SAP Plant Maintenance
MEB
Scenario STEPS
MEB Links
1 Notification to Many MOs
If MEB Revision Header is set with MECHANIK
and Task List Work Center is Z0
Therefore change to Work Center T-ME20 in the MEB Generated MO
Task List
PMZ1 Ctr 1
Set with WC Z0
Task List
PMZ2 Ctr 1
Set with WC Z0
Hierarchy TList
PMZ0 Ctr 1
Task List PMZ1, PMZ2
is assigned to the
Hierarchy TList PMZ0
You can use a Maintenance Plan to Call a Notification or Manually Create a Notification with a Hierarchy Task List
In MEB, create a REVISION
Revision number
Drag Notification to Revision
Generate Order
2 MOs about the be generated
SAVE
2 MOs
Work Center is Replaced in the MO
Revision is the key that links the Notification, MEB Header and MOs