Norfolk Public Schools
Enrollment Projections and Educational Space
Select Board
October 29, 2019
Historical Context
Over the course of the past five years, the Town of Norfolk has seen an increase in growth and development, with a number of chapter 40B projects proposed and in various states of approval with the town.
School Committee Members, Administrators, Staff, Parents and Citizens have expressed significant concern about the capacity of the schools to manage increased enrollment within our current school buildings.
This is one of the top concerns parents have shared at Parent Leaders meetings and on surveys the district has conducted.
Survey Feedback
Sample Parent Comments
In January of 2017 NPS sent out a survey to parents to solicit feedback that could be used to help us shape goals and inform the development of a new 3-year strategic plan. While the district did not ask any questions about enrollment or space, several parents wrote in comments regarding this concern.
Below are a few samples of comments we received:
“I believe that planning and improving facilities to meet expanding enrollments will be the biggest challenge in 4-6 years. With our current housing increases we will see more children in the schools soon!”
“They keep building new homes in Norfolk. How will the schools be able to accommodate all these kids?”
Formation of the Space Study Committee
The space study committee included the following members:
Jack Hathaway, Town Administrator
Ingrid Allardi, School Superintendent
Linda Balfour, H. Olive Day Principal
Todd Hassett, Business Consultant
Matthew Haffner, Facilities Director
Bob Bullock, Building Inspector
Ann Proto, Recreation Dept. Director
In order to be proactive and to develop a thoughtful and cost-effective plan for managing potential increases in enrollment, the Town of Norfolk and the Norfolk Public Schools established a space study committee in April of 2017.
The committee was responsible for the following tasks:
Current Building Status- H. Olive Day School
Current Building Status- Freeman-Kennedy
The Critical Importance of the Arts and Technology to 21st Century Education
Many experts argue that the skills needed to be successful in the future job market will involve “creative work”- design, development, innovation, creative thinking, collaboration and communication.
Instruction in the Arts and in Technology are now as fundamental as instruction in any other academic discipline.
21st Century Skills: Learning for Life in Our Times by Trilling and Fadel
“We are currently preparing students for jobs that don’t yet exist, using technologies that haven’t been invented, in order to solve problems we don’t even know are problems yet.” Richard Riley, Former US Secretary of Education
*We are projecting that we will have one open classroom for 2020-2021 and will be out of space at FK the following year.
Grade Level | # of Classes 2017 | # of classes 2018 | # of classes 2019 |
3 | 5 | 7 | 7 |
4 | 7 | 5 | 7 |
5 | 5 | 7 | 6 |
6 | 6 | 5 | 6 |
Open Classrooms | 4 | 3 | 1 |
Changes in Enrollment and Space Availability at
Freeman-Kennedy 2017-2019
Current Enrollment/ Class Sizes
Grade | Number of Students | Number of Classes |
Preschool | 70 | 6 |
K | 133* | 7 |
1 | 129* | 7 |
2 | 116* | 6 |
3 | 133* | 5 |
4 | 154* | 7 |
5 | 117* | 6 |
6 | 133* | 6 |
Total | 985 | |
*Indicates that class sizes exceed the target established by School Committee policy
Norfolk Public Schools Average Class Size in Relation to Massachusetts Department of Education Identified Comparison Districts
Elementary Average Class Size |
|
|
|
|
|
Town | 2015-2016 |
| 2016-2017 |
| 2017-2018 |
BERKLEY | 21 | BERKLEY | 22 | BERKLEY | 21 |
PLAINVILLE | 21 | BOXFORD | 21 | WRENTHAM | 21 |
SUDBURY | 20 | MIDDLETON | 21 | SUDBURY | 20 |
WRENTHAM | 20 | TOPSFIELD | 21 | NORFOLK | 20 |
SOUTHBOROUGH | 20 | NORFOLK | 21 | BOXFORD | 19 |
BOXFORD | 18 | SOUTHBOROUGH | 20 | PLAINVILLE | 19 |
CONCORD | 18 | WRENTHAM | 20 | CONCORD | 19 |
MIDDLETON | 18 | PLAINVILLE | 19 | SOUTHBOROUGH | 18 |
TOPSFIELD | 18 | CONCORD | 19 | TOPSFIELD | 18 |
NORFOLK | 18 | SUDBURY | 18 | MIDDLETON | 17 |
LINCOLN | 14-17 | LINCOLN | 17 | LINCOLN | 16 |
Community Needs not Addressed
*The district can not expand either of these programs due to lack of space even though the before/after care program is self-funding and preschool is tuition-based for most children.
Massachusetts Requirements for Early Childhood Education
Early Childhood Special Education services are designed for young children (aged 3-5) with disabilities who need specially designed instruction or related services and whose disability(ies) cause the children to be unable to participate in developmentally appropriate typical preschool activities. School districts are required by law to ensure that developmentally appropriate ESCE programs and services are available. ECSE programs and services ensure that all children with disabilities have a free and appropriate public education (FAPE). (Massachusetts Dept. of Education)
It is the expectation that these students will be educated in inclusive environments with their typically developing peers (see the National Department of Education and The Department of Health and Human Services Joint Policy Statement https://www2.ed.gov/policy/speced/guid/earlylearning/joint-statement-full-text.pdf )
Options Explored By the Space Study Committee
Option 1- Expanding the H. Olive Day School
This option was determined not to be feasible for a number of reasons including:
Renting/ Leasing Portable Classrooms
Option 2- Renting/ Leasing Portable Classrooms
This option was determined not to be fiscally prudent and does not provide a safe, secure environment-
New Construction Option
Option 3- Purchasing/Building a new site to house Special Ed. Offices/ Early Childhood Center
This option offers only a partial solution to the growth challenges-
Expanding the Freeman-Kennedy School
Option 4: Expand the Freeman-Kennedy School
Additional Benefits of Freeman-Kennedy Expansion
A Cost Effective/ Efficient Solution
*Special education secretaries would run the office
at the preschool site, with the Special Education
Director serving as the building administrator.
*The FK nursing staff could provide emergency
services to preschool students if needed.
*Special education secretaries would run the office at the Pre-K site, with the Special Education Director serving as the building administrator.
*The FK nursing staff could provide emergency services to Pre-K students if needed.
Expanding the Freeman-Kennedy School is the most cost effective/ efficient solution to accommodating growth
Benefits to the Town of Norfolk
Preliminary Studies/ Conceptual Design
At the Fall Town Meeting in Nov. of 2017, the Town of Norfolk voted to appropriate funding for the purpose of contracting with an architectural firm to conduct a preliminary feasibility study and to draft a conceptual design plan for expansion at Freeman-Kennedy School.
The Town and the District wanted to determine if an additional wing would enable us to meet the demand for projected enrollment growth. Additionally, the Town and NPS wanted to assess the potential cost of a renovation project.
NPS hired Flansburgh Architects to complete this work. A preliminary conceptual design plan was completed and shared with the School Committee and the Town in October of 2018.
Potential Funding Sources/ Next Steps
MSBA will now consider participating in projects to prevent severe overcrowding expected to result from increased enrollment. In order to be eligible towns/ districts must be able to substantiate growth.
53.16%
Past Reimbursement Rate
Freeman-Kennedy School Building:
Opened on-time
$946,605 under budget
HOD Roof Replacement
Substantial completion achieved by contract deadline
Estimated minimum $200,000 under budget
Benefits of Partnering with MSBA:
MSBA Process
Questions???