Program Gradient
Tim Lawrence
Agenda
Program Gradient
1
2
3
Introduction
Introduction to Program Gradient and the need to move Payroll providers.
Timeline
Review program timeline and come to agreement on proposed dates.
Stakeholders
Review Stakeholders and their responsibilities as well as identify any gaps.
5
6
7
Risks & Opportunities
Review all known risks and discuss mitigation plans.
Resources & Budget
Resource allocation among stakeholders, responsibilities, and budget forecast.
KPI Dashboard
Review KPI Dashboard used to report out Program health
4
Requirements
Align on program requirements and definition of done.
Introduction
Program Gradient
Introduction
The Why
Considerations
Program Gradient
Timeline
Program Gradient
Timeline
Planning & Start
Implement
Deliver
Implement
Program Close
January 2022
February
2022
March
2022
April
2022
Program Gradient
May
2022
3 Month Program Execution
Stakeholders
Program Gradient
Stakeholders
Program Gradient
Internal
Stef Henao
External
Clients
ADP
Protocol Labs
Contractors
1
External
2
Internal
3
Protocol Labs
150+ Labbers
Future Labbers
Tim
Lawrence
Liz Chein
Zach
vN
Requirements
Program Gradient
Requirements & Definition of Done
Program Gradient
User Stories
Key Requirements
Dependencies
Definition of Done
Employees are paid the correct amount on the correct schedule and Global Tax is provided the correct information needed to be compliant in all areas where Labbers are employed.
Risks & Opportunities
Program Gradient
Risks & Opportunities
Program Gradient
Risks & Issues | Potential Impact | Status | Mitigation |
Implementation Timeline Current timeline is for go-live in April 2022 and first payroll run in May 2022. | Delayed Go-Live: We are on track for Go-Live but data conversion errors are putting timeline at risk. | Data conversion errors are behind us, but PL team needs to complete validation by EOM to maintain Program timeline. | Push Go-Live to run payroll on new system for second payroll of May 2022 instead of first. |
Data Conversion Failed or inaccurate data conversion from legacy to go-forward system. | Rework: Data conversion tool provided by 3rd party vendor is creating errors that have to be manually corrected by Labber teams. | Team is currently behind 1 week due to data conversion errors needing manual correction. Other work moving ahead. | If no significant progress by EOW additional Labbers will be temporarily re-assigned to assist current team in data validation. |
Resource Availability Limited resources available from both a Vendor and Labber perspective in terms of number and time zone availability. | Delays: Limited resources and time zone difference between teams could cause a lag in work being completed | Both teams embracing asynchronous work and the time zone difference has not been an issue. | Request additional resources from 3rd Party vendor and/or temporarily assign more PL resources, if needed. |
Resources & Budget
Program Gradient
Resource Allocation
In addition to the Program sponsor and other key stakeholders, this Program will involve 10 resources
Program Gradient
Employee Type | Protocol Labs | 3rd Party Vendor |
FTE |
|
|
Contractor |
|
|
Resource RACI
Program Gradient
R | RESPONSIBLE: Person(s) who completes the task. | Leadership Team | Program Team | External resources | ||||||
A | ACCOUNTABLE: Person(s) who own the end result and approves decisions. | SH | LC | TL | RG | VL | AR | ZvN | Vendor Team | |
C | CONSULTED: Person(s) who reviews the deliverables | |||||||||
I | INFORMED: Person(s) kept in the loop of Program progress | |||||||||
Phase | Task Description | | | | | | | | | |
Planning decisions | Agree budget | R / A | I | A | | | | | | |
Determine the scope of the Program | A / C | I | R / A | I | I | I | I | I | ||
Verify tax rules/regulations | C | R / A | I | I | I | I | C | | ||
Requirements Gathering | A | C | C | C | C | C | R | C | ||
Execution decisions | Program Kick-Off and Weekly Status Reporting | C | C | R / A | C | C | C | C | I | |
Build / Configure | C | | I | C | I | I | A | R / A | ||
Mock Data Conversion | I | | I | I | I | I | C | R / A | ||
Data Validation | I | I | I | R | | I | ||||
UI / UX | A | | I | C | C | C | C | R / A | ||
UAT | A | C | I | C | C | C | C | C | ||
Production Conversion | C | | I | I | I | I | I | R / A | ||
Mock Payroll Run | A | C | I | C | C | C | R / A | C | ||
Post Go-Live | First Payroll Run | A | C | I | C | C | C | R / A | C | |
Budget
Program Gradient
Budget Item | Current Month | Program To Date | ||||
| Budget | Actual | Variance | Budget | Actual | Variance |
Implementation Fees | $50,000 | $65,000 | ($15.000) | $100,000 | $115,000 | ($15,000) |
Variable Expenses | | | | | | |
Compliance Auditor | $10,000 | $3,000 | $7,000 | $10,000 | $3,000 | $7,000 |
Training | $10,000 | $0.00 | $0.00 | $10,000 | $0.00 | $0.00 |
Total Variable Expenses | $20,000 | $3,000 | $7,000 | $20,000 | $3,000 | $7,000 |
Fixed Expenses | | | | | | |
Salaries (PL - Internal) | $60,000 | $60,000 | $0.00 | $300,000 | $120,000 | $0.00 |
KPI Dashboard
Program Gradient
KPI Dashboard
Program Gradient
10
100
Monthly Progress
60%
10
100
Risk Removed
30%
10
100
Overall Program Progress
85%
Thank You!
Please contact tim@protocol.ai or reach out in the #Program-gradient slack channel with any questions or follow up concerns
Program Mascot: Justice