1 of 15

Civil Engineering Department

TOPIC-BAR BENDING FABRICATION OF REINFORCEMENT FOR A SLAB

SEMESTER-6TH

BY

Mrs. MANDAKINI MOHANTA / MR BIKASH DAS

(LAB ASST. Civil Engineering Department)

AY:2021-2022

2 of 15

AIM OF THE EXPERIMENT :-

Bar bending and fabrication of reinforcement for a slab.

INSTRUMENTS REQUIRED:-

BAR BENDER

TAPE

STEEL BSRS

BINDING WIRES

BAR CUTTING MACHINE

3 of 15

Slabs

Slab is an important structural element which is constructed to create flat and useful surfaces such as floors, roofs, and ceilings. It is a horizontal structural component, with top and bottom surfaces parallel or near so. Commonly, slabs are supported by beams, columns (concrete or steel), walls, or the ground. The depth of a concrete slab floor is very small compared to its span.

4 of 15

What Is a One Way Slab?

According to IS 456:2000, The ratio of longer span(l) to shorter span(b) which is (L/B) greater than 2 is known as One way slab. In practical, One way slab is supported by only two parallel beams or walls. Normally we don’t use one way slabs often.

5 of 15

What Is a Two Way Slab?

two way street is a street that allows vehicles to travel in both directions. On most two way streets, especially main streets, a line is painted down the middle of the road to remind drivers to stay on their side of the road. Sometimes one portion of a street is two way and the other portion is one way.

6 of 15

One Way Slab Reinforcement Details

To support the bending moment, the main bars are provided in a shorter span.

  • Slab Size = 6000 x 2500 x 150
  • 10mm Main Bars @ 150mm c/c spacing
  • 8mm Distribution Bars @ 150mm c/c Spacing
  • Slab thickness is 150 mm
  • Top Extra Bars – 8mm @ 150 c/c
  • Beam Cover – 25 mm

7 of 15

Bar Bending Schedule for One Way Slab

Step 1 – Find out the total Number of Main Bars & Distribution Bars

  • Number of Main Bars = (Length of Longer Side / Spacing) + 1 = (6000/150)+1 = 41 Numbers
  • Number of Distribution Bars = (Length of Shorter Side / Spacing) + 1 = (2500/150)+1 = 18 Numbers

Step 2 – Find Out the Cutting Length of Bars (Main bar & Distribution bar)

8 of 15

Therefore, Inclined Length D = 0.42 x d

Where, D = Slab thickness – 2 x Clear Cover – Bar Dia = 150-(2*25)-10 = 90 mm

Inclined Length = 0.42 X 90 = 37.8 mm

  • Cutting Length of Main Bar =  Clear Span (Lclear) + (2 x Beam Width) – (2 x Con. Cover) + (1 x Inclined Length) – (45° bend x 2)

= 2500+(2*240)-(2*25)+37.8-20 = 2947.8 mm = 2.95 m

  • Cutting Length of Distribution Bar =  Clear Span (Lclear) – (2 x Con. Cover)= 6000 – 50 = 5950 mm or 5.95 m

9 of 15

  • Number of Top Bars  = Crank Length (L/4) / Spacing + 1 = ((2500/4)/150)+1 x 2 side = 10 Numbers
  • Cutting Length of Top Bars = Same cutting length as distribution bars (5.95 m)

Step 3 – Find out the number of Top Extra Rods (for L/4 length)

Description

Dia of Bar

No of Bars

Cutting Length (m)

Steel weight per metre

Qty (Kg)

Main Bar

10

41

2.95

0.62

74.98 Kg

Distribution Bars

8

18

5.95

0.40

42.84 Kg

Top Extra Bars

10

10

5.95

0.62

36.89 Kg

Total

154.71 Kg

10 of 15

Two Way Slab Reinforcement Details

11 of 15

From Drawing

  • Slab size – 6000 x 5400 x 150
  • 10mm Main Bars @ 150mm C/C spacing
  • 10mm Distribution Bars @ 200mm C/C Spacing
  • Development Length Ld = 40d
  • Top Extra Bar 8mm @ 150 mm c/c (both direction)

Bar Bending Schedule for Two Way Slab

Step 1 – Find out the Total Number of Main Bars & Distribution Bars

  • Number of Main Bars = (Length of Longer Side / Spacing) + 1 = (6000/150)+1 = 41 Numbers
  • Number of Distribution Bars = (Length of Shorter Side / Spacing) + 1 = (5400/150)+1 = 28 Numbers

12 of 15

Step 2 – Find Out the Cutting Length of Bars

  • Cutting Length of Bar = Clear Span (Lclear) + (2 x Beam Width) – (2 x Con. Cover) + (1 x Inclined Length) – (45° bend x 2)

Therefore, Inclined Length D = 0.42 x d

Where, D = Slab thickness – 2 Side Clear Cover – Bar Dia = 150 – (2*25) – 10 = 90 mm

Inclined Length = 0.42 X 90 = 37.8 mm

13 of 15

  • Cutting Length of Main Bar = Clear Span (Lclear) + (2 x Beam Width) – (2 x Con. Cover) + (1 x Inclined Length) – (45° bend x 2)

where 45° bend = 1 d

= 5400 + (2*240) -(2*25) + 37.8 – (10*2) = 5847.8 mm = 5.85 m

  • Cutting Length of Distribution Bar = Clear Span (Lclear) + (2 x Beam Width) – (2 x Con. Cover) + (1 x Inclined Length) – (45° bend x 2)

= 6000 + (2*240) -(2*25) + 37.8 – (10*2) = 6447.8 mm or 6.45 m

Step 3 – Top Extra Rods

a) Number of Top Bars (Longer & Shorter Side)

  • Number of Top Bars (Longer Side) = Crank Length (L/5)/ Spacing = (5400/5)/150 = 7.2 = 7 No.s x 2 side = 14 No.s
  • Number of Top Bars (Shorter Side) = Crank Length (L/5)/ Spacing = (6000/5)/150 = 8 = 8 No.s x 2 side = 16 No.s

b) Cutting length of Top Bars (Longer & Shorter Side)

  • Cutting Length of Top Bars (Longer Side) = 6000 + (2 x Ld) = 6000 + (2 x 40 x 10) = 6800 mm or 6.8 m
  • Cutting Length of Top Bars (shorter Side) = 5400 + (2 x Ld) = 5400 + (2 x 40 x 10) = 6200 mm or 6.2 m

14 of 15

Description

Dia of Bar

No of Bars

Cutting Length (m)

Steel weight per metre

Qty (Kg)

Main Bar

10

41

2.95

0.62

74.98 Kg

Distribution Bars

8

18

5.95

0.40

42.84 Kg

Top Extra Bars

10

10

5.95

0.62

36.89 Kg

Total

154.71 Kg

15 of 15