mature tree copses and grasslands in the fields south of Hinksey Meadow
(97% of British meadows have been lost since WW2 and we are the most de-afforested country in Europe)
This
becomes
this
Willow Walk
Environmental degradation
BEFORE OFAS
AFTER OFAS
Drone photo 4th April 2023
(James Wynne)
Showing loss of ~1000 mature trees
(entire scheme entails felling 4000 trees)
The channel runs from Seacourt Nature Park to the Old Abingdon Rd at Kennington- 5 kms long in its full extent and up to 250 yards wide.
Source: EA website (initially published without reference to growth time frame: corrected under pressure from public comments)
Willow Walk in
late summer now
And in future?
Social Costs
Dr Rod Chalk, University of Oxford
Financial cost £176M �(up from £111M in 2017)��Social cost?
OXFORD FLOOD ALLEVIATION SCHEME
Social costs:
*Costs are substantial, permanent and borne by the entire community
They are NOT factored into the cost-benefit model
Positive effects of nature on mental health*
*according to MIND, mentalhealth.org.uk, BUPA & RSPB
Temporary loss of access
Willow walk has been closed for 3 months forcing a 2-mile diversion on a busy trunk road for pedestrian and cyclists and causing massive inconvenience for commuters local residents and school children
Access to the flood plain will (now) be severely restricted for 5 years
Permanent loss of access
Pity the residents of South Hinksey
Works compound and material storage
Works compound and material storage
South
Hinksey
Village
Trees felled
Access haulage road 20m wide (2 bus lengths)
Haulage Road
Haulage Road
Haulage Road
Haulage Road
A34 national trunk road at South Hinksey
Inadequate South Hinksey slip road is just 90m
HOEG�Pumped Pipeline
Seacourt
to
A423 Bypass
East side of Railway
Kevin Larkin (Architect)
Jonathan Madden
33
Triple level plan and profile drawings of pump house.
Vehicular access to pump house from car park.
Spillway diameter: 100m
Major axis: 40m
Minor axis: 20m
ii) Penstock level: flood water intake into axial flow pumps.
iii) Axial flow pump room. Sub-ground level. Four pump output converged into two pipes.
Profile of spillway into penstock and pumping system. Spillway protected with grilles to control debris ingress.
Outlet of 2 x 2m diameter GRP pipes, on shallow gradient to ca. 2.5m depth.
Flood level
Grassed area surrounding utilities housing
Pylon anchors with ‘H’ girders reinforce concrete surround and spillway.
34
X-sections showing buried pipeline in trench to scale parallel to the Electric Road. (Measurements in mm)
37
Advantages of Pumped Pipeline System
38
Hinksey and Osney Environment Group |
|
|
|
| |||
| | | | | |
| |
Pumped Pipeline Alternative Proposal: Outline Costings | | |
| ||||
| | | | | |
| |
| Item: | | | Cost: (£1,000) | | Notes: | |
| | | | | |
| |
i) | GRP Pipe Sections: 5km, 2m diameter. Twin Pipes | £2,000 | | Future Pipe Industries: Pipe Sections, delivered as telescoped sections of increasing diameter | |||
| | | | | |
| |
ii) | Four x Ensival Moret 1.5m dia. Axial Flow Pumps | £2,000 | | Low pressure head, high volume. With cycloconverter high-torque start system. | |||
| | | | | |
| |
iii) | Steel 'Y' manifolds from pump outlets to main 2m pipes | £250 | | Steel ‘Y’ manifolds, bringing output from four pumps into two, 2m dia. pipes. Equipped with valves to permit flexible operation with fewer than four pumps. | |||
| | | | | |
| |
iii) | 2MW Standby Backup Diesel Generator and switchgear | £400 | | Reconditioned, used unit. Switchgear for transfer from grid in case of outage. Located over pump room, above flood level. | |||
| | | | | |
| |
iv) | Pump House | | | £2,500 | | ‘Swimming Pool’ concept, excavated to 10m depth. | |
| | | | | |
| |
v) | Inlet spillway | | | £750 | | Reinforced concrete, elliptical profile, with varying OD elevation, for graded floodwater ingress. | |
| | | | | |
| |
vi) | Penstock | | | £250 | | Epoxy screed penstock, guiding flood water into pump inlets. | |
Pumped Scheme: Approximate Costings:
39
| | | | | |
|
vii) | Pipelaying onto concrete supports | | | £1,500 | | Anchoring to control float forces by flexible steel bands |
| | | | | |
|
viii) | Trenching, and backfill. Shallow bund construction | £4,000 | | Est. £25/cumet, for 150,000 cumets. | ||
| | | | | |
|
ix) | Design | | | £1,000 | | Detailed engineering design. Environmental and archaeological studies. |
| | | | | |
|
x) | Discharge Race | | | £200 | | 30m reinforced concrete ramp, baffled |
| | | | | |
|
xi) | Landscaping | | | £2,000 | | Recover landscape to previous state. Plant trees and grasses. Reinstate footbridges etc. |
| | | | | |
|
xii) | Electrical Connection to Mains | | | £250 | | Connect to national grid |
| | | | | | |
| | |
| | | |
| | | | | |
|
| | | Total: | £17,100 | |
|
| | | | | |
|
| Contingency for uncertainty in ground works, other on-site work, etc. | £5,000 | |
| ||
| | | | | |
|
|
|
| Extended Total: (£k) | £22,100 |
| Does not include work in OAR/Railway/Bypass area. |
Costings: cont’d
How the scheme design can be improved based on the present planning consultation under Regulation 25 ��Brian Durham�New Hinksey Resident�Archaeologist to Oxford City Council (retired)
In August last year the planning authority requested that the application be `supplemented with additional information which is directly relevant to reaching a reasonable conclusion’.
The applicant (Environment Agency) has responded.
Reg 25 para 5.2 Channel improvements on Seacourt Stream please provide confirmation these have been applied to Scenario A2
Better Flood Scheme Public Meeting 2023
41
17/04/2023
Reg 25 para 5.1 Willow Walk New Bridge #N/A values please provide the missing water levels or full explanation
The applicant has ignored the request for missing levels at what is ecologically the most sensitive location next to MG4 grassland.
The communities need the Peer Reviewer to ask why the engineers were not able manually to infill these gaps in their model output?
Better Flood Scheme Public Meeting 2023
42
17/04/2023
Reg 25 para 5.3 Please provide the reason for not applying locally-lowered beds in modelling proposed bridges
Better Flood Scheme Public Meeting 2023
43
17/04/2023
Reg 25 para 5.10.2 Need for single-bridge design at Old Abingdon Road
On 16 February 2021 the applicant’s consulting engineer described the single offline bridge option as a `more elegant solution’, and HOEG asked to see County Highways view of this option.
The communities can reasonably ask for that response to be made available in the planning process
Better Flood Scheme Public Meeting 2023
44
17/04/2023
Proposed bridging at Old Abingdon Road (red) and
flood-friendly, traffic-friendly alternative (green)
Reg 25 para 5.10.3 Need for protection of the railway at Kendall Copse East
Better Flood Scheme Public Meeting 2023
45
17/04/2023
Reg 25 para 5.10.4 Need for formal floodplain compensation analysis
Scheme has not provided a floodplain compensation analysis (FCA). For example:
The communities can reasonably ask for the Peer Reviewer to assess the extent to which this embanking degrades performance of the scheme
Better Flood Scheme Public Meeting 2023
46
17/04/2023
Floodplain compensation analysis provided by City Council for Seacourt Park and Ride extension
Applicant’s response to peer review
Modelling domains
The Environment Agency is on record that the proposed meadowland channel design has never been tried on this scale.
The communities can reasonably ask for the Peer Reviewer to assess whether the applicant’s response on their modelling (opposite) justifies the experimental design of the meadowland channels, given the scale of ecological and landscape damage we have heard.
Better Flood Scheme Public Meeting 2023
47
17/04/2023
Reg 25 para 6.2 Please simulate a higher resolution or multi-domain set up
Is this good enough to expect our cooperation?
Better Flood Scheme Public Meeting 2023
48
17/04/2023
NEXT STEPS�How to comment�
Patricia Murphy, author and TV Producer/Director,
Oxford Flood and Environment Group
NEXT STEPS
How to comment
The planning process
WE ARE HERE
WHAT YOU CAN DO
Compulsory Order Process -
Making our voices heard� the power of numbers �
Effective Comments and Objections
Economic, impact, errors and omissions
HOEG will be asking the planning authority for:
OCC Peer Reviewer to report on whether the comparison process with the no channel excavation option proposed by Dr Tim King has been even-handed.
To review on any impact from the avoidable removal of 10ha from the east flood plain on the effectiveness of the flood alleviation.
To review the safety of the experimental channel in the light of the `unsuccessful’ modelling reported by the applicant.
Network Rail chartered engineer to confirm in writing that, in the light of the existence of an additional track, the 0.36m water level difference presented no risk to the railway.
OCC Highways to confirm in writing that the twin bridges design is optimal compared to a single line bridge “elegant solution” proposed by Jacobs engineers.
Objections – Environmental
INFORMATION SOURCES
How To Comment�
Councillors https://mycouncil.oxfordshire.gov.uk/mgMemberIndex.aspx?VW=TABLE&PIC=1&bcr=1
https://mycouncil.oxford.gov.uk/mgCommitteeMailingList.aspx?ID=0
What will be Oxford’s gift to our green King?
DON’T LET THIS SUMMER BE THE LAST FOR HINKSEY MEADOW AND THE WILDLIFE CORRIDOR