1 of 25

Soil Nail Walls�Module 5: Testing and Monitoring

Menu:

Introduction

Training support files are available as attachments from the resources link.

2 of 25

Course Map

Menu:

Course Map

Module 1

Module 2

Module 3

Module 4

Module 5

Introduction to Soil Nail Walls

Fundamentals of Soil Nail Walls

Pre-Construction and Construction

Construction Inspection Activities

Testing and Monitoring

Production: Please add relevant icons for each module. Do not use the example shown for Module 5.

Testing and Monitoring

3 of 25

Module Overview

This module will take approximately 45 minutes to complete.

Menu:

Module Overview

Testing

Types of Tests

Monitoring

Testing and Monitoring

4 of 25

Module Learning Outcomes

Upon completion of this module, you should be able to:

  • Explain the importance of testing during and after soil nail wall construction
  • Summarize the types of tests that should be performed as part of soil nail wall construction
  • Describe the importance of monitoring soil nail walls after construction

Menu:

Module Learning Outcomes

Testing and Monitoring

5 of 25

Testing

Menu:

Testing

In the last module…

Write your answer in the provided box and then select submit.

What do you think?

Type your thoughts here:

1a

1a

1b

1b

Submit

Testing and Monitoring

6 of 25

Testing

Menu:

Testing

Verify that soil nails can carry the load without much movement

1b

First, to verify that soil nails can carry the design loads without too much movement

Were you able to think of something? There are…

1b

1b

1c

You can see a typical load test set up …

1a

1c

Testing and Monitoring

7 of 25

Testing

Menu:

Testing

Is the contractor’s method working?

Watch for soil changes

Field conditions may lead to more testing

Another reason it’s important…

Testing is used to verify the contractor’s…

...additional testing may be needed…

If the subsurface conditions…

2c

2d

2b

2a

2a

2b

2c

2d

Testing and Monitoring

8 of 25

Testing

Menu:

Testing

Now, let’s talk about what happens…

Select each question to …

What happens if the test results are not acceptable?

Where are the testing procedures and acceptance criteria described?

What are the inspector’s responsibilities during testing?

Testing and Monitoring

9 of 25

Testing

Menu:

Testing

What happens if the test results are not acceptable?

Where are the testing procedures and acceptance criteria described?

What are the inspector’s responsibilities during testing?

What happens if the test results aren’t acceptable?

  • Contractor must revise their methods
  • Inspector documents and reports the issue
  • Engineer decides how to proceed

Testing and Monitoring

10 of 25

Testing

Menu:

Testing

What happens if the test results are not acceptable?

Where are the testing procedures and acceptance criteria described?

What are the inspector’s responsibilities during testing?

Where are the testing procedures and criteria described?

  • Procedures and criteria are in the project specifications
  • Specs explain how testing done and what counts as “passing”
  • Inspectors use the specs to evaluate test results

SMEs, do you have high quality examples of project specifications?

Testing and Monitoring

11 of 25

Testing

Menu:

Testing

What happens if the test results are not acceptable?

Where are the testing procedures and acceptance criteria described?

What are the inspector’s responsibilities during testing?

What are the inspector’s responsibilities during testing?

  • Observe each load test and log the results
  • Confirm follows contractor submittals and project schedule
  • Suggest which nails to proof test, based on field conditions

Testing and Monitoring

12 of 25

Types of Testing - setup

Menu: [indent]

Setup

…shown in the plan details

The equipment often includes…

Hydraulic jack

Load cell

Dial gauges

1a

1b

1e

1c

1d

SMEs, do you have high quality examples of plan details and corresponding testing images?

Testing and Monitoring

13 of 25

Testing

Menu:

Testing

Now that you’ve seen the setup and equipment…

Select each type to learn…

Proof Tests

Verification Load Tests

Creep Tests

Testing and Monitoring

14 of 25

Verification Load Tests

Menu: [indent]

Verification Load Tests

Proof Tests

Verification Load Tests

Creep Tests

Verification Load Tests

  • Sacrificial nails are for testing only
  • Hydraulic jack applies force to pull the nail away from the wall
  • Nail is tested at higher-than-normal pressure
  • Unbonded length isolate nail from the wall

SMEs, do you have photos or a short video?

Testing and Monitoring

15 of 25

Verification Load Tests

Menu: [indent]

Proof Tests

Proof Tests

Verification Load Tests

Creep Tests

Proof Tests

  • Similar to verification tests, but nails stay in the wall
  • May occur before or early in construction
  • Spot checks continue during construction
  • Uses lower pressure than verification testing
  • Includes an unbonded length

SMEs, do you have photos or a short video?

Testing and Monitoring

16 of 25

Creep Tests

Menu: [indent]

Creep Tests

Proof Tests

Verification Load Tests

Creep Tests

Creep Tests

  • Part of verification or proof testing
  • Test applies steady pressure over time
  • Measures nail movement at intervals
  • Load must hold for 10-60 minutes
  • Too much “creep” signal potential problems

SMEs, do you have results of a creep test that failed and one that passed?

Testing and Monitoring

17 of 25

Monitoring

Menu:

Monitoring

Once a soil nail wall is built…

…regularly check the underdrain outlets…

Without a way for water to escape…or even wall failure, as shown here.

1a

1a

1b

1c

1a

Testing and Monitoring

18 of 25

Monitoring

Menu:

Monitoring

Now that you’ve seen…

Select each key area to learn…

Ground Movement

Signs of Distress

Routine Maintenance

Monitoring after construction

Testing and Monitoring

19 of 25

Monitoring

Menu:[indent]

Ground Movement

Now that you’ve seen…

Select each key area to learn…

Ground Movement

Signs of Distress

Routine Maintenance

Monitoring after construction

Monitor Ground Movement

  • Ground movement is measured with an inclinometer
    • Place in pipe installed deep into wall
    • Tracks horizontal movement of soil
    • Identifies early signs of instability

Testing and Monitoring

20 of 25

Monitoring

Menu:[indent]

Signs of Distress

Now that you’ve seen…

Select each key area to learn…

Ground Movement

Signs of Distress

Routine Maintenance

Monitoring after construction

Monitor Signs of Distress

  • Not all monitoring is done by inspectors
  • Site and maintenance staff need to know what to monitor
    • Cracks in shotcrete
    • Rust on nail heads
    • Wall tilting
  • Long-term performance of soil nail walls depend on routine inspection and monitoring

Nail head with rust

Testing and Monitoring

21 of 25

Monitoring

Menu:[indent]

Routine Maintenance

Now that you’ve seen…

Select each key area to learn…

Ground Movement

Signs of Distress

Routine Maintenance

Monitoring after construction

Routine Maintenance

  • Perform maintenance on a regular basis
  • Clear vegetation near the wall
  • Repair cracks in shotcrete facing
  • Check for wear or corrosion around nail heads
  • Simple checks extend the life of the wall and prevent more serious problems

SMEs, do you have images of any maintenance activities?

Cracks in shotcrete may lead to wall failure

Testing and Monitoring

22 of 25

Limitations of Soil Nail Walls

Read each description and review the photo. Decide which type of test is being shown, then select the correct answer and click Submit

1). This test uses a hydraulic jack to pull on a nail that will remain in the wall.

Menu:

Knowledge Check – Which Test is This?

Knowledge Check – Which Test is This?

Submit

1). This test uses a hydraulic jack to pull on a sacrificial nail that will not be part of the wall.

1). This test measures nail movements at different time intervals. The goal is to ensure the wall doesn’t shift too much.

Proof Test

Verification Load Test

Creep Test

Loads applied up to 200%

Loads applied up to 150%

Proof Test

Verification Load Test

Creep Test

SMEs, do you have images of creep testing?

Proof Test

Verification Load Test

Creep Test

Testing and Monitoring

23 of 25

Read each description and review the photo. Decide which type of test is being shown, then select the correct answer and click Submit

1). This test uses a hydraulic jack to pull on a nail that will remain in the wall.

Menu: [indent]

Debrief– Which Test is This?

Debrief – Which Test is This?

Submit

1). This test uses a hydraulic jack to pull on a sacrificial nail that will not be part of the wall.

1). This test measures nail movements at different time intervals. The goal is to ensure the wall doesn’t shift too much.

Verification Load Test

Loads applied up to 200%

Loads applied up to 150%

Proof Test

SMEs, do you have images of creep testing?

Creep Test

Testing and Monitoring

24 of 25

Learning Outcomes

You should now be able to:

  • Explain the importance of testing during and after soil nail wall construction
  • Summarize the types of tests that should be performed as part of soil nail wall construction
  • Describe the importance of monitoring soil nail walls after construction

Menu:

Learning Outcomes

Testing and Monitoring

25 of 25

Summary

This concludes Module 5: Testing and Monitoring.

Menu:

Module Complete

You have reached the end of this module.

Select the next module to continue.

Testing and Monitoring