CRITICAL PATH METHOD (CPM)
Dr Adewale Abimbola, FHEA, GMICE.
Aim: Critical Path Method (CPM)
Objectives: At the end of the lesson, the students should be able to:
Aim and Objectives
Introduction
Network Analysis
Figure 1. Nomenclature for compiling the Program Evaluation and Review Technique (March, 2017).
Figure 2. Nomenclature for compiling the Critical Path Method (March, 2017).
The Critical Path Method (CPM) - Definition
The Critical Path Method (CPM) - Definition
The Critical Path Method (CPM)
Figure 2. Nomenclature for compiling the Critical Path Method (March, 2017).
Worked Example
Using the information in the table below;
Activity/Task | Duration (days) | predecessor |
A | 3 | |
B | 8 | A |
C | 10 | A |
D | 12 | C |
E | 15 | B |
F | 9 | D, E |
G | 13 | F |
H | 5 | F |
I | 2 | A |
J | 5 | G, H, I |
Worked Example: Solution
1) Construct the project network or logic.
Activity/Task | Duration (days) | predecessor |
A | 3 | |
B | 8 | A |
C | 10 | A |
D | 12 | C |
E | 15 | B |
F | 9 | D, E |
G | 13 | F |
H | 5 | F |
I | 2 | A |
J | 5 | G, H, I |
Worked Example: Solution
2) Find the expected project completion time.
Complete the forward pass to determine the project completion time of 53 days.
Worked Example: Solution
3) Find the critical path.
Complete the backward pass to confirm the project completion time and determine critical path.
Dependency Relationships – CPM
Benefits – CPM
Limitations– CPM
Self-assessment Task 1 – CPM
Using the information in the table below;
Task | Activity | Days ending | Predecessor |
A | Strip site - topsoil to a depth of 150 mm minimum | 3 | |
B | Excavate to reduced level | 4 | A |
C | Set out house foundations | 2 | B |
D | Excavate foundation trenches (including ducts for services) | 3 | C |
E | Cast concrete to deep strip foundations | 5 | D |
F | Brickwork to dpc (damp proof course) level | 5 | E |
G | Fill cavity below dpc level | 2 | F |
H | Supply and compact hardcore to ground floor slab (including 50 mm sand blinding) | 6 | F,G |
I | Lay dpm (damp proof membrane) | 2 | H |
J | Spread and compact hardcore to ground floor slab | 5 | I |
K | Excavate trenches for drainage/inspection chambers & lay them | 10 | I, J |
L | Test drain for leaks and backfill drainage | 4 | K |
Self-assessment Task 2 – CPM
Using the information in the table below;
Activity/Task | Duration (weeks) | predecessor |
A | 1 | - |
B | 3 | - |
C | 9 | A |
D | 7 | B, G |
E | 4 | C, D |
F | 2 | D |
G | 6 | A |
H | 3 | E |
I | 4 | - |
J | 1 | I |
References/Bibliography