SAP Project System
Unit 6 Exercise 26
Confirm Activities
Confirm more Activities for Project T-100##. An effective option is to enter Confirmations using the Structure Information System.
Use CN41 to Confirm Activities
Project T-100##
Select ALL the Objects
Set Final Confirmation for Activities 0100, 1000, 1200, 1300, 2000, 2100, and 2200
Press ENTER
7 Activities Confirmed
Refresh
Actual Costs udpated
Operation 10 confirmed
MCNF means Manually Confirmed