SAP Project System

Project WBS w/o Network

Settlement to

Profitability Segment and Cost Center

2 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

3 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

Project E-0088

is created with Project Profile

“0002” Cost Project

4 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

Both WBS level 2 E-0088-1 & E-0088-2 will be Debited with COST from the Goods Receipt of the Account Assignment Purchase Order to the WBS respectively

5 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

Milestones are corrected at Level 2 WBS

E-0088-1 with Milestone#1 at 20%

E-0088-2 with Milestone#2 at 80%

(for Billing Plan)

6 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

Sales Order created at Level 1 WBS E-0088

where the Lower Level WBSs of Level 2 (ie: E-0088-1 & E-0088-2’s Milestones) will be copied as Billing Dates respectively

7 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

For the Level 1 WBS

E-0088

it is set with Billing Element indicator

and therefore the Strategy (assigned to the Project Profile) dictates the Settlement Rule will be the Profitability Segment

8 of 76

E-0088

Project Definition

“0002 Cost Project”

E-0088

E-0088-1

E-0088-2

20%

80%

Billing Element

Account Assignment Element

Account Assignment Element

Settle to

Profitability Segment

Settle to

Cost Center

Settle to

Cost Center

Sales Order

Billing Plan

Non-Stock

PO

Non-Stock

PO

1

2

3

4

5

6

For the Level 2 WBSs

E-0088-1 & E-0088-2

both are set with Account Assignment Element only and the Strategy for the Project Profile dictates the Settlement Receiver to tbe the Responsibility Cost Center respectively

9 of 76

Project Definition E-0088 was created with Project Profile “0002” (Cost Project) in IDES

10 of 76

E-0088

Billing Element

E-0088-1

E-0088-2

Account Assignment Element

11 of 76

Milestone for E-0088-1

Usage PS01

Usage Sales doc date

Billing Percentg 20%

Basic fix date 22.05.2018

12 of 76

Milestone for E-0088-2

Usage PS03

Usage Sales doc date

Billing Percentg 80%

Basic fix date 22.06.2018

13 of 76

Cost Center as Settlement Receive is the

Responsible Cost Center

E-0088-1 4290/1000

E-0088-2 4290/1000

14 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

15 of 76

PO item 10

Account Assignment “P”

WBS E-0088-1

16 of 76

PO item 20

Account Assignment “P”

WBS E-0088-2

17 of 76

GR to charge Debit Cost to these WBS

18 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

19 of 76

use SD Order Type PS1

in IDES

20 of 76

Use Customer

1600 in IDES

Use Material T-20000 in IDES

21 of 76

$10,000 as Selling Price in Conditions TAB

22 of 76

Enter the Level 1

WBS E-0088

23 of 76

In Billing Plan TAB, accept the WBS E-0088

24 of 76

25 of 76

Billing Dates are BLOCKED as Actual Dates are not yet reported

26 of 76

SAVE the

Sales Order

27 of 76

Sales Order

15069

28 of 76

Report Actual Date in

Milestone #1

29 of 76

Report Actual Date in

Milestone #2

SAVE Project

30 of 76

BLOCK indicators should now be RELEASED due to Actual dates

31 of 76

Billing Dates BLOCK indicators Removed by the system after Actual dates reported for the WBS which was assigned with the respective Milestones

32 of 76

Sales Order

Press ENTER

33 of 76

SAVE to Generate Billing documents

34 of 76

Billing Documents generated

35 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

36 of 76

37 of 76

Total PO cost $6000 Debit to Project,

Check “Call Up Report’ ICON

38 of 76

As per the PO,

$2000 debited to E-0088-1

$4000 debited to E-0088-2

39 of 76

Revenue Credit to the Project,

click “Call Up Report” to check details

40 of 76

Revenue Credit to the Project at WBS

E-0088

41 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

42 of 76

Set

Technical Completion

TECO

43 of 76

SAVE TECO status

44 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

45 of 76

Both the Project Profile and the Account Assignment indicators affect the decision of the Settlement Profile & Settlement Rules

46 of 76

Project Profile “0002” was assigned to Strategy “11”

in

IMG

-> Project System

-> Costs

-> Automatic and Periodic Alloc.

-> Settlement

-> Settlement Rule for WBS

-> Assign Strategy to Proj.Profile

47 of 76

If WBS is set with Account Assignment Element, Settlement Profile is 130001 and Settlement Receiver is Cost Center “3”

If WBS is set with Billing Element, Settlement Profile is 130000 and Settlement Receiver is Profitability Segment “1”

48 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

49 of 76

Settlement Receiver yet to be Generated after TECO

50 of 76

51 of 76

52 of 76

E-0088 Receiver is Profitability Segment

E-0088-1 & E-0088-2’s Receiver as Cost Center was generated earlier.

53 of 76

E-0088’s Settlement Receiver is

Profitability Segment

54 of 76

E-0088-1’s Settlement Receiver is

Cost Center 4290 (Responsibility CC)

E-0088-2’s Settlement Receiver is

Cost Center 4290 (Responsibility CC)

55 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

56 of 76

57 of 76

Settle Cost incurred in

Period 5

Settle Revenue incurred in

Period 5

58 of 76

Settle Cost incurred in

Period 6

59 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

60 of 76

Cost Element 651000 & 652000 ORS shows Settlement done

61 of 76

Revenue collected in WBS E-0088

Settled to Profitability Segment

62 of 76

63 of 76

Check COPA

64 of 76

COPA Characteristics

65 of 76

COPA�Value fields

66 of 76

Cost collected in WBS E-0088-1

Settled to Cost Center

67 of 76

68 of 76

69 of 76

Debit Cost Center

Credit WBS

70 of 76

Cost collected in WBS E-0088-2

Settled to Cost Center

71 of 76

72 of 76

73 of 76

Debit Cost Center

Credit WBS

74 of 76

  • Project Structure of WBS w/o Network
  • Purchase Order and GR to Debit Cost to WBS E-0088-1 & E-0088-2
  • Sales Order to Credit Revenue to WBS E-0088
  • Check Cost/Revenue Posted to the Project
  • TECO Project
  • Understanding Settlement Receivers in PS
  • Generate Settlement Receiver
  • Settlement
  • Review Settlement Results
  • Close Project

75 of 76

Perform Business Closing

76 of 76

Status CLSD

Business Closing