SAP Project System
Internal Labor
Plan and Execute
via Easy Cost Planning
for WBS w/o Network
Assign Cost Element 615000
Create new Activity Type 4421 (copy from 1421)
Note Cost Element 615000 is part of Value Category 615
Cost Center
4290
Activity Type
4421
Cost Center
4290
Activity Type
4421
$100 per Hour
Cost Element
615000
For Cost Element 615000 Current Actual Cost $600
For Cost Element 615000 Current Plan Cost $0
Plan Internal Labor for E-99##-1-2 using
Easy Cost Planning
click “Show/Hide Item View” for E-99##-1-2
Item Category “E”
Resource 4290 (Cost Center)
Activity Type 4421
Quantity 2
Press ENTER
Rate from
KP26
Cost Element from 4421 Activity Type Master
Work Center 8000
Plant 1300
BACK and SAVE
Note Plan Cost of $200 for Cost Element 619000
Select “Internal Activity Allocation”
Document
900054106 created
Previous Actual Cost $600 (now added $200)
Select “Call Up Report” ICON
Note Document number (review Slide 29)
Only CO Posting
Debit WBS
Credit Cost Center/Activity