Consultancy contract for techno- economic feasibility study, Detailed Master Planning, Urban Designing, Engineering and preparation of Detailed Project Report for Redevelopment
of Pune Railway Station of Pune Division, Central Railway.
PUNE RAILWAY STATION REDEVELOPMENT
PUNE RAILWAY STATION : RAILWAY YARD (Existing)
6
PLATFORMS
4
FOBs
47/47
ORIGINATING /TERMINATING TRAINS
37.44 HA
SITE AREA
60
TRAINS PASSING THROUGH
16450
PAX. CURRENT PEAK HOUR TRAFFIC (2025-26)
6
NEW ISLAND
PLATFORMS
2
FOBs
PUNE RAILWAY STATION : RAILWAY YARD (Proposed)
5
EXTENSION OF PLATFORMS
DESIGN PHT
24249
(2065)
STATUS OF WORKS
AT
PUNE STATION
A: Pune Station: Sanctioned work under PH 53
SN | Name of Work | PH | Sanction Date | Executing Agency | Cost in Cr. | Work Status |
1. | Pune - Construction of New Island Platform No (7 & 8) at Pune Railway station.� | 53 | 05/02/2026 | Construction | 10.39 | Tender invited & due for opening on 17.04.26 |
2. | Pune - Construction of New Island Platform No (9/10) at Pune Railway station along with COP, Toilet block, Water stand. | 53 | 24/02/2026 | Construction | 18.38 | Tender invited & due for opening on 17.04.26. |
3. | Pune - Construction of New Island Platform No (11/12) at Pune Railway station along with COP, Toilet block, Water stand. | 53 | 20/02/2026 | Construction | 15.32 | Tender invited & due for opening on 17.04.26. |
4. | Pune - Provision of 06m wide FOB from New RRI building to RBM road connecting to PF No 7/8 at Pune station. | 53 | 16/02/2026 | Construction | 9.64 | Tender invited & due for opening on 17.04.26 |
5. | Provision of 06-meter-wide FOB connecting to Platform No 9/10 & 11/12 from circulating area. | 53 | 17/02/2026 | Construction | 15.86 | Tender invited & due for opening on 17.04.26 |
6. | Pune - Provision of COP and other passenger amenities to new platform (7&8), Booking office at Pune station | 53 | 20/02/2026 | Construction | 9.47 | Tender invited & due for opening on 17.04.26.. |
7. | Provision of Lighting, Fan, lifts facility at New Platform (7 & 8), FOB, Sky walk and offices, at Pune station | 53 | 17/02/2026 | Construction | 6.67 | Electrical Tender opened on dated 29.01.2026, TC under process. |
8. | Pune - Provision of lifts, escalators, Lighting, Fans, Telecom and seating facility at Platform No 9/10, 11/12 at Pune railway station | 53 | 18/02/2026 | Electrical: construction Telecom: Open line | 15.87 | Electrical Tender opened on dated 29.01.2026, TC under process. Telecom portion tender to be invited |
9. | Telecom work - Coach, indicator, train indicators and other telecom work at New platform No 7/8 and at existing station at Pune | 53 | 17/02/2026 | Open line | 7.98 | Tender to be invited |
A: Pune Station: Sanctioned Work under PH 53
S No | Name of Work | PH | Sanction Date | Executing Agency | Cost in Cr. | Work Status |
10 | Pune - Provision of 06 m wide Sky walk to New PF No 7/8 from PF No. 1 at Pune station | 53 | 25/03/2026 | CONSTRUCTION | 19.99 | Tender invited pending sanction of estimate & due for opening on 17.04.26 |
11 | Pune~~Pune~~Dismantling the exiting parcel office and construct new parcel office in connection with Pune station decongestion plan. | 53 | 30/03/2025 Executive agency decided on DEC 2025. | OPEN LINE | 13.57 | Tender to be invited. TDC-NIT 07.04.2026 |
TOTAL | 143.14 | | ||||
S No | Name of Work | PH | Sanction Date | Executing Agency | Cost in Cr. | Work Status |
1 | Pune~ Creation of Trip Maintenance / Advance inspection Centers for inspection and maintenance activity of electric locomotives. | 42 | 15/10/2025 | Construction | 10.41 | Work in progress. Foundation completed, column erection is in progress. Physical progress 60%. TDC- 31.05.2026 |
A: Pune Station: Sanctioned Work under PH 42
A: Pune Station: Sanctioned Work under PH 16
S No | Name of Work | PH | Sanction Date | Executing Agency | Cost in Cr. | Work Status |
1 | Pune - Extension of platform(2,3,4,5 & 6) for 24/26 coaches and removal of DDS | 16 | 26/11/2015 | Construction | 60.35 | First ESP approved on 21.02.2022, alteration 1 -27.06.22, Alt -2 on 12.12.23. Alt-3 on 29.02.24 Latest ESP approved on 20.01.2026 Civil potion- Tender invited & due for opening on 17.04.26. P.way Tender awarded. Work will be started after construction and commissioning of platforms 7 to 12. |
2 | Construction of additional transfer line between GCMC to Hadapsar. | 16 | 08/07/2024 | Construction | 97.16 | Work in progress, Track linking completed. Physical progress - 92 % TDC- 31.05.2026 |
3 | Provision of 2 additional platforms with ancillary works at Pune. | 16 | 21/03/2025 | Construction | 49.43 | Tender awarded. Lines have been surrendered for construction of PF 11 and 12. Work is started. |
4 | Pune- Construction of Two UP & DN run through stabling lines and allied works related to Pune yard. | 16 | 08/08/2025 | Construction | 28.18 | Tender awarded. Bridge work in progress, formation work will be started after commissioning of EI due to bunch of cables available. |
TOTAL | 235.12 | | ||||
Total Cost of sanctioned works of Pune Station – INR 388.67Cr
C: Pune Station: Works Yet to be Shortlisted Under PH-53
S No | Name of Work | Cost in Cr. | Current status |
1 | Construction of subway connecting to PF no. 7/8, 9/10, 11/12 and 13/14 to circulating area of 3rd entry at Pune station. | 46 | Proposal under process. |
TOTAL | 46 | | |
B: Pune Station: Works Shortlisted but not yet sanctioned
S No | Name of Work | Cost in Cr. | Current status |
1 | Development of Permanent holding area at Pune Railway station for Rush Management. | 48.51 | GM administrative approval taken on 08.03.2026 File is currently with Dy FA &CAO for PFA Concurrence since 18/03/2026 in IRPSM |
Grand Total - INR 483.18 Cr
TOTAL | 48.51 | |
Existing Site Images
EXISTING SITE IMAGES
MAIN ENTRY CIRCULATING AREA
UMBRELLA ENTRY
OLD STATION BUILDING
REAR SIDE CIRCULATING AREA
EXISTING PASSENGER FOOTFALL:
Year | UTS Total | PRS Total | Total Passengers | Growth % | Passengers per Day |
2014-15 | 2,93,88,870 | 1,79,48,294 | 4,73,37,164 | | 129691 |
2015-16 | 2,87,14,374 | 1,81,29,590 | 4,68,43,964 | -1 | 128340 |
2016-17 | 2,82,41,678 | 1,83,12,717 | 4,65,54,395 | -1 | 127546 |
2017-18 | 2,85,66,258 | 1,84,97,694 | 4,70,63,952 | 1 | 128942 |
2018-19 | 2,17,06,932 | 1,86,84,539 | 4,03,91,471 | -14 | 110662 |
2019-20 | 3,77,51,890 | 1,84,33,385 | 5,61,85,275 | 39 | 153932 |
2020-21 | 5,87,550 | 59,19,210 | 65,06,760 | -88 | 17827 |
2021-22 | 45,00,986 | 1,74,36,208 | 2,19,37,194 | 237 | 60102 |
2022-23 | 2,76,70,400 | 2,07,60,972 | 4,84,31,372 | 121 | 132689 |
2023-24 | 3,42,92,161 | 2,22,99,986 | 5,65,92,147 | 17 | 155047 |
2024-25 | 3,60,59,995 | 2,33,88,608 | 5,94,48,603 | 5 | 162873 |
Category | 2014–15 | 2024–25 | CAGR |
UTS | 2,93,88,870 | 3,60,59,995 | 2.07 % |
PRS | 1,79,48,294 | 2,33,88,608 | 2.68 % |
PUNE STATION
PASSENGER PROJECTION FOOTFALL CONSIDERING CAGR 2% ( UTS 2% & PRS 2%)
Year | UTS (Annual) | UTS (Per Day) | PRS (Annual) | PRS (Per Day) | Total (Annual) | Total (Per Day) |
2024-25 | 3,60,59,995 | 98,795 | 2,33,88,608 | 64,078 | 5,94,48,603 | 1,62,873 |
2025–26 | 3,67,81,195 | 1,00,770 | 2,38,56,380 | 65,360 | 6,06,37,575 | 1,66,130 |
2034–35 | 4,39,56,933 | 1,20,430 | 2,85,10,583 | 78,111 | 7,24,67,515 | 1,98,541 |
2044–45 | 5,35,83,256 | 1,46,803 | 3,47,54,241 | 95,217 | 8,83,37,497 | 2,42,021 |
2054–55 | 6,53,17,690 | 1,78,953 | 4,23,65,226 | 1,16,069 | 10,76,82,916 | 2,95,022 |
2064–65 | 7,96,21,899 | 2,18,142 | 5,16,42,974 | 1,41,488 | 13,12,64,873 | 3,59,630 |
Base Year (2024–25):
UTS: 3,60,59,995 annually (98,795/day)
PRS: 2,33,88,608 annually (64,078/day)
Total: 5,94,48,603 annually (162,873/day)
CAGR adopted :
UTS = +2%
PRS = +2%
Daily Passengers | Platform Ticket (3%) | Total Design Footfall / Day |
3,59,630 | 10,789 | 3,70,419 |
EXISTING LAND UTILIZATION
DEVELOPABLE LAND PARCELS
TOTAL PROJECT AREA- 3.74.475 SQM/ 37.44HA
Ambedkar road
Pune railway station road
Wellesley Road
Connaught Road
LAND PARCEL-2
AREA- 26,175SQM/2.61HA
LAND PARCEL-1
AREA- 3,48,300 SQM/ 34.83HA
Mangalwar
Peth Metro station
Pune Junction Metro
EXISTING TRAFFIC SITUATION ANALYSIS
EXISTING MOVEMENT
MSRTC
Bus Stand
ELEVATED ROAD
STATION BUILDING
Vehicular Movement
Vehicular Access to Station
Existing Road width- 20 m wide
Existing Road width- 20 m wide
Existing Road width- 22 m wide
Pedestrian Access
Bus Movement
AMBEDKAR ROAD
WELLESLEY ROAD
CONNAUGHT ROAD
PUNE RAILWAY STATION ROAD
Pune Municipal
Parking
Parcel Movement
TRANSPORTATION PLANNING AND TRAFFIC SIMULATION
ISSUES
2.One side has a railway officers' colony with a compound wall, and the other side has buildings, a petrol pump, etc.
3. This road has the potential for widening, but the reason behind the congestion is rickshaws and the jam at the intersection near the bus stand (A).
4. This road faces congestion from the exit road from the front entrance of the railway station.
5. There is an overhead bridge over the railway tracks. This bridge reduces the potential for road widening.
6. This road has high traffic volume, with a dargah on one side and Sohrab Hall on the other.
7. The exit from the back entrance of the railway station contributes to traffic and delays. There is no scope for road widening due to the platform.
8. There is no scope for road widening, as there is a chance to utilize the area under the station.
Scope for widening Roads
PROPOSED MASTER PLAN
PROPOSED MASTERPLAN
AMBEDKAR ROAD
CONNAUGHT ROAD
PROPOSED FRONT STATION BUILDING(B+G+2) (110 x 98.5)
PROPOSED ELEVATED ROAD
12M WIDE FOB
AT 6.5M LVL
EXISTING STATION BUILDING
6M WIDE UNDERPASS FOR PASSENGER
PARCEL OFFICE 75M X 60M
NEW BUS STAND + MLCP (86M X 55M)
PROPOSED REAR STATION BUILDING (B+G)
PROPOSED HOLDING AREA BY RITES/RLDA
FOB BY CONSTRUCTION
Club area
PROPOSED MASTERPLAN- DEPARTURE CIRCULATION
AMBEDKAR ROAD
Movement under the proposed ROB through Existing Road
Movement over the bridge
PROPOSED MASTERPLAN- ARRIVAL CIRCULATION
ESP OF PROPOSED YARD REMODELING
ESP OF NEW PROPOSED YARD REMODELING
Platform No. | Existing Length (m) | Proposed Length (m) |
Proposed Platform 7 & 8 | (new) | 630 |
Proposed Platform 9 & 10 | (new) | 750 |
Proposed Platform 11 & 12 | (new) | 600 |
Proposed CSR Platform 13 & 14 | -For Suburban EMU | 330 |
Existing Platforms no 1 to 6
Proposed Platforms no 7 to 12
Future Platforms no 13, 14
Proposed Skywalk
Proposed FOB
Proposed Underpass
Platform No. | Existing Length (m) | Proposed Length (m) |
Platform 1 | 710 | 710 |
Platform 2 & 3 | 532 & 584 | 714 |
Platform 4 & 5 | 442 | 480 |
Platform 6 | 517 | 607 |
AREA AND PARKING REQUIREMENTS
3D VIEWS
Existing 2-way traffic, city road.
FRONT STATION BUILDING , 3 Floors
FUTURE COMMERCIAL, 6 Floors
REAR STATION BUILDING , 1 Floors
FUTURE COMMERCIAL, 6 Floors
Elevation
PROPOSED STATION: ELEVATED ROAD VIEW
FUTURE COMMERCIAL ,6 Floors
FRONT STATION BUILDING
ELEVATED ROAD HAS BEEN PROPOSED FOR PICKUP AND DROP OFF
EXISTING PUNE METRO STATION
ELEVATED DROP OFF
EXISTING PUNE METRO STATION
PROPOSED PICK UP DROP OFF
FUTURE COMMERCIAL, 6 Floors
PEDESTRIAN PLAZA, Width – 12m
6.5 m wide lane
97 m
8 m
Station Entry
PROPOSED REAR STATION VIEW
REAR STATION BUILDING
FUTURE COMMERCIAL ,6 Floors
Station Entry
Commercial Entry/Exit
DROP OFF
Entry
Exit
Capital Expenditure
COST SUMMARY:
SALIENT FEATURES
PROJECT COST – 498.20Cr
MANDATORY STATION DEVELOPMENT
26312 sqm
Platforms Refurbishment
5643 sqm
Elevated Road
6520 sqm
Pedestrian Plaza
(Front of Existing Station Building)
25200 sqm
Front Station Building
( Station Facilities)
1485 sqm
FOB cum Concourse
at 6.5m lvl
10400 sqm
(G + 3) Bus Stand & MLCP
6000 sqm
Rear Station Building
THANK YOU