Bond Accountability Committee Update
Q1 January 28, 2026
January 28, 2026
Agenda
Introductions
Greg DiLoreto, BAC Committee Chair
Cara Turano, BAC Committee Member
Norm Dowty, BAC Committee Member
Ryan Kinsella, BAC Committee Member
Jonathan Truitt, BAC Committee Member
Chris Dunning, BAC Committee Member
Travis George, BAC Committee Member
Director Christy Splitt, BOE Liaison to the BAC
Jon Franco, Senior Chief of Operations, PPS
Tom Odgers, Chief of Integrated Operations, PPS
Sarah Norman, Executive Director, OSM (PROCEDEO)
TJ Hopkins, Program Director, OSM (PROCEDEO)
Presenters will introduce themselves at the time of their presentation.
3
Public Comment (5:40 pm)��(public comments received via email prior to the meeting will be read aloud)
Bond Program Financial Update (5:50 pm)
February Bond Sale Update: with Michelle Morrison
7
February 10th Bond Sale
NOTE: Bond proceeds may only be spent on capital projects, not district operations or school staffing.
* Sales amounts are the maximum, pending market conditions
8
Major Factors for School District Ratings
9
10
Bond Programs
All Bond Programs Dashboard – As of 12/19/25
2012 Bond Dashboard – As of 12/19/25
2012 Program Financial Status 12/31/2025
2017 Bond Dashboard – As of 12/19/25
2017 Program Financial Status 12/31/2025
2020 Bond Dashboard – As of 12/19/25
2020 Program Financial Status 12/31/2025
2025 Bond Dashboard – As of 12/19/25
2025 Program Financial Status 12/31/2025
Modernizations
Cleveland High School Update
Jefferson High School Update
Risk: Mass timber
Mitigations:
Supply has been diversified since the projects are on same timelines so as not to compete for production.
PPS has approved certain related scopes to be completed through self-perform within the parameters of the contract
The MPG process commits to a 16 week review/approval process by the City
Jefferson High School Update
Ida B. Wells High School Update
Ida B. Wells High School Update
Risk: Building Permit approval timeline is critical path
Mitigations:
Two initial permits are planned - early permit for site prep, underground utilities at 50% CDs, and foundations with second permit for full building at 100% CDS
PPS and Design Team is meeting every two weeks with the City of Portland via the "Major Project Groups" or MPG process to talk through code related topics prior to the first permit application
The MPG process commits to a 16 week review/approval process by the City
34
MAIN ENTRY
COMMONS
ACADEMICS
ATHLETICS
PERFORMING ARTS
BUILDING MASSING
STUDENT COURTYARD
Interior views offer glimpses of activity in the commons
Secured courtyard for outdoor eating and gathering
Shared patio connects to campus and views
Certified Business
Certified Business Update
* Colas/Hoffman Joint Venture
- Colas is a formerly certified firm
- 25% CMGC goal for certified participation
* Currently at 12.12% paid to Certified subcontractors
- 12.77% for consultants
- 5.45% for subcontractors
- 23 of 44 are certified subcontractors/52%
* 17 of the 16 required Career Learning activities have taken place
* Mahlum partnered with Studio Petretti a certified firm
* 0 of the 8 required Career Learning activities have taken place (meeting has been scheduled to get started on this)
*BORA
* 37 of the required 8 Career Learning activities have taken place
Certified Business Update (continued)
Center for Educational Excellence
Center for Educational Excellence (CEE) Update
2025 Program Next Steps
Next Steps 2025 Program
Program Management Update (6:20 pm)
BAC Draft Charter Review with Liz Large (6:30 pm)
BAC General Discussion and Updates (7:15 pm)
Adjourn��Next Meeting:�TBD (April 2026)�(In-Person or Virtual – TBD)