1 of 10

Tonga

Presented by

Taniela Takeifanga

ClimSA

Steering Committee Meeting

2 of 10

  • Tonga Meteorological Service (MEIDECC) is implementing LOA AP_3/35/LOA 5 — 11 national activities totalling USD 679,500 (USD 228,000 TMS-managed) — spanning observation infrastructure, sector climate services, connectivity, and capacity development.
  • Automatic Weather Stations: 2 of 4 installed and operational (Fua'amotu and Matatoa, Tongatapu); Hunga Vava'u and Ha'apai sites scheduled for late 2026.
  • Sea level monitoring: procurement commenced for portable tide stations at Hunga Vava'u and Ha'ano, Ha'apai (USD 60,000).
  • Community connectivity: Starlink deployment for the Niuas endorsed — 10 kits for schools, health and community sites, supporting Early Warnings for All.
  • Climate services: full suite of specialist ToRs delivered — drought early warning, agriculture and maritime calendars, data rescue, COPE translation, and ICT.

Snapshot

Country

3 of 10

Status update

National Activities Under ClimSA

# 

Activity Description 

ROG 

Update for this period 

1

Drought Activities

🟠 AMBER

  • Drought Early Warning Specialist ToR finalised; commencement July 2026.

2

ICT Training for TMS

🟢 GREEN

  • ICT Expert internal ToR produced; expert engagement and training package to follow.

3

Agriculture Sector Products

🟢 GREEN

  • ToR finalised for Vava'u vanilla and kava crop calendars; National TA recruitment in progress.

4

Maritime Services Sector

🟢 GREEN

  • Tide station procurement for Hunga Vava'u and Ha'ano commenced with Director's authorisation; quotations sought from three NZ suppliers. Tide calendar ToR finalised.

5

Weather & Climate Monitoring Network

🟢 GREEN

  • Fua'amotu and Matatoa AWS installed and operational; Milestone 2 evidence submitted to SPREP. Remaining two stations scheduled for late 2026.

6

Climate Data Rescue & Digitization

🟠 AMBER

  • ToR completed for the Data Entry Assistant; recruitment to be confirmed.

4 of 10

Status update

National Activities Under ClimSA

# 

Activity Description 

ROG  (RED/ORANGE/GREEN)

Update for this period 

7

Community Communication Tools & Early Warning

🟢 GREEN

  • Niuas Starlink phase endorsed: 10 kits, supplier selected, SPREP to issue the purchase order and manage subscriptions; deployment 6–20 Oct 2026.

8

Quality Management System for TMS

🟢 GREEN

  • Internal audit programme commenced, beginning with the Observations division — Weather Observations audit conducted 15 July 2026 against the Aerodrome Meteorological Reports Manual (Ed. 3).

9

Education Sector

🟢 GREEN

  • COPE book translation expert ToR prepared (3–4 month assignment) for the Tongan-language COPE book.

10

TMS Communication Strategy & TV Weather Services

🟢 GREEN

  • ToR drafted and to be finalized; recruitment to be confirmed by Late September.

11

National Climate Outlook Forums (NCOFs)

🟠 AMBER

  • Potential dates identified: NCOF Tongatapu 22 October 2026; NCOF Vava'u 12 November 2026. Concept note to follow.

5 of 10

Work Plan

Planning for Year 2026 Implementation

# 

Description 

Timeline

Summary

1

Niuas Starlink deployment

Oct 2026

  • 6–20 Oct: 10 kits: 6 Niuafo'ou, 4 Niuatoputapu/Tafahi; two 4-person TMS teams; schools, hospital and community sites; Phase 1 budget TOP 69,300.

2

Complete AWS network

Oct–Nov 2026

  • Install Hunga Vava'u and Ha'apai stations to complete the 4-station network; triggers final milestone payment.

3

Tide monitoring stations

Q4 2026

  • Procure and deploy portable sea level stations at Hunga Vava'u and Ha'ano (USD 60,000); MOI clearance and community endorsement precede deployment.

4

Specialist onboarding

Jul–Dec 2026

  • Drought Early Warning Specialist commences July 2026; crop/tide calendar to be advertised and 12-month Data Entry Assistant recruited.

6 of 10

Risks

Suggestions for Mitigation

Multi-phase Starlink connectivity (Niuas, Ha'apai, Vava'u — est. TOP 225,200) exceeds the LOA allocation of USD 70,000.

Decision paper submitted to the SC; phased implementation beginning with the Niuas within the current allocation; SPREP to issue the kit purchase order and manage subscriptions directly.

Inter-island shipping and vessel delays to remote deployment sites.

Early cargo bookings and pre-positioning of equipment; field calendar includes contingency; kits tested 2–4 weeks before deployment so warranty claims are resolved onshore.

Supplier quotation validity expiring during approval cycles. Procurement ceilings from Tonga is low to operate these orders.

Align TMS and SPREP approvals ahead of quote expiry; SPREP procures directly where the three-quote requirement is already met.

Equipment standardisation — new sensors and loggers differ from the ~30 systems in the existing national network.

Compatibility, spares and training weighted in technical evaluation; TMS retains full ownership and account credentials for connectivity equipment.

Cyclone-season constraints on outer-island fieldwork.

Deployments scheduled for October–November, ahead of peak season, with combined missions (Starlink, AWS, tide stations) to reduce travel.

Challenges &

Risk Mitigation

7 of 10

  • Community financing model: district and town officers and community councils to agree arrangements to finance and maintain Starlink services once project support ends.

  • TMS retains full ownership of connectivity equipment and Starlink account credentials — avoiding rental models and vendor lock-in.

  • Procurement weighted toward standardisation with the existing national observation network to contain long-term maintenance costs.

  • Capacity embedded within TMS: ICT expertise, data digitisation, and TMS-led installation and technical support for all field infrastructure.

  • Investments aligned to Early Warnings for All 2027 and the Sendai Framework, anchoring continued national and partner support.

Sustainability

Planning for

8 of 10

  • Decision Paper
  • Multi-phase community Starlink connectivity (Niuas → Ha'apai → Vava'u) is estimated at TOP 245,000, exceeding the LOA allocation of USD 70,000.

  • Phase 1 (Niuas, 10 kits) proceeds within the current allocation, with SPREP issuing the purchase order and managing subscriptions directly.

  • Request: the SC's decision on financing the Ha'apai and Vava'u phases with additional allocation or through redistribution of funds within the LOA.

9 of 10

Open for Questions and Discussion

Q&A

Session

Add an image

10 of 10

Thank You