1 of 38

SAP Project System

Internal Labor

Plan and Execute

via Easy Cost Planning

for WBS w/o Network

2 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

3 of 38

Assign Cost Element 615000

Create new Activity Type 4421 (copy from 1421)

4 of 38

Note Cost Element 615000 is part of Value Category 615

5 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

6 of 38

7 of 38

Cost Center

4290

Activity Type

4421

8 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

9 of 38

Cost Center

4290

Activity Type

4421

10 of 38

$100 per Hour

Cost Element

615000

11 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

12 of 38

13 of 38

14 of 38

For Cost Element 615000 Current Actual Cost $600

For Cost Element 615000 Current Plan Cost $0

15 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

16 of 38

Plan Internal Labor for E-99##-1-2 using

Easy Cost Planning

17 of 38

click “Show/Hide Item View” for E-99##-1-2

18 of 38

Item Category “E”

Resource 4290 (Cost Center)

Activity Type 4421

Quantity 2

Press ENTER

19 of 38

Rate from

KP26

Cost Element from 4421 Activity Type Master

20 of 38

Work Center 8000

Plant 1300

BACK and SAVE

21 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

22 of 38

23 of 38

24 of 38

Note Plan Cost of $200 for Cost Element 619000

25 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

26 of 38

27 of 38

Select “Internal Activity Allocation”

28 of 38

29 of 38

Document

900054106 created

30 of 38

  • Prepare Activity Type
  • Create Work Center
  • Prepare Activity Rates
  • Review current Cost Report
  • Plan an Internal Activity using Easy Cost Planning
  • Review updated Cost Report (Plan Cost)
  • Activity Allocation using Easy Cost Planning
  • Review updated Cost Report (Actual Cost)

31 of 38

32 of 38

33 of 38

Previous Actual Cost $600 (now added $200)

34 of 38

Select “Call Up Report” ICON

35 of 38

Note Document number (review Slide 29)

36 of 38

37 of 38

38 of 38

Only CO Posting

Debit WBS

Credit Cost Center/Activity